Daily Report-19 04-02-2012
Daily Report-19 04-02-2012
Site
: HAYDARIA
Report No. : 19
Date
04/02/2012
Man power
Admin.
1
Engineer
5
Surveyor
1
Admin.
Engineer
Surveyor
Sub Contractor
Eng.
in
power
charge
Pr
en
t
Man
Max:16 Min: 3
Eq
ui
pm
Section
No.
Weather: Sunny
Civil works
Mobilization
1
2
3
4
5
6
supplying sub base for storage area ( today are supplied 170 cubic
meters ) remaining about 3360 cubic meters
spreading sub base for storage area
wetting & compacting for storage area .
compacting the roads sub base .
45
surveyor karrar
Eng.Wissam
starting civil work for building toilets in camp area (excavation works and sub base
spreading for toilet building base )
cleaning the camp foundation by water.
40
30
100
5
70
soil investigation
level device
shovel
water tank
Eng.Shawkat
1
2
3
85
5
documents
Eng.Ali Hanoon
1
2
civil works
continue supplying sub base for storage area
spreading and leveling sub base for storage area
cleaning and prepare the site foundation .
continue building works for toilets ( excavation, spreading ,wetting and compacting sub base )
.
electrical works
waiting for receiving remaining materials of 11KV feeding line from contractor
continue civil works for installing 11KV line from tire plant to site area by contractor
Foreman
0
technician
1
worker
2
Total
10
Foreman
technician
worker
Total
0
0
0
16 Min: 3
en
t
Progress
Plan
Actual
start
finish
start
1/23/2012
2/4/2012
1/23/2012
1/25/2012
12/28/2011
1/26/2012
2/6/2012
1/20/2012
2/4/2012
1/25/2012
12/28/2012
1/26/2012
1/28/2012
2/12/2012
2/4/2012
2/3/2012
2/5/2012
2/3/2012
12/9/2011
2/15/2012
12/9/2011
finish
2/4/2012
1/3/2012
1/25/2012
1/4/2012
1/26/2012
2/18/2012
2/4/2012