You should use the 2004 Edition of the CSI Master Format to answer the following questions:

1. What is the division name and number where you would find Instructions to Bidders?
Division00ProcurementandContractingRequirements(002113)
2. What is the division name and number where you would find custom, built in, bamboo
millwork?
Division09Finishes(096223)
3. What is the division name and number where you would find Auto-operated glass doors?
Division08Openings
4. What is the division name number where you would find specifications on an escalator?
Division14ConveyingEquipment
For items 5 -27 list the SIX digit CSI code associated with each of the following items of work:
5. 02 40 00: DEMOLITION AND STRUCTURE MOVING
6. 03 41 00: Precast Structural Concrete
7. 04 22 00: Concrete Unit Masonry
8. 05 12 13: Architecturally-Exposed Structural Steel Framing
9. 06 41 16: Plastic -Laminate-Clad Architectural Cabinets
10. 07 00 00: THERMAL AND MOISTURE PROTECTION
11. 08 06 71: Door Hardware Schedule
12. 08 44 19: Glazed Stainless-Steel Curtain Walls
13. 09 68 13: Tile Carpeting
14. 09 91 13: Exterior Painting
15. 22 01 00: Operation and Maintenance of Plumbing
16. 23 30 00: HVAC AIR DISTRIBUTION
17. 23 00 00: Heating, Ventilating, & Air-Conditioning
18. 26 51 13: Interior Lighting Fixtures, Lamps, And Ballasts
19. 27 00 00: Communications
20. 27 13 00: Communications Backbone Cabling
21. 31 62 16 16: Steel H Piles
22. 31 60 00: SPECIAL FOUNDATIONS AND LOAD-BEARING ELEMENTS 31 62 00
Driven Piles
23. 32 00 00: Exterior Improvements
24. 34 00 00: TRANSPORTATION
25. 48 00 00: ELECTRICAL POWER GENERATION
26. 48 16 00: Geothermal Energy Electrical Power Generation Equipment
27. 48 12 13: Nuclear Reactors
28. Under the old (1995) CSI format, which many architects and engineers still use, all electrical
work would be found in division?
Division16Electrical

29. Which of the following would NOT be considered a standard type of construction contract?
a. Lump Sum
b. GMP
c. Cost of Work plus Fee
d. Low Monthly Rates
30. After a thorough review and investigation of the contract documents, if a conflict still exists
between the drawing and specifications, which takes precedence?
a. the drawings
b. the specifications

You might also like