You are on page 1of 14

Daily Site Report

Site
: HAYDARIA
Report No. : 19
Date
04/02/2012

Man power

Admin.
1

Engineer
5

Surveyor
1

Admin.

Engineer

Surveyor

Sub Contractor

Eng.
in

power

charge

Pr

en
t

Job Description & Comment

Man

Max:16 Min: 3
Eq
ui
pm

Section

No.

Weather: Sunny

Civil works
Mobilization
1
2
3
4
5
6

supplying sub base for storage area ( today are supplied 170 cubic
meters ) remaining about 3360 cubic meters
spreading sub base for storage area
wetting & compacting for storage area .
compacting the roads sub base .

45
surveyor karrar
Eng.Wissam

starting civil work for building toilets in camp area (excavation works and sub base
spreading for toilet building base )
cleaning the camp foundation by water.

40
30
100
5
70

soil investigation

electrical work (11 kv feeding line )

level device
shovel
water tank

Eng.Shawkat

1
2
3

receiving materials for installing 11KV feeding line to site


( contractor promised that he will complete supplying ) . A warn letter had sent from site manager
to contractor to commit to his responsibility according the contract paragraphs
starting civil works for installing 11KV line ( determine and excavation work for poles bases ) on the route from
tire planet to site area .
preparation works for sample poles testing by MOE / QC department in Baghdad
as supposed the commission from Najaf Electricity Distribution Director will come
to site in order to take the samples to Baghdad.

85
5

gas line supplying installing


the gas pipe had laid under connected road between Najaf Refinery and main road ( Karbala- Najaf) towards the unit area.

documents

Eng.Ali Hanoon

Visits and Meetings

Site Manager Comment

installing caravans camp had delayed to next Monday according t


from prefabricated buildings company in Amman .

Next day works


1
2
3
4

1
2

civil works
continue supplying sub base for storage area
spreading and leveling sub base for storage area
cleaning and prepare the site foundation .
continue building works for toilets ( excavation, spreading ,wetting and compacting sub base )
.

electrical works
waiting for receiving remaining materials of 11KV feeding line from contractor
continue civil works for installing 11KV line from tire plant to site area by contractor

Foreman
0

technician
1

worker
2

Total
10

Foreman

technician

worker

Total
0
0
0

16 Min: 3

en
t

Progress

Plan

Actual

start

finish

start

1/23/2012

2/4/2012

1/23/2012

1/25/2012
12/28/2011
1/26/2012

2/6/2012
1/20/2012
2/4/2012

1/25/2012
12/28/2012
1/26/2012

1/28/2012

2/12/2012

2/4/2012

2/3/2012

2/5/2012

2/3/2012

12/9/2011

2/15/2012

12/9/2011

finish

2/4/2012

1/3/2012

1/25/2012

1/4/2012

1/26/2012

2/18/2012

2/4/2012

Site Manager Comments

elayed to next Monday according to order


ompany in Amman .

You might also like