Professional Documents
Culture Documents
WWW.TOCWEEKLY.COM
PAGE 1
WWW.TOCWEEKLY.COM
The sooner we start the sooner
we will finish
This is valid if and only if there is no other work
to do. If I can dedicate my time to solely one
thing then of course the sooner I start the
sooner I will finish it. This is not valid when there
are multiple projects for resources to work on,
or multiple tasks for a resource to do in a project. Having too much work being done in parallel just extends the lead time to complete everything! There are various exercises that demonstrate this easily the paper tearing exercise,
the bead game, the A 1 - ..B 2 exercise, etc.
resources
PAGE 2
WWW.TOCWEEKLY.COM
The more detailed and the precise the project plan the easier it is to control
Ask most managers how they can gain more
control and more predictability over a system
and they will tell you we break the system
down into smaller parts and give each part a
local target and if we still get surprises then
we break it down further, etc. In an attempt to
tackle the uncertainty and complexity they actually make the management of the system more
complex and react to every variation creating
even more noise than exists normally and fuelling disharmony between owners of the parts.
This is evident in all types of business environment from Governments to a single project.
In a project plan, the tendency is to break the
tasks down into many hundreds or even thousands of tasks, detailing every possible dependency on the assumption that we can actually plan the way reality will turn out. In some
cases, even to the extent of planning for every
possible eventuality and recording this in the
project plan. Planning in hundreds of tasks
even for a project such as building a North Sea
oil rig is overkill and does little to aid the actual
execution. It draws resources into having to
constantly re-plan to reflect reality. When this
becomes too onerous then it is no longer done
properly and in fact the project is out of control.
It is often about trying to build the whole of the
work content into the project plan, when really
the project plan should be the basis for managing the flow of the project. Answering the questions are we going to finish on time? and is
corrective action needed?
Critical Chain project plans are built at a level
and in enough detail to adequately monitor the
flow of the project and to minimise re-planning.
As such they provide much greater control to
the project manager.
Including safety at a task level is the best
way to protect a project
When each task owner includes safety in their
estimated durations they are in fact hurting the
project and setting it up to fail. We understand
why people do this because they want to be
reliable, they want to meet their local milestone
PAGE 3
WWW.TOCWEEKLY.COM
fund. This way there is enough safety to cover
for most uncertainties.
% complete is the best estimate of the
progress of a task [task content and task
duration are equivalents]
Why is it that very often when we ask someone
who is working on a task - that had say an
original estimated duration of 10 days and we
are asking them on day 11 what is your %
completion; and they tell us 90% - and it then
takes them another 5 days to finish? The answer must be that everyone is equating the
content with the duration which is obviously not
valid.
The most important thing for us to know, in relation to the managing the flow of the project is
the most current estimate of the remaining duration to complete the task. This has no relation
to the original estimate or the work completed
so far. The estimated remaining duration is a
professional estimate based on all currently
known data. This is the best estimate we can
get and is how we report on CCPM project
tasks.
The most eective way to synchronise
execution is through many meetings
In many companies that have what are thought
of as large projects or organisations that have
many medium sized projects another approach
to dealing with the inherent uncertainty and
complexity that seems to constantly exist is to
hold frequent alignment or synchronisation
meetings. They might not be called by these
names but this is their intent. This involves hundreds of hours of management time which in
itself is a scarce resource. The meetings seek to
deal with the variation and the resultant priorities. Often these meetings do help but many
times they cause additional confusion and shifting of focus to every small variation that is happening. They often have to spend time on what
has been done on previously discussed issues.
In a prestigious car company we saw this first
hand in their daily meetings. The trivia was impressive. Often the issues needed senior management to get involved to sort out conflicting
needs. None of this really helps the critical flows
of the project.
PAGE 4
WWW.TOCWEEKLY.COM
the first people to change and they drive the
implementation themselves proactively. They get
involved in ensuring that the new rules are followed and actively provide support for difficult
situations. They help in the initial stages to
check the new behaviours are happening and if
not take action to redress the situation. Sponsorship is necessary but not sufficient to
achieve systemic change.
Conclusion
If when you read the top ten you thought that
makes sense to me then you better think
again. If you can understand how these assumptions and paradigms are possibly erroneous then you should explore more how they
impact your organisation. Test them out by asking other people dont do them all together
do them one at a time.
CCPM tackles all these paradigms in that way
it is simple; even common sense. Unfortunately
common sense is rarely common practice!
Martin Powell.
http://www.TOC-Goldratt.com/Top-10-PM-Tools
PAGE 5