Professional Documents
Culture Documents
Date :
Floor Area
Floor
B1
Structural
Completion
Date
(Revised
Schedule)
Done
Done
Done
Started
Actual
Start Date
Started
Target
Completion
Date
30-Nov-15
Final Fix
Actual
Completion (%)
81%
Target
Completion
Date
3-Dec-15
L1
Done
22-Jul-15
22-Jul-15
Started
Started
31-Dec-15
60%
6-Dec-15
L2
1-Jun-15
27-Jul-15
27-Jul-15
3-Aug-15
7-Aug-15
31-Dec-15
60%
9-Dec-15
L3
12-Jun-15
15-Aug-15
11-Aug-15
17-Aug-15
17-Aug-15
15-Dec-15
64%
12-Dec-15
L4
23-Jun-15
19-Aug-15
18-Aug-15
21-Aug-15
24-Aug-15
15-Dec-15
71%
15-Dec-15
L5
4-Jul-15
23-Aug-15
22-Aug-15
25-Aug-15
26-Aug-15
15-Dec-15
69%
18-Dec-15
L6
15-Jul-15
27-Aug-15
25-Aug-15
29-Aug-15
3-Sep-15
15-Dec-15
61%
21-Dec-15
L7
26-Jul-15
31-Aug-15
8-Sep-15
2-Sep-15
21-Sep-15
20-Dec-15
43%
24-Dec-15
L8
29-Aug-15
18-Sep-15
16-Sep-15
20-Sep-15
20-Oct-15
20-Dec-15
28%
27-Dec-15
L9
4-Sep-15
24-Sep-15
12-Oct-15
26-Sep-15
20-Oct-15
20-Dec-15
57%
30-Dec-15
L10
10-Sep-15
2-Oct-15
21-Oct-15
4-Oct-15
9-Nov-15
31-Dec-15
44%
2-Jan-16
L11
18-Sep-15
12-Oct-15
31-Oct-15
14-Oct-15
31-Dec-15
39%
5-Jan-16
L12
28-Sep-15
20-Oct-15
20-Nov-15
22-Oct-15
15-Jan-15
29%
8-Jan-16
L13
6-Oct-15
28-Oct-15
3-Dec-15
30-Oct-15
15-Jan-15
17%
11-Jan-16
L14
14-Oct-15
6-Nov-15
4-Dec-15
8-Nov-15
15-Jan-15
14-Jan-16
L15
23-Oct-15
15-Nov-15
11-Dec-15
17-Nov-15
15-Jan-15
17-Jan-16
L16
1-Nov-15
26-Nov-15
28-Dec-15
28-Nov-15
30-Jan-15
20-Jan-16
L17
12-Nov-15
4-Dec-15
6-Dec-15
30-Jan-15
23-Jan-16
L18
20-Nov-15
12-Dec-15
14-Dec-15
30-Jan-15
26-Jan-16
L19
28-Nov-15
20-Dec-15
22-Dec-15
30-Jan-15
29-Jan-16
L20
6-Dec-15
28-Dec-15
30-Dec-15
30-Jan-15
1-Feb-16
L21
14-Dec-15
5-Jan-16
7-Jan-16
6-Feb-16
11-Feb-16
L22
22-Dec-15
13-Jan-16
15-Jan-16
14-Feb-16
19-Feb-16
L23
30-Dec-15
29-Jan-16
31-Jan-16
1-Mar-16
6-Mar-16
Lower Roof
(Core area
Y4 to Y10)
23-Dec-15
6-Jan-16
8-Jan-16
22-Feb-16
27-Feb-16
Proposed
Equipment
Delivery Date
Target Structural /
Architectural
Actual Structural /
Estimated
Clearance Issue
Architectural
Delivery Date
Date
Clearance Issue
(MCI & IL
Date
Approved)
(A)
1-Dec-14
31-Oct-15
21-Nov-15
6-Aug-15
30-Oct-15
30-Oct-15
1-Oct-15
1-Oct-15
10-Oct-15
27-Sep-15
Done
20-Nov-15
20-Nov-15
Done
23-Oct-15
23-Oct-15
24-Sep-15
24-Sep-15
3-Oct-15
20-Sep-15
IT Room
31-Oct-15
24-Oct-15
Transformer Room
LV Switch Room
PAHU Room
17-Oct-15
12-Oct-15
5-Oct-15
10-Oct-15
15-Jan-15
26-Oct-15
Chiller Room
Generator Room
20-Sep-15
17-Oct-15
13-Sep-15
10-Oct-15
27-Oct-15
27-Oct-15
1-Dec-15
FL01 LMR
FL02 LMR
Actual
Delivery Date
Done
18-Dec-15
Target
Completion
Date
31-Jan-15
31-Dec-15
31-Dec-15
30-Nov-15
31-Dec-15
31-Dec-15
31-Dec-15
31-Dec-15
15-Jan-15
31-Dec-15
90%
0%
0%
80%
20%
0%
0%
0%
0%
0%
31-Dec-15
0%
18-Oct-15
12-Oct-15
5-Oct-15
15-Dec-15
4-Feb-15
31-Dec-15
70%
0%
10%
25-Sep-15
17-Oct-15
31-Dec-15
31-Dec-15
40%
25%
28-Oct-15
31-Dec-15
80%
4-Dec-15
15-Jan-15
0%
15-Sep-15
6-Jan-16
22-Feb-16
0%
15-Sep-15
6-Jan-16
22-Feb-16
0%
PL05-08 LMR
15-Sep-15
6-Jan-16
22-Feb-16
0%
30-Nov-15
6-Jan-16
22-Feb-16
0%
Fire Pump Rm
10-Oct-15
6-Jan-16
22-Feb-16
0%
10-Oct-15
6-Jan-16
22-Feb-16
0%
Fire Tank
10-Oct-15
6-Jan-16
22-Feb-16
0%
Done
30-Sep-15
30-Sep-15
30-Sep-15
20-Sep-15
20-Sep-15
10-Sep-15
10-Aug-15
30-Oct-15
30-Oct-15
30-Oct-15
Lower Roof
(Y1a to Y4)
8-Jan-15
15-Jan-15
17-Jan-15
16-Feb-15
16-Feb-15
15-Dec-15
15-Jan-15
16-Feb-15
0%
Upper Roof
15-Jan-16
23-Jan-16
25-Jan-16
24-Feb-16
29-Feb-16
PAHU
10-Oct-15
23-Jan-16
24-Feb-16
0%
Storey
Basement-1
90%
70%
88%
90%
86%
ACMV SYSTEM
BMS SYSTEM
(% work done)
1 & 2nd 3rd
Fix
Fix
st
90%
81%
(% work done)
1 & 2nd 3rd
Fix
Fix
st
85%
81%
FIRE PROTECTION
(% work done)
1 &2
Fix
3
Fix
95%
50%
st
nd
rd
93%
PA SYSTEM
PLUMBING
(% work
1st & 2nddone)
3rd
Fix
Fix
(% work
(% work
1st & done)
2nd rd
1st &done)
2nd 3rd
3 Fix
Fix
Fix
Fix
90%
81%
70%
SANITARY
DATE: 30-Dec-15
P&S
OVERALL
(%)
65%
61%
GAS
LIFT
ESC
OVERALL
(%)
50%
70%
10%
81%
Level 1
70%
63%
70%
67%
75%
68%
85%
81%
40%
38%
80%
72%
65%
80%
65%
60%
50%
50%
60%
Level 2
65%
59%
60%
57%
70%
63%
85%
81%
60%
57%
70%
63%
60%
80%
63%
20%
70%
50%
60%
78%
77%
77%
77%
85%
85%
85%
85%
81%
81%
81%
81%
50%
75%
75%
75%
45%
68%
68%
68%
70%
70%
70%
50%
67%
67%
67%
48%
80%
90%
85%
60%
76%
90%
85%
57%
75%
75%
75%
75%
68%
68%
68%
68%
20%
50%
25%
10%
40%
40%
27%
23%
11%
23%
70%
70%
70%
70%
64%
71%
69%
61%
50%
45%
40%
38%
40%
38%
40%
36%
40%
18%
70%
43%
0%
40%
38%
40%
38%
40%
36%
0%
70%
28%
88%
50%
45%
50%
80%
59%
57%
57%
48%
38%
19%
19%
19%
19%
0%
0%
0%
0%
0%
0%
0%
70%
70%
70%
70%
40%
40%
40%
40%
40%
40%
40%
40%
63%
63%
63%
63%
36%
36%
36%
36%
36%
36%
36%
36%
0%
0%
20%
70%
70%
70%
60%
40%
5%
41%
32%
32%
27%
18%
2%
0%
0%
0%
0%
0%
0%
0%
0%
44%
39%
29%
17%
17%
12%
12%
3%
3%
3%
3%
3%
0%
0%
Level
Level
Level
Level
3
4
5
6
85%
85%
85%
85%
Level 7
75%
68%
40%
38%
Level 8
50%
45%
30%
29%
Level 9
50%
45%
30%
29%
60%
54%
40%
38%
90%
Level
Level
Level
Level
Level
Level
Level
Level
Level
Level
Level
Level
Level
Level
40%
30%
30%
36%
27%
27%
0%
14%
0%
0%
0%
0%
0%
0%
0%
0%
0%
30%
30%
30%
29%
29%
29%
0%
14%
0%
0%
0%
0%
0%
0%
0%
0%
0%
40%
40%
36%
36%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
40%
40%
40%
40%
40%
40%
40%
38%
38%
38%
38%
38%
38%
38%
0%
0%
0%
0%
0%
0%
0%
60%
50%
40%
20%
20%
20%
20%
10
11
12
13
14
15
16
17
18
19
20
21
22
23
15%
10%
5%
15%
80%
80%
50%
90%
Transformer Room
LV Switch Room
PAHU Room
70%
Chiller Room
Generator Room
40%
25%
80%
FL01 LMR
FL02 LMR
PL05-08 LMR
Booster Pump & Filtration Rm
Fire Pump Rm
PAHU Rm (GL Y8)
Fire Tank
Water Supply Tank
PAHU (GL Y4)
Lower Roof
ELECTRICAL
1) 1ST FIX:
2) 2ND FIX:
3) FINAL FIX:
PLANT ROOM
SYSTEM
conduit & the brackets, K.O box, etc
exposed conduit, trunking & wiring work, Isolator,DBs, etc
Lighting, power points, switches, etc..
ACMV SYSTEM
1) 1ST FIX:
Drain pipes, conduit, pipe sleeve, duct sleeve & brackets, pipe sleeve & support, etc
2) 2ND FIX:
exposed piping, ducting & wiring work, FCU, CU, MV FANs, Chiller, AHU & Cooling Tower, etc..
3) FINAL FIX: Grill, Louver, etc..
SANITARY SYSTEM
pipe sleeve & brackets, etc
exposed piping & wiring work, WC, Basin, Urinal bowl
Water tap, Spary shower, etc..
80%
20%
10%
1) Every floors are not linked together. The Sub-contractors need to provide separate team
every floors.
2) The critical path is at Lower Roof. 1st & 2nd fix require 45 days to complete because ma
room & equipment are at this level. The MEP installation completion date is targeted on
4 Feb 2016. Due to the congested area, the programme could not be compressed any m
3) The Testing & Commissioning period is less than 2 months. Saperate teams to complete
T&C activities is necessary and only one way to complete by end March.
n date is targeted on
MEP Progress
Floor
B1
L1
L2
L3
L4
L5
L6
L7
L8
Trades
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
Done
Done
Started
21-Aug-15
2-Nov-15
Done
Done
Started
28-Aug-15
5-Nov-15
1-Jun-15
27-Jul-15
3-Aug-15
2-Oct-15
8-Nov-15
12-Jun-15
15-Aug-15
17-Aug-15
16-Sep-15
11-Nov-15
23-Jun-15
22-Aug-15
24-Aug-15
23-Sep-15
14-Nov-15
4-Jul-15
29-Aug-15
31-Aug-15
30-Sep-15
17-Nov-15
15-Jul-15
5-Sep-15
7-Sep-15
7-Oct-15
20-Nov-15
26-Jul-15
12-Sep-15
14-Sep-15
13-Nov-15
23-Nov-15
4-Aug-15
19-Sep-15
21-Sep-15
21-Oct-15
26-Nov-15
Actual
Completion (%)
Target
Completion
Date
MEP Progress
Floor
L8
L9
L10
L11
L12
Trades
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
15-Aug-15
5-Sep-15
7-Sep-15
7-Oct-15
29-Nov-15
24-Aug-15
14-Sep-15
16-Sep-15
16-Oct-15
2-Dec-15
4-Sep-15
25-Sep-15
27-Sep-15
27-Oct-15
5-Dec-15
14-Sep-15
5-Oct-15
7-Oct-15
6-Nov-15
8-Dec-15
Actual
Completion (%)
Target
Completion
Date
MEP Progress
Floor
L13
L14
L15
L16
L17
L18
L19
L20
L21
Trades
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
21-Sep-15
12-Oct-15
14-Oct-15
13-Nov-15
11-Dec-15
28-Sep-15
19-Oct-15
21-Oct-15
20-Nov-15
14-Dec-15
5-Oct-15
26-Oct-15
28-Oct-15
27-Nov-15
17-Dec-15
12-Oct-15
2-Nov-15
4-Nov-15
4-Dec-15
20-Dec-15
19-Oct-15
9-Nov-15
11-Nov-15
11-Dec-15
23-Dec-15
25-Oct-15
15-Nov-15
17-Nov-15
17-Dec-15
26-Dec-15
31-Oct-15
21-Nov-15
23-Nov-15
23-Dec-15
29-Dec-15
6-Nov-15
27-Nov-15
29-Nov-15
29-Dec-15
1-Jan-16
12-Nov-15
3-Dec-15
5-Dec-15
4-Jan-16
9-Jan-16
Actual
Completion (%)
Target
Completion
Date
MEP Progress
Floor
L21
L22
L23
Lower Roof
Trades
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
18-Nov-15
9-Dec-15
11-Dec-15
10-Jan-16
15-Jan-16
24-Nov-15
15-Dec-15
17-Dec-15
16-Jan-16
21-Jan-16
30-Nov-15
21-Dec-15
23-Dec-15
6-Feb-16
11-Feb-16
Actual
Completion (%)
Target
Completion
Date
MEP Progress
Floor
B1
L1
L2
L3
L4
L5
L6
L7
L8
Trades
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
Done
Done
Started
21-Aug-15
2-Nov-15
Done
Done
Started
28-Aug-15
5-Nov-15
1-Jun-15
27-Jul-15
3-Aug-15
2-Oct-15
8-Nov-15
12-Jun-15
15-Aug-15
17-Aug-15
16-Sep-15
11-Nov-15
23-Jun-15
22-Aug-15
24-Aug-15
23-Sep-15
14-Nov-15
4-Jul-15
29-Aug-15
31-Aug-15
30-Sep-15
17-Nov-15
15-Jul-15
5-Sep-15
7-Sep-15
7-Oct-15
20-Nov-15
26-Jul-15
12-Sep-15
14-Sep-15
13-Nov-15
23-Nov-15
4-Aug-15
19-Sep-15
21-Sep-15
21-Oct-15
26-Nov-15
Actual
Completion (%)
Target
Completion
Date
Actual
Completion (%)
MEP Progress
Floor
L8
L9
L10
L11
L12
Trades
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
15-Aug-15
5-Sep-15
7-Sep-15
7-Oct-15
29-Nov-15
24-Aug-15
14-Sep-15
16-Sep-15
16-Oct-15
2-Dec-15
4-Sep-15
25-Sep-15
27-Sep-15
27-Oct-15
5-Dec-15
14-Sep-15
5-Oct-15
7-Oct-15
6-Nov-15
8-Dec-15
Actual
Completion (%)
Target
Completion
Date
Actual
Completion (%)
MEP Progress
Floor
L13
L14
L15
L16
L17
L18
L19
L20
L21
Trades
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
21-Sep-15
12-Oct-15
14-Oct-15
13-Nov-15
11-Dec-15
28-Sep-15
19-Oct-15
21-Oct-15
20-Nov-15
14-Dec-15
5-Oct-15
26-Oct-15
28-Oct-15
27-Nov-15
17-Dec-15
12-Oct-15
2-Nov-15
4-Nov-15
4-Dec-15
20-Dec-15
19-Oct-15
9-Nov-15
11-Nov-15
11-Dec-15
23-Dec-15
25-Oct-15
15-Nov-15
17-Nov-15
17-Dec-15
26-Dec-15
31-Oct-15
21-Nov-15
23-Nov-15
23-Dec-15
29-Dec-15
6-Nov-15
27-Nov-15
29-Nov-15
29-Dec-15
1-Jan-16
12-Nov-15
3-Dec-15
5-Dec-15
4-Jan-16
9-Jan-16
Actual
Completion (%)
Target
Completion
Date
Actual
Completion (%)
MEP Progress
Floor
L21
L22
L23
Lower Roof
Trades
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Overall
ACMV
BMS
Fire Service
Electrical
ELV
PS
Final Fix
Structural
Completion
Date
(Revised
Schedule)
Overall Structural
/ Architectural
Clearance Issued
Start Date
Target
Completion
Date
18-Nov-15
9-Dec-15
11-Dec-15
10-Jan-16
15-Jan-16
24-Nov-15
15-Dec-15
17-Dec-15
16-Jan-16
21-Jan-16
30-Nov-15
21-Dec-15
23-Dec-15
6-Feb-16
11-Feb-16
Actual
Completion (%)
Target
Completion
Date
Actual
Completion (%)