Professional Documents
Culture Documents
&
progress report
Trade
No.
Hrs
No.
Trade
Day:Thursday
No.
Hrs
10
A.P.M
10
17 Elect.Foreman
C.M
10
18 Plumber
10
10
Technical engineer
10
19 Electricain
21
10
Civil Engineer
15
10
20 Surveyor
10
10
Elect.Engineer
10
21 Surveyor Helper
12
10
Mech. Engineer
10
22 Civil Foreman
14
10
Q.C. Engineer
10
23 Driver
10
10
Planning Engineer
10
24 Equip.Foreman
10
No.
Administrator
10
25 IT. Technician
10
10 Accountant
10
26 LABOR
82
10
11 Doc. Controller
10
27 Tea boy
10
12 Safety Engineer
10
28 Mech.Foreman
10
10
Subcontractors
29 (Man Power)
144
10
13
Safety Officer
14
Weather
Temperature
15 Security Guard
11
10
10
Minimum: 14C
Material
Name
Dusty
Maximum:27C
Qty.
Unit
Description of works do
Organization
Works
No.
Blasting Chiller B
S-PRC-SS-02(F19) REV 1
Windy
Visitors on site
No.
Rainy
10
384
Cloudy
Delivery of materials
Total
Sunny
14 Security officer
16 Male nurse
Page 1 of 5
Remarks
13/82 labour with surveyors
10/82 labour with safety
49/82 labour site works
Bore holes balance 15 in Chiller B
Total excavation volume
Submission:
Project Manager:
S-PRC-SS-02(F19) REV 1
Page 2 of 5
Signature:
Engineer:
Ref.:
FTCO
Contractor:
Sheet
No.
Category
No.
Hrs
No.
35
10
17
18
Excavator
Bobcat
10
Bulldozer (D9R)
10
Tower lights
106
10
Generator (150kva)
27
10
Forklift (3 Ton)
10
Compactor
10
Pick-up (ISUZU)
10
10
Bus (COASTER)
10
10
Mobile Crane
10
11
Dump Truck-BIG
40
12
12
Dump Truck-Small
10
10
13
Water tanker
14
GPS (LAICA)
10
15
TOTAL STATION
10
16
LEVEL (LAICA)
10
16
S-PRC-SS-02(F19) REV 1
No.
Hrs
Drilling Machine
10
Grader
10
10
Total Excavation
Category
QTY
UNIT
500
12800
4000
105600
Page 3 of 5
10%
Station0 to Station100)
70%
350
Count
8384
vation volume
473750
Noted:
Signed by:
S-PRC-SS-02(F19) REV 1
Signature:
Page 4 of 5
Trade
NO
Excavation
Eng
Forman
Labour
Truck Drivers
Heavy equipement operators
water tanker Driver
0
2
10
50
46
16
Concrete works
Eng
Forman
Steel fixer
Labour
Blasting team
Operators
Forman Supervisor
4
1
144