Professional Documents
Culture Documents
Oleh :
Dr. Eng. Rony Seto Wibowo
Maintenance scheduling
Introduction to Distribution
Systems
Typical Distribution Systems:
Radial
< 100 MVA
< 69 kV class
Distributed load
20-30% Unbalance
Both 1 & 3 phase
Introduction to Distribution
Systems
Sec t i on
W CA45
Dist ributi on L i ne
N. O. Swit c h
N. C. Swit c h
Rec l ose r
(t o T hre e
L ake s)
Sec t i onal i z er
Fuse
Fee der Bounda ry
(t o Sul t an)
(t o Sul t an)
W oods Cre ek
Subst at i on
Background
Typical Distribution Systems
Supply Transformers are
housed in
Distribution Substations
A Planning Scenario includes:
Each substation supplies:
4 to 14 Feeders
About 10 Substations
That is, about 100
Feeders
System under study has:
Trees
Squirrels
Lightning
Wind
etc.
Strategies
Strategies
Operation
New systems
Expansion of existing system
Upgrading of existing facilities
MTTF m
MTTR r
MTBF
Mean Time Between Failure
MTBF T m r
T waktu siklus rata rata
m waktu rata rata gangguan
r waktu rata rata perbaikan
Model Komponen
Type of Failure Rates
A = Active Failure Rate (Failure / Year)
Bentuk kegagalan komponen yang menyebabkan
beroperasinya zona pengaman primer di sekitar
komponen yang mengalami kegagalan tersebut.
Jika kegagalan aktif telah terisolasi maka breaker akan
menutup kembali (reclosed)
Contoh: Kegagalan short circuit
Model Komponen
Type of Failure Rates
p = Passive Failure Rate (Failure / Year)
Bentuk
kegagalan
komponen
yang
tidak
menyebabkan beroperasinya breaker pengaman dan tidak
berpengaruh terhadap komponen sehat yang tersisa,
pembukaan jaringan dan membukanya breaker karena
kesalahan operasi yang tidak meyebabkan pemadaman.
Kegagalan dari komponen itu sendiri dan akan
berakhir setelah diperbaiki atau dilakukan penggantian
Reliability Index
Reliability Index
Reliability Index
Interrupted Energy Assesment Rate Index pada Load
Point, IEARi ($/kWhr):
ri N i N lpU lp
NT
N lp
Reliability Index
Historical assessment:
Total Number of Customer Interruptions
SAIFI
Total Number of Customers Served
Predictive assessment:
N i N lp lp
SAIFI
NT
N lp
Reliability Index
Historical assessment:
Customer Interruption Durations
CAIDI
Total Number of Customer Interruptions
Predictive assessment:
SAIDI
CAIDI
SAIFI
Reliability Index
Reliability Index
Historical
Network Reduction
Fault Modes and Effects Analysis
Markov Modeling
Monte Carlo Simulation
Network Modeling
Markov Modeling
Failure Modes and Effects Analysis
(FMEA)
Monte Carlo Simulation
Markov Modeling
Network Reduction
A. Komponen Rangkaian Seri
S 1 2
Durasi perbaikan rata-rata sistem adalah
rS
1 .r1 2 .r2
r1 r2
.r
U S S . rS
Example
1.Pemadaman rata-rata
1 1,0
r1 5
2 0,005
r2 4
S 1 2
S ( 0,1 . 10 ) ( 0,5 % ) 1,005
(1 . 5 ) ( 0,005 . 4 ) 5 0,2
1 0,005
1,005
4,995
Network Reduction
B. Komponen Rangkaian Pararel
P 1 . 2 ( r1 r2 )
Durasi perbaikan rata-rata sistem adalah
r1 x r2
rP
r1 r2
Jumlah rata-rata waktu pemadaman
U P P . rP
Example
Example
2 a (0,1 * 10) 1
r2 a 5
r2b 4
1 1a 1b
.r .r
r1 1a 1a 1b 1b
r1a r1b
1 1,005
r1 4,995
2 1,005
r2 4,995
Example
A. Laju kegagalan rata-rata per tahun
P 1 . 2 ( r1 r2 )
p (1,005 * 1,005 ) (4,995 4,995 ) / 8760 10,09 / 8760 0.0011
B. Rata- rata lama pemadaman
rP
r1 * r2
r1 r2
rP
2,497
4,995 4,995
9,99
Example
Load Point
1000
5000
800
3600
600
2800
800
3400
500
2400
300
1800
Total
4000
19000
Example
Interruption Load Point
Case
Affected
Number of
Load Duration of Customer
Customer
Curtailed Interruption
Hours
Disconnected
Lc (kW) d (hours)
Curtailed
(Nc)
Energy not
Supplied
(kWh)
800
3600
2400
10800
600
2800
1800
8400
300
1800
600
3600
600
2800
600
2800
500
2400
1.5
750
3600
300
1800
1.5
450
2700
3100
15200
6600
31900
Total
800+600 +300+500
=2200
Example
Example
Load Point
L1
L2
L3
Load Point
(f/yr)
0.2
0.3
0.5
r (hours)
6
6
6
U (hours/yr)
1.2
1.7
2.9
()
L1
200
1000
L2
150
700
L3
100
400
Total
450
2100
Evaluation Method
Line
A
B
C
Load Point
L1
L2
L3
(f/yr)
0.2
0.1
0.15
(f/yr)
0.20
0.30
0.45
r (hours)
6
5
8
r (hours) (hours/yr)
6.0
1.2
5.7
1.7
6.4
2.9
Component
Section
1
2
3
4
Distributor
a
b
c
d
Length (km)
f/yr
r (hours)
2
1
3
2
0.2
0.1
0.3
0.2
4
4
4
4
1
3
2
1
0.2
0.6
0.4
0.2
2
2
2
2
Data Sistem
Load Point A
Load Point B
Load Point C
(f/yr)
r
(Hour
s)
U
(Hours/yr)
(f/yr)
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.2
0.1
0.3
0.2
4
4
4
4
0.2
0.6
0.4
0.2
2
2
2
2
0.4
1.2
0.8
0.4
0.2
0.6
0.4
0.2
2
2
2
2
0.4
1.2
0.8
0.4
0.2
0.6
0.4
0.2
2
2
2
2
U
r (Hours) (Hours/yr)
(f/yr)
Load Point D
(f/yr)
r
(Hours)
U (Hours/yr)
0.8
0.4
1.2
0.8
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.4
1.2
0.8
0.4
0.2
0.6
0.4
0.2
2
2
2
2
0.4
1.2
0.8
0.4
6.0
2.2
2.73
6.0
U
r (Hours) (Hours/yr)
Section
1
2
3
4
Distributo
r
a
b
c
d
Total
2.2 2.73
6.0
2.2 2.73
6.0
2.2 2.73
Load Point A
Load Point B
Load Point C
r
(f/yr) (Hours) U (Hours/yr) X (f/yr) r (Hours) U (Hours/yr) X (f/yr) r (Hours) U (Hours/yr)
Load Point D
X (f/yr) r (Hours)
U (Hours/yr)
Section
1
2
3
4
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.2
0.4
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.6
1.2
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.4
0.8
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.2
0.4
1.0
3.6
3.6
Distributor
a
b
c
d
Total
1.0 3.6
3.6
1.4
3.14
4.4
1.2
3.33
4.0
Effect of Sectionalizer
Component
Failure
Load Point A
Load Point B
Load Point C
r
(f/yr) (Hours) U (Hours/yr) X (f/yr) r (Hours) U (Hours/yr) X (f/yr) r (Hours) U (Hours/yr)
Load Point D
X (f/yr) r (Hours)
U (Hours/yr)
Section
1
2
3
4
0.2 4
0.1 0.5
0.3 0.5
0.2 0.5
0.8
0.05
0.15
0.1
0.2
0.4
0.2
0.1
0.3
0.2
4
4
0.5
0.5
0.8
0.4
0.15
0.1
0.6
1.2
0.2
0.1
0.3
0.2
4
4
4
0.5
0.8
0.4
1.2
0.1
0.4
0.8
0.2
0.1
0.3
0.2
4
4
4
4
0.8
0.4
1.2
0.8
0.2
0.4
1.0
3.6
3.6
Distributor
b
c
d
Total
1.4
1.89
2.65
1.2 2.75
3.3