Division 01 – General Requirements

01 45 00 Structural Testing and Inspection


01 89 00 Site Construction Performance Requirements
01 91 00 General Commissioning Requirements
01 91 10 Functional Performance Testing (FPT) Procedures

Division 02 – Existing Conditions

02 41 13 Selective Site Demo and Removal

Division 03 – Concrete

03 10 00 Concrete Formwork
03 20 00 Concrete Reinforcement
03 30 00 Cast-In-Place Concrete
03 38 00 Post-Tensioned Concrete
03 35 43 Polished Concrete Finishing
03 54 16 Hydraulic Cement Underlayment

Division 04 - Masonry

04 20 00 Unit Masonry

Division 05 - Metals

05 12 00 Steel
05 12 50 Architectural Exposed Structural Steel
05 30 00 Steel Deck
05 50 00 Metal Fabrications
05 51 13 Metal Pan Stairs
05 52 13 Pipe and Tube Railings
05 52 13 Metal Railings (Landscape)
05 70 00 Decorative Metal
05 73 00 Decorative Metal Railings

Division 06 - Wood, Plastics, and Composites

06 10 00 Rough Carpentry
06 41 16 Interior Architectural Woodwork
06 64 00 Plastic Paneling

Division 07 - Thermal and Moisture Protection

07 13 26 Self-Adhering Sheet Waterproofing


07 14 16 Cold Fluid-Applied Waterproofing
07 16 16 Crystalline Waterproofing
07 21 00 Thermal Insulation
07 26 26 Below-Grade Vapor Retarders
07 27 26 Fluid-Applied Membrane Air Barriers
07 41 13 Formed Metal Roof Panels
07 42 13 Metal Composite Material Wall Panels

TABLE OF CONTENTS
TOC - 1
Columbia Tennis PERKINS+WILL
Columbia University, New York, NY PROJECT #159013.001
Design Development May 29, 2020

07 42 16 Insulated Core Metal Wall Panel


07 42 26 Metal Wall Panel
07 42 41 Composite Framing Support (CFS) Clip System
07 54 23 Thermoplastic Polyolefin (TPO) Roofing
07 62 00 Sheet Metal Flashing and Trim
07 81 00 Applied Fireproofing
07 84 13 Penetration Firestopping
07 84 46 Fire-Resistive Joint Systems
07 92 00 Joint Sealants

Division 08 - Openings

08 11 13 Hollow Metal Doors and Frames


08 14 16 Flush Wood Doors
08 31 13 Access Doors and Frames
08 39 60 Removable Floor Barrier
08 41 26 All-Glass Storefronts
08 44 13 Glazed Aluminum Wall Assemblies
08 45 13 Structured Polycarbonate Wall Panel Assemblies
08 71 00 Door Hardware
08 80 00 Glazing
08 81 13 Decorative Film Overlay for Glazing
08 83 00 Mirrors
08 95 43 Flood Vents

Division 09 - Finishes

09 21 16 Gypsum Board Shaft Wall Assemblies


09 22 16 Non-Structural Metal Framing
09 29 00 Gypsum Board
09 30 13 Tiling
09 51 23 Acoustical Tile Ceilings
09 54 23 Linear Metal Ceilings
09 65 13 Resilient Base and Accessories
09 65 66 Resilient Athletic Flooring
09 68 13 Tile Carpeting
09 72 00 Wall Coverings
09 91 23 Interior Painting
09 96 00 High-Performance Coatings
09 97 13 Insulating Steel Coatings

Division 10 - Specialties

10 11 00 Visual Display Surfaces


10 21 13 Toilet Compartments
10 21 23 Cubicles
10 22 39 Hanging Felt Baffles
10 26 00 Wall and Door Protection
10 44 00 Fire Protection Specialties
10 51 00 Solid Surface Lockers
10 81 00 Toilet Accessories

Division 12 - Furnishings

TABLE OF CONTENTS
TOC - 2
Columbia Tennis PERKINS+WILL
Columbia University, New York, NY PROJECT #159013.001
Design Development May 29, 2020

12 24 13 Roller Window Shades


12 48 13 Entrance Floor Mats and Frames
12 48 16 Entrance Floor Grilles
12 93 00 Site Furnishings

Division 14 – Conveying Equipment

14 21 00 Electric Traction Elevators

Division 21 - Fire Protection

21 05 00 Common Work Results for Fire Suppression


21 05 04 Corrosion Protection of Fire Protection System From Humid Salt Laden
Outdoor Air
21 07 00 Fire Suppression System Insulation
21 08 00 Commissioning Of Fire Suppression System
21 08 01 Commissioning Agent Requirements
21 13 00 Fire Suppression Sprinkler Systems
21 90 00 Fire Protection System Closeout
Division 22 - Plumbing

22 05 00 Common Work Results for Plumbing


22 05 04 Corrosion Protection from Humid Salt Laden Outdoor Air
22 05 13 Plumbing Motors And Starters
22 05 23 Plumbing Valves
22 05 29 Plumbing Pipe Supports and Anchors
22 05 30 Electronic Speed Controllers
22 05 49 Plumbing Seismic Restraints
22 05 53 Plumbing Identification
22 05 93 Test-Adjust-Balance
22 07 00 Plumbing Insulation
22 08 00 Plumbing Systems Commissioning
22 08 01 Commissioning Agent Requirements
22 10 00 Plumbing Piping and Accessories
22 21 23 Natural Gas Systems
22 30 00 Plumbing Equipment
22 40 00 Plumbing Fixtures
22 90 00 Project Closeout

Division 23 - Mechanical

23 05 01 Mechanical and Electrical Coordination


23 05 02 Basic Mechanical Requirements
23 05 03 Basic Mechanical Materials and Methods
23 05 04 Corrosion Protection from Humid Salt-Laden Outdoor Air
23 05 13 Motors and Starters
23 05 23 Valves
23 05 29 Pipe Supports and Anchors
23 05 30 Electronic Speed Controllers
23 05 48 Vibration Control
23 05 53 Mechanical Identification
23 05 93 Test-Adjust-Balance
23 07 00 Mechanical Insulation
23 08 00 Commissioning of Mechanical Systems

TABLE OF CONTENTS
TOC - 3
Columbia Tennis PERKINS+WILL
Columbia University, New York, NY PROJECT #159013.001
Design Development May 29, 2020

23 08 01 Building Automation System (BAS) Commissioning


23 09 00 Building Automation and Automatic Temperature Control Systems
23 23 00 Refrigerant Piping
23 31 13 Ductwork
23 31 14 Duct Cleaning
23 33 00 Ductwork Accessories
23 34 00 Fans
23 36 00 Air Terminal Units
23 37 00 Air Inlets and Outlets
23 40 00 Air Cleaning
23 54 00 Furnaces
23 62 13 Air-Cooled Condensing Units
23 73 13 Air Handling Units
23 74 00 Packaged Rooftop air Conditioning Units
23 75 00 Outdoor Air Handling Units (Modular Or Semi-Custom)
23 81 26 Split System Dx Air Conditioning System
23 82 16 Air Coils
23 82 19 Room Terminal Units
23 82 39 Heating Terminal Units
23 84 19 Desiccant Air Handling Units With Coils
23 90 00 Project Closeout

Division 26 - Electrical

26 05 01 Mechanical and Electrical Coordination


26 05 02 Electrical Requirements
26 05 03 Testing
26 05 05 Manufacturers
26 05 06 Basic Material and Methods
26 05 10 Project Closeout
26 05 11 Electric Service System
26 05 19 Wires and Cables
26 05 26 Grounding
26 05 29 Supporting Devices
26 05 33 Raceways
26 05 34 Electrical Boxes and Fittings
26 05 43 Underground Service and Manholes
26 05 48 Noise and Vibration Control for Electrical Systems
26 05 49 Seismic Design
26 05 53 Electrical Identification
26 09 43 Network Lighting Control
26 22 00 Low Voltage Transformers
26 24 13 Switchboards
26 24 15 Service Entrance Switchboard
26 24 16 Panelboards
26 27 26 Wiring Devices
26 28 16 Disconnects, Fuses and Enclosed Breakers
26 29 13 Motor Controllers
26 41 14 Lightning Protection System (E.S.E)
26 43 13 Surge Protection Devices
26 51 00 Lighting Fixtures
26 56 68 Sports Lighting Fixtures - LED

Division 27 - Telecommunications

TABLE OF CONTENTS
TOC - 4
Columbia Tennis PERKINS+WILL
Columbia University, New York, NY PROJECT #159013.001
Design Development May 29, 2020

27 05 00 Common Work Results for Communications


27 05 26 Telecommunications Grounding and Bonding
27 05 33 Telecommunications Raceways and Boxes
27 05 36 Cable Trays
27 11 00 Communications Equipment Room Fit-Out
27 13 13 Communications Copper Backbone Cabling
27 13 23 Communications Optical Fiber Backbone Cabling
27 15 00 Communications Horizontal Cabling
27 33 53 Technology Uninterruptable Power Supply (UPS)
27 41 00 Audio Video Systems
27 51 00 Public Address and Music System
27 51 16 Public Address Systems
28 00 00 Security Systems - General
28 00 01 Security System Monitoring and Controls
28 13 00 Access Controls
28 23 00 IP Video Surveillance System
28 31 00 Fire Alarm System

Division 31 – Earthwork

31 20 00 Earth Moving
31 20 10 Earthwork (For Site Utilities)

Division 32 - Exterior Improvements

32 12 43 Porous Flexible Paving


32 13 13 Concrete Paving
32 13 73 Paving Joint Sealants
32 14 00 Unit Paving
32 14 43 Porous Unit Paving
32 17 13 Parking Bumpers
32 31 16 Fences and Gates
32 32 13 Cast-inPlace Concrete Retaining Walls
32 91 00 Planting Soils
32 92 00 Turf and Grasses
32 93 00 Plants

Division 33 - Utilities

33 39 00 Sanitary Utility Sewerage Structures


33 40 00 Storm Drainage Utilities
33 40 20 Warning And Tracer Tape

Appendix

Appendix A Fixture Cuts

END OF TOC