TEMS Operation Steps

install and setting

when we finish the install ,we will found the view as follow:

3Basic information by

4Basic information

we need to setting the layout of windows as follow:

1Map and
engineer

2Service
and
neighbors
5Rx_level and Rx_quality

imput map and engineer parameter

a Click presentation option and display the map on overview

window

b input engineer parameter


tems.cel

Firstly :we need to make a cell file ,


open it and we can
modify the BCCH BASIC and each parameter in the cell file and
save it(if the basic data update)
Can not modify the
header format and backup
cell file

Second:
genral cellfile load add .

press configuration

When the engineer parameter input the tems and we should


setting the site or cell name in the map window otherwise we can
not see it:

Service and neighbors cell

Basic information by channel

Basic information by cell

Rx_level and Rx_quality color chat

For we can see Rx_level and quality clearly when we do the drive
test. Operation stes as bellow:

Chart

For example: we just want to setting chart 1 (sevice cell Rx_level


Sub) , edit chartpitch on Rx_level Subedit color and thickness.

And also we can set the service cell line when you do the drive
test .

All of the above interface was set up later ,just need to connect
the GSP and cell phone(K790).
Mobile phone setting : MS1 is dedicate mode ; MS2 is
idle mode
Pls remember the port of MS and GPS , do not replace the
mobile and GPS port unless it is not working.
set mobile and GPS port

Ctrl&Config Equipment Configuation.if we have installed


mobile and GPS driver ,GPS or mobile type will be display
in port as bellow pictures.

set automatic dialing


Firstly we need to set Loop in command Sequence, and
then Dial. Operation steps as follow: (loop Dial)

Times calling

Call duration
Call setup
time

Secondly , in the command sequence window , click


properties button ,set the number and interval of the calling .
This completes the atuomatic dialing program settings.

Lock BCCH
When you finish connection ,we can lock the BCCH as bellow:

Mapinfo and Tab layer


A create point layer
1

Open your engineer parameter by excel ,save as


text(Macintosh) on desktop.
Open your mapinfo and input the file which you made it , in
Table option click create points. At last open your tab file on
your desktop, you can find the point layer.

B create cell layer


we have created a text file at A, choose WFI seesite in Table
options , create site boundaries . The specific steps as below

Required field

Display
cell_name

Export ( Rx_level Rx_quality and SQI ) report

Rx_level
Firstly export the Rx_level form tems , operation steps as
bellow:

MS2 is Idle mode


MS1 is dedicate

Combine the log file


and export if you
pitch on

Click the
button

Open export file by mapinfo

Setting
Rx_level

Clcik
recalc

Save as

Name rule : Cluster


2_MS1_Dedicate by
Or Cluster _2_MS2_Idle by.

B Rx_quality
We are same steps with Rx_level , when you export file form
tems,it is Rx_quality format. The details are as follows:

Combine
logfile

Choose
logfile

Open the export file by mapinfo ,create thematic map in Map


option.
Choose region ranges solid Yellow-bule

,
Field is Rx_qual Sub , set ranges Styles and Legend.

After you finish the ranges set , next step is style setting, and
last step is legend setting . The details are as follows:

Save sa

All of the above Rx_level and Rx_qualty color setting be


unified.

Standard
name

C FER layer

According to the above approach , export the FER SUB(%)file ,


you can make a tab layer in mapinfo , the following diagram:

Notes:
1 if your laptop power off or disconnect
with device ,
you must check the MS1 and MS2 ,
sometimes we found the MS3 exist
2
All of the above chart are kept to same
size .
3 During the test, if the path has more than
cluster level,

we need to stop the test and stop the


logfile , we only test the BTS in cluster.