23RD & 29TH AVENUE OC OPERATION AND

SAFETY IMPROVEMENTS
MAJOR ELEMENTS:
REMOVE AND RECONSTRUCT 23RD
AVENUE OC AND 29TH AVENUE OC
(INCREASE VERTICAL CLEARANCE)
IMPROVE NB ON/OFF-RAMPS AND
SB OFF-RAMP
CONSTRUCT SOUNDWALLS AND
RETAINING WALLS
RECONSTRUCT DRAINAGE
SYSTEMS

23RD & 29TH AVENUE OC OPERATION AND


SAFETY IMPROVEMENTS
Stage Construction
Stage 1 July 2014 to May 2015
Relocate Lisbon Ave on-ramp to 29th Avenue
Construct majority of sound wall

Stage 2 April 2015 to October 2016


Reconstruct 29th Ave overcrossing

Stage 3 July 2016 to March 2017


Construct 29th Ave northbound off ramp structure and roundabout

Stage 4 March 2017 to April 2018


Reconstruct 23rd Ave overcrossing
Maintaining EB Traffic on Southerly Structure

Stage 5 April 2018 to September 2018


Open New 23rd Ave OC and Demo Southerly Structure

Reconstruct 23rd Ave northbound off ramp


Complete sound wall construction

23RD & 29TH AVENUE OC OPERATION AND


SAFETY IMPROVEMENTS

Stage 1 Northbound Onramp &


Soundwall

Stage 1 Northbound Onramp &


Soundwall

27th AVE. - Sidewalk Construction