Professional Documents
Culture Documents
1a: The various steps to be taken before the actual approval process are as
follows:
To identify the need
Preparing a realistic estimate of the costs involved per stage of the project
Calculating if sufficient amounts of fund are available internally or not
Calculation of all the taxes required to be paid.
Check if all the required approvals can be obtained within the estimated
timelines
1b) The list of approvals required from the agencies outside the Transco
are:
License
Transmission
License
from
State
Electricity Regulatory Commission
Section 68 of Electricity Act 2003 from
State Government
Duration (months)
18
12
12
6
6
6
18
24
6
12
12
6
24
6
Yes, there might be some opposition or resistance to the project by parties who may
be adversely affected by the project. Some of the strategies to reduce
damage/compensation costs are:
Sending out letters with project information and invite interested parties to
attend public meetings
Consult with village leaders and community counselors,
Publicize the project in national and local newspapers,
Hold Public Participation Meeting and provide leaflets for attendees, and
provide for discussion opportunities including questions and answers session,
Provide opportunities for concerns to be raised verbally or in written form..
Key activities adapted in receiving ongoing comments and concerns or
complaints:
Providing a clear grievance mechanism including: Contact details
Locations and means to obtain project information and associated ESIA
documents,
Response to comments and concerns or complaints within reasonable time
frame.
Maintain a register and records of inputs from all stakeholders and interested
parties including a copy of the response.
In order to introduce the project and to effectively evaluate the
environmental, social and techno-economic impacts of the project, people
that might potentially be affected directly and the local people living in the
region and legal authorities were firstly invited to the meeting.
3a) The project scope Involves:
a) The detailed survey to be got conducted including route map, tower schedule,
soil investigation reports.
b) The Tower designs to be done and all the BOQ to be freezed
c) The foundation designs to be done for different soil classifications like normal,
submerged, hard rock, fissured rock etc and provisional quantities to be indicated in
the BOQ.
d) Construction of S/C line through a combination of Overhead line on double circuit
towers and UG Cable e) Stringing of ACSR Panther conductor.
f) Fitting of Insulators & hardware fittings.
g) Construction of foundation (Civil Work) for the towers, 4 poles structure and DPs.
h) Erection of Isolator with earth switches.
i) Erection of DP structure and 4-Pole structure with required Insulators and H/W
fittings.
j) Erection of Lightning Arrestors.
k) Erection of 1 set of HG Fuse unit.
l) Laying of UG Cable with spare.
m) Straight through Jointing kits , UG Cable
n) Jointing of HT cable termination end kit, UG Cable (20 nos)
o) Erection of rigid PVC pipes.
The supply of all the required materials on TOTAL TURN KEY is in the scope of the
contractor
3a ii) The following are the deliverables from the Transco engineers:
3b) We have to ensure the implementation of the Quality Assurance Plan which
involves material testing at regular intervals and Appointment of Third Party
Inspection Agency. We have to also include the clause of submission of Performance
Bank Guarantee which will be submitted to the bidder in advance and would be
released only upon successful completion of Work. Inclusion of the following
clauses:
In case of results of all the tests conducted do not comply with the technical
specifications, re-testing of additional samples selected on random basis shall have
to be carried out by the vendor at their risk and cost.
If vendor brings defective / sub-standard materials to the site, it shall be the
responsibility of the tenderer for the removal and disposal of the same at his cost.
Owner shall not entertain any claim from the tenderer on this account. In case the
tenderer fails to remove such materials within fifteen days after issuing notice in
writing to the tenderer; owner reserves the right to dispose off such materials at the
entire risk and cost of the tenderer.
3c) In case the Vendor carries out the work as per his own specifications and not
acceptable to the owner, in such cases, the same will be required to be redone as
per the specification(s) given by owner at the tenderers risk and cost. In case of
failure to re-do the work by the Vendor, owner reserves the right to get it done
through any other agency entirely at the risk and cost of the Vendor.
3d) We ensure that only reputed and capable contractors get the contract by
adopting a transparent and unbiased Tendering Criteria such as following:
Prefer open tendering as far as possible
In case limited tenders are resorted to, prepare & update panel of contractors/
vendors in a transparent way.
Ensure adequate & wide publicity. (Web publicity is necessary even in case of
limited tenders)
Ensure adequate time for submission of offers.
Open the bids in presence of bidders.
Attest and account for corrections, omissions, insertions, overwriting
Keep the PQ criteria neither too stringent nor too lax.
Prepare the PQ criteria specific to the requirement of the work in clear terms.
Notify the evaluation criteria in the PQ document.
Verify PQ credentials.
Evaluate the bids exactly as per the notified criteria
In detail the following details of vendors should be taken in PQ Criteria:
The criteria fall under 5 major heads which are as follows:
1) Statutory: This section deals with the legal requirement which a vendor needs
to have in order to work in India.
2) Safety: This section is aimed at analysing the emphasis given by the Vendor
towards the safety of its employees while carrying out works.
3) Quality: This section tries to explore the quality checks/measure taken by the
Vendor to ensure quality level at working locations.
4) Financial : This section uncovers the financial stability of the vendor and looks
for both short term financial condition as well as the capability of the vendor to
finance its projects on annual basis.
5) Past Experience/Capacity/Resources: This section deals with the following 3
things:
a) Past Experience: This section gauges the capability of vendor to carry out the
Project by analysing his/her experience of having carried out work of similar nature
and scale in the past.
b)
Capacity : It looks into the capacity of the Vendor to take up the work by
scrutinizing Vendors other commitments within as well as outside Reliance and
understanding the capability of the vendor to carry the projects simultaneously.
c)
Resource: This section is focused primarily on the capacity of the Vendor to
deploy skilled/unskilled labour at site along with the Administrative/Managerial Staff
the vendor has to facilitate the completion of the Project. This activity is to realize
the vendors ability to engage Manpower. Apart from Manpower, it also provides the
buyer a status of the Plant & Machinery held by the Vendor which can be freely
deployed at Site to facilitate the completion of Project.
4a): The various steps of the bidding process would be:
Estimate (Qty. and Amount)
The payment schedule has to be made keeping in mind the outgoing cash flows
which we will incur on our project. We can resort to milestone billing for the goods
contractors stating that once 30% of work is done on the project, they will get the
money for the procured items. Meanwhile we will have to ensure that we also paid
for that 30% work done on the project part. So the milestones can be made into
30%, 30% and then 40%. This will give us sufficient credit terms and also not
discourage the goods contractor from bidding.
6) Detailed L2 network in MS project:
Task
Mode
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
Name
Duration
Start
Start
0 days
Awarding Contract
28 days
Profile Checking
56 days
Sat 12-1116
Finish
Successors
Sat 12-1116
Thu 22-1216
Tue 18-046,7,8
17
Designing Standard
foundation
42 days
56 days
Solid Testing
49 days
Fri 16-06-17
Foundation class
Section 1
140 days
Wed 23-089,11,13
17
Thu 08-0318
Foundation class
Section 2
133 days
Tue 03-0715
18
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Auto
Schedul
ed
Foundation class
Section 3
168 days
Tue 24-0718
28 days
Tue 09-1016
18