Professional Documents
Culture Documents
Power System Seminar 20th April Combined PDF
Power System Seminar 20th April Combined PDF
Michael Burke
NCC
Power System Control
Doireann Barry
Generation Team
Power System
Operational Planning
Capacity Adequacy
20 Years >> 5 Years
Flexible
Plant Portfolio System Issues = Adaptable
Generators
Process for scheduling maintenance
Provides certainty regarding start/end dates
System Users
Security of Supply keeping the lights on
Economic & efficient - keeping the costs down
What is Risk?
Adequate?
Weekly
Demand
Peak
Forced
Outage
Probabilities
of
Generators
Weekly
Generation
Capacity
(including
Outages)
Wind
Generation
Capacity
Credit
Imports
available
from SONI
Usable?
Usable?
2,300 MW
(conventional)
+
650MW (wind)
Flexible
NCC
2 Days Ahead
3 Years Ahead
10
Forced
Outage
Probabilities
of Generators
Constraint
on our
system
or on SONIs
system
Duration
?
Weekly
Generation
Capacity
(including
Outages)
Wind
Generation
Capacity
Credit
Time of
Year
Blackstart
Imports
available
from SONI
11
Fast-Acting
Plant
Predicted
DAILY
Demand
Peak
Constraint
on our
system
or on SONIs
system
Wind
Generation
FORECAST
Duration
Weekly
Generation
Capacity
(including
Outages)
Timing
Imports
available
from SONI
Timing of
Outage
Blackstart
12
13
14
Generator submits
Outage Plan
No
EirGrid provide
load forecast, wind
capacity credit &
FOPs
Yes
SONI provide tieline capacity
15
Key Points
Aim is to deliver an adequate, usable, flexible portfolio
of plant for Scheduling & Dispatch
Generator Outage Planning takes place from 3 years
ahead 2 Days ahead
Coordination with the Generators is very important
16
Michael Burke
National Control Centre Engineer
EirGrid
Overview
50 Hz:
Generation = Demand
SCHEDULING
& DISPATCH
What is Scheduling?
Scheduling
Assignment of generation in advance to meet forecast system demand,
while observing security standards and other expected constraints.
Uses best forecast of input variables (Demand, Wind, Availability etc)
What is Dispatch?
Dispatch
Refines schedule in real time to ensure that generation meets actual
demand on a second by second basis
Maintains reserve requirements and system security in real time
Day Ahead
Schedule
16:00 D-1
Generation
Outage
Planning
In Day
Schedule 1
04:00 D
Subsequent
In Day
10:00 D &
21:00 D
Outputs:
RCUC
Generation Schedule
Tie Line Flow Schedule
Reserve Schedule
Forecasting
Operational Security
Economics
Mon.
Tue.
Fri.
Sat.
Sun.
Load Forecasting
Software Tool Forecasts system demand for 14 days ahead
Uses historical system demand & weather data supplied by Met Eireann
NCC Engineer input
00
:
00 00:0
:
01 30:00
:
01 00:00
:
02 30:00
:
02 00:00
:
03 30:00
:
03 00:00
:
04 30:00
:
04 00:00
:
05 30:00
:
05 00:00
:
06 30:00
:
06 00:00
:
07 30:00
:
07 00:00
:
08 30:00
:
08 00:00
:
09 30:00
:
09 00:00
:
10 30:00
:
10 00:00
:
11 30:00
:
11 00:00
:
12 30:00
:
12 00: 0
: 0
13 30:00
:
13 00:00
:
14 30:00
:
14 00:00
:
15 30:00
:
15 00:00
:
16 30:00
:
16 00:00
:
17 30:00
:
17 00:00
:
18 30:00
:
18 00:00
:
19 30:00
:
19 00:00
:
20 30:00
:
20 00:00
:
21 30:00
:
21 00:00
:
22 30:00
:
22 00:00
:
23 30:00
:
23 00:00
:
00 30:00
:0 0
0:
00
MW
Impact of Grand Slam Rugby: Saturday 14th March v. Saturday 21st March
3800
Presentation Ends TV Ad Break
3600
3400
3200
Match Ends
3000
2800
Half Time
2600
14th
March
2400
2200
2000
21st
March
Wind Forecasting
2-Day Forecast
Constraint/Curtailment
Removal
Forecasting
Operational Security
Economics
Operating Reserve
Provided by additional generation or demand reduction
Ensures security of supply and control of system:
Frequency Regulation
System Stability
Unit 1
Trip
Unit 2
Trip
Loss of supply
Unacceptable frequency conditions
Unacceptable voltage conditions
Unacceptable overloading of any transmission plant
System instability
VO
FO
Gen.
Solution?
Reduce Cork generation - approx.
675MW
N-1 Overloads < 110%.
FO can now proceed
VO
Cancelled
FO
Gen.
Forecasting
Operational Security
Economics
Economic Dispatch:
Dispatch online units in the most economic fashion
Incremental costs will be the governing cost factor
Reserve typically held on the more expensive units
RCUC Output
Real Time
Considerations
EDIL
Re-Schedule or Re-Dispatch?
Significant
Departure from
Schedule
(>100MW)
New Schedule is
Jointly Prepared
Demand Change
Wind Change
Availability Change
Transmission Contingencies
Generator Performance
Small
Departure from
Schedule
(<=100MW)
In Summary
The Scheduling Process feeds into the Dispatch Process
NCC Engineers take a number of real-time factors into
account when issuing dispatch instructions
Time permitting, Engineers will re-schedule if the current
schedule cannot be followed
NCC will face unplanned issues when dispatching
At all times NCC give priority to safety and security