Daily activities on CPU Process

Start up gas LP comp. MK.7720 CPU 2

Open / reset SDV 7116 gas lines from V.4110 & SDV 7117 gas
lines from V.4130 at cpu1
Reset SDV .7705 , 7710 , 7704 , 7709 at gas comp area
Close 2 pcs manual valve inlet suction scrubber MK.7720
Open SDV 7708 , & 7703 inlet suction scrubber MK.7720
Reset BDV 7706, 7707 , 7701 , 7702
1st step ..running motor prelube
Check lube oil pressure ( should be 75 psi
After than running motor cooler.
Push the start button to run the compressor
Route condensate flow from NPU to CSU at STP 2

Route condensate from NPU paralel to CPU2 & to CSU


By open ESDV 7172 & open manual valve no 47 downstream
ESDV 7172
Adjust PV.7176 gradually until fully open
Close ESDV 7130 inlet MP header cpu2 at cpu2 area
Close manual valve upstream ESDV 7130

Route back condensate flow from NPU to CPU2 after routed to


CSU
Open ESDV 7130 inlet MP header CPU2
And open manual valve downstream ESDV 7130 on CPU 2
Close ESDV 7172 and adjust PV.7176 at STP2
Close manual valve no 47 at STP 2

Route Condensate from NPU/CPU2 to CPU1


Open ESDV 7173 & open manual valve inlet MP Header CPU 1 at
CPU1
Close ESDV 7130 and close glove valve inlet MP header at CPU2.

Route Condensate from SNB/CPU1 to CPU2