You are on page 1of 3

DAILY MORNING MEETING REPORT AT 06.

10 AM
Date
By
Safety/environmental
issue during last 24
hours
Follow Up job

Remarks

1.
2.
3.
4.
5.
6.
7
8
9.
10
Electrical

1.
2
3
4
5
Break down job during last 24 hours

Remarks

Night Shift Reported


Safety Status :

1.
2.
3
Electric N/Shift Reported

Remarks

Safety Status :

1.
2.

Operation Reported

Remarks

Page : 1

Overland ,Crusher & SWTP Mechanic


Safety Status :

OLC, Crusher & SWTP Electric


Safety Status :

1.
2
Grinding Mechanic
Safety Status :

Grinding & Flot.130 Electric


Safety Status :

1.
2.
3
Flotation#130 Mechanic
Safety Status :

1.

Regrind Cleaner & CCD Mechanic


Safety Status :

Down Stream Electric


Safety Status :

1.
2

TWC Mechanic
Safety Status :

1.
2.
3.
Fabrication Shop

Remarks

Safety Status :

1.
2
Machine & Rebuild Shop

Remarks

Safety Status :

1.
2.
3.
Lube. & TFM team

Remarks

Safety Status :

1.
2.
3.
Service Equipment

Remarks

Safety Status :

1. Flat bad :
2. Boom truck :

Page : 2

Condition Monitoring Reported

Remarks

Safety Status :

1.
2.
Process Control

Remarks

Safety Status :

Instrument

Remarks

Safety Status :

Reliability

Remarks

Safety Status :

SUPRA Reported

Remarks

Safety Status :

Atlas Copco Indonesia

Remarks

Safety Status :

DEMAG

Remarks

Safety Status :

Atlas CopcoNusantara

Remarks

PDP

BBS

Planning

Remarks

Page : 3