Strabag Oman LLC, Post Box No.

444, Muscat, Postal Code 100, Sultanate of Oman

DUALIZATION OF IBRI - AD DARIZ MISKIN ROAD


OPTION 1 (Roundabouts), alternative II - (km 0+000 to km 34+000)
New Rate Built Granular subbase course, class B (upto 100mm thick)
Item No
New

Description

Quantity

H.rock cutting in Muscat Hills(H.rock by 30% of total


cutting)

46,200

Unit

Rate (R.O)

M3

6.550

Amount R.O)
302,610.000

Material

Sl No

Description

Factor

Total Qty

Unit

Rate (R.O)

Amount R.O)

No.

Total Qty

Unit

Rate (R.O)

Amount R.O)

Total Material Cost per sq.m


B

Plant and equipment

Sl No

Description

1902.20

Rock breaker Excavator

10

Hr

18.000

900.000

1902.29

Dump truck from 10 tonne to 15 tonne

10

Hr

8.000

320.000

Subtotal

1220.000

Out put 250 Cu.m per day


Total plant Cost per cu.m

Sl No

250.000
4.880

Labour cost

Description

Nos

Total Qty

Unit

Rate (R.O)

Foreman (Rate including accomodation,food


& transportation)

10

Hr

1.900

19.000

Semi skilled Labour(Rate including


accomodation,food & transportation)

10

Hr

1.000

20.000

Out put 250 Cu.m per day

250.000

Sub total

Amount R.O)

39.000

Total Labour cost per cu.m

0.156

Total Cost per cu.m

5.036

add contractor profite by 30%

6.547
6.550

say