Professional Documents
Culture Documents
Project Report
Topic:
Reduction of Aux. power consumption by
introducing cooling tower in the Aux. cooling system at
Southern Generating station.
Sampad Ghosh
NIT Durgapur
2012
Contents
Objective of the project.
ACKNOWLEDGEMENT
This present project would not have been possible without the help; I
have received from various quarters of Southern Generating Station
of CESC.I extend a special thanks to my project guides Mr. Sudipta
Laha, Mr. S.N.Lahiri, Mr. Suprakash Ghosh for their guidance
throughout the entire period of the project .I also convey special
thanks to all staff members of Southern Generating Station who gave
their precious duty hours to provide an insight into the working of
the power plant. Finally I would like to thank CESC for providing me
this opportunity to work on real life industrial project like this.
ID,FD,PA FAN#1
GEN. AIR
COOLER 1
MILL COOLERS
A
C
W
P
A
C
W
R
35 C
T
O
G
A
N
G
E
S
ACWP
COMPRESSOR
CEPS#1
A/C COMP
T G L O C#1
H/EX
A
CCW
TANK#2
BFPS#1
BFP#1
F
R
O
M
CCW
TANK#1
A
C
W
S
CCWP
C
C
W
S
H/EX
B
C
C
W
R
39 C
H/EX
C
38.5 C
D
ID,FD,PA FAN#2
T G L O C#2
MILL COOLERS
BFP#2
CEPS#2
BFPS#2
GEN. AIR
COOLER 2
42 C
Parameters
Design
Design
Actual
Actual
Max
Avg.
Max
Avg.
Max
Avg.
Max
Avg.
7.93
8.2
8.06
---
8.5
8.2
TSS (ppm)
400
348
318
161
---
100
100
45
132
74
122
88
---
144
95
62
62
40
67
52.3
---
95
68
40
70
34
55
35.7
---
49
27
22
218
132
178
140
---
238
140
84
30
20
26
22.4
---
64
22
19
18
5.98
8.88
6.36
---
5.72
6.2
5.9
37
---
22.2
19.1
---
54.7
18.8
16.2
0.5
<0.5
0.5
<0.5
---
<0.5
0.5
<0.5
pH
Spec.
Centri
-fugal
Net head
(MWC)
35
Flow
(Cu
m/Hr)
485
MOTOR SIDE
Input
power
(KW)
Rated
Power
(KW)
Rated
Volts
(V)
Rated
Amps
(A)
Speed
(RPM)
52.5
75
415
132
1480
PUMP SIDE
CCW
Type
Spec.
Centri
-fugal
Net head
Flow
(MWC)
(Cu m
/Hr)
50
585
MOTOR SIDE
Input
power
(KW)
Rated
Power
(KW)
Rated
Volts
(V)
Rated
Amps
(A)
Speed
(RPM)
95.5
125
415
216
1485
INLET
TEMP.
OUTLET
TEMP
FLOW
RATE/COOLER
(Kg/Cm2)
(Kg/Cm2)
(C)
(C)
(Cu m/Hr)
TG LUB
COOLER
(ACW)
6 (Max)
0.4
31
33
85
BFP OIL
COOLER
(ACW)
0.2
31
35
16.8
12
4.5 (Max)
0.4
36
40
288
H/EX CCW
Side
0.5
40
37
535
H/EX-ACW
Side
0.6
35
39
600
UTILITY
GENERATOR
AIR COOLER
INLET
PRESSURE
Nos.
Present
(CCW)
ACW Pump A
Voltage
Current
432.0
75.0
432.0
66.0
0.8
45.72
0.8
39.50
Not Measured
ACW Pump D
ACW Pump E
(Design)
Not Measured
ACW Pump B
ACW Pump C
Power Factor
432.0
72.0
0.8
43.10
Not measured
ACW Pump F
CCW Pump A
440.0
173.0
0.8
105.50
CCW Pump B
440.0
166.7
0.8
101.63
CCW Pump C
440.0
155.3
0.8
94.68
CCW Pump D
440.0
183.0
0.8
111.57
UTILITY
INLET
PRESSURE
OUTLET
INLET
TEMP.
OUTLET
TEMP.
Approx. FLOW
RATE/COOLER
(C)
(C)
(Cu m/Hr)
(Kg/Cm2)
PRESSURE
(Kg/Cm2)
PA FAN (CCW)
3.60
3.20
39
43
6.00
FD FAN (CCW)
3.60
3.20
39
42
7.00
ID FAN (CCW)
3.55
3.15
39
43
4.50
COMPRESSOR
(CCW)
5.20
3.70
39
43
7.50
BFP SEAL
COOLER(CCW)
Cannot be
measured
3.20
39
42
12
CEP
BEARING(CCW)
Cannot be
measured
Cannot be
measured
38
42
1.5
SAMPLE
COOLER(CCW)
2.60
Cannot be
measured
39
45
2.05
AIR HEATER
BEARING(CCW)
2.60
Cannot be
measured
39
42
2.00
H/EX (CCW)
6.00
5.70
43
39
Cannot be
measured
UTILITY
INLET
PRESSURE
OUTLET
INLET
TEMP.
OUTLET
TEMP.
Approx. FLOW
RATE/COOLER
(C)
(C)
(Cu m/Hr)
(Kg/Cm2)
PRESSURE
(Kg/Cm2)
GEN. AIR
COOLER (CCW)
5.50
5.00
39
42
Cannot be
measured
BFP LUB
COOLER(ACW)
Cannot be
measured
Cannot be
measured
35
37
24.00
COAL MILL
(ACW)
2.70
2.30
35
40
4.00
TG LUB
COOLER(ACW)
2.80
2.00
35
37
Cannot be
measured
H/EX (ACW)
3.70
3.40
35
38
Cannot be
measured
NOTES:
The flow has been measured physically and against atmospheric
pressure.
Temperatures have been measured by thermo gun.
Period of reading: 3rd week of May 2012.
Utility
(Cu m/Hr)
Total no. of
Total flow rate
cooler
(Cu m/Hr)
present in the
(Approx)
circuit.
85 (Design)
170
10
40
24
144
367 (Derived)
1101
See Note 1
See Note 2
Heat exchanger
1455
Total no. of
Total flow rate
cooler present in
(Cu m/Hr)
two unit
288 (Design)
576
Compressor
7.50
11
82.5
ID fan Bearing
Cooler
4.50
18
FD fan Bearing
Cooler
7.00
28
PA fan Bearing
Cooler
6.00
10
60
Sample cooler
2.05
4.1
Air Heater
2.00
12.00
72
CEP Bearing
1.50
Oil centrifuge
0.50
Generator Air
cooler
855.6
EXISTING REQUIREMENT
In peak summer condition number of pumps required for proper
cooling of the different auxiliaries are
EXISTING
SYSTEM
INLET BUS
PRESSURE
(Kg/Cm2)
INLET
TEMP.
OUTLET
TEMP
TOTAL FLOW
(Cu. M/ Hr)
POWER
(KW)
(C)
(C)
See Note 1
See Note 2
ACW
System
3.7
35
38.5
1455
128.30
CCW
System
5.5
39
42
855.6
217.07
Note 1: Total flow has been derived on the basis of design values &
measured values wherever design values are not available.
Note 2: Summated measured MAX power value as measured for 3 ACW
Pumps & 2 CCW Pumps for any combination.
EXISTING PAIN.
High Auxiliary Consumption of SGS.
% Aux. consumption.
9.4
9.2
9
8.8
8.6
8.4
% Aux.
consumption.
20072008
20082009
20092010
20102011
20112012
8.84
8.94
9.07
9.35
9.27
OPTION :A
SEPARATE COOLING TOWER FOR AUXILIARY COOLING WATER
SYSTEM
&
SEPARATE COOLING TOWER FOR CLARIFIED COOLING WATER
SYSTEM
39 C
ID,FD,PA FAN#1
39 C
U 1 BFP COOLERS
ACWP
A
CT#1
35 C
Blow Down
B
C
ELIMINATION
OF
HEAT
EXCHANGERS
A/C COMP
A
C
C
W
S
REDUCTION
OF
ACW FLOW
CCWP
B
D
U 2 TG LOC
Blow Down
ID,FD,PA FAN#2
U 2 MILL COOLERS
U 2 BFP COOLERS
C
C
CT#2 W
R
35 C
COMPRESSOR
CEPS#1
U 1 TG LOC
A
C
W
S
CCW
TANK#2
BFPS#1
U 1 MILL COOLERS
EXPECTED
ACW FLOW
1 Pump
CCW
TANK#1
A
C
W
R
GEN. AIR
COOLER 1
EXPECTED ACW
FLOW = 1/2
CCW FLOW
CEPS#2
BFPS#2
GEN. AIR
COOLER 2
Total no. of
cooler
present in
the circuit.
Total flow
rate
(Cu m/Hr)
(Approx)
85 (Design)
170
10
40
24
144
Utility
TG lub. oil cooler
354
The new ACW circuit is a close circuit while the existing one is a
open type circuit.
The coolant in the new ACW circuit should be as in the existing
circuit ; i.e. raw water.
CCW circuit
Approx. Flow Rate
/cooler
Utility
(Cu m/Hr)
Total no. of
cooler present
in two unit
288 (Design)
576
7.50
11
82.5
4.50
18
7.00
28
6.00
10
60
Sample cooler
2.05
4.1
Air Heater
2.00
12.00
72
CEP Bearing
1.50
Oil centrifuge
0.50
855.6
OPTION-B
39 C
ID,FD,PA FAN#1
CCW
TANK#1
GEN. AIR
COOLER 1
A
C
W
R
35 C
U 1 TG LOC
A/C COMP
U 1 BFP COOLERS
ACWP
To
Outfall
A
C
W
S
ELIMINATION
OF
HEAT
EXCHANGERS
REDUCTION
OF
ACW FLOW
C
C
W
S
EXPECTED
CCW
FLOW - 2
Pumps
U 2 MILL COOLERS
Limited High
Temp return
to Ganges
COMPRESSOR
CEPS#1
U 1 MILL COOLERS
FROM
CWP
39 C
BFPS#1
U 2 BFP COOLERS
U 2 TG LOC
CCWP
B
Blow Down
ID,FD,PA FAN#2
CEPS#2
BFPS#2
GEN. AIR COOLER 2
C
C
CT#2 W
R
35 C
A
C
W
R
EXPECTED
ACW FLOW
1 Pump
CCW
TANK#2
Flow rate
(Cu m/Hr)
855.6
40
144
1039.6
Flow rate
(Cu m/Hr)
170
170
OPTION-C
COMPLETE TRANSFER OF ACW LOAD TO CCW
&
CONVERSION OF THE ENTIRE CCW CIRCUIT TO
COOLING TOWER
39 C
ID,FD,PA FAN#1
GEN. AIR
COOLER 1
A
C
W
R
35 C
U 1 TG LOC
ACWP
To
Outfall
High Temp
return to
Ganges
ELIMINATED
A/C COMP
U 1 BFP COOLERS
FROM
CWP
39 C
COMPRESSOR
CEPS#1
U 1 MILL COOLERS
CCW
TANK#2
BFPS#1
A
C
W
S
ELIMINATION
OF
HEAT
EXCHANGERS
CCWP
C
C
W
S
B
CT#2
C
EXPECTED
CCW
FLOW - 2
Pumps
35 C
A
C
W
R
NO ACW
SYSTEM
REQUIRED
CCW
TANK#1
U 2 MILL COOLERS
Blow Down
ID,FD,PA FAN#2
U 2 BFP COOLERS
CEPS#2
U 1 TG LOC
BFPS#2
GEN. AIR COOLER 2
C
C
W
R
Total no. of
cooler present in
two unit
Total flow
rate
(Cu m/Hr)
288 (Design)
576
Compressor
7.50
11
82.5
4.50
18
7.00
28
6.00
10
60
Sample cooler
2.05
4.1
Air Heater
2.00
12.00
72
1.50
Oil centrifuge
0.50
85 (Design)
170
10
40
24
144
1209.6
Technical analysis:
Energy savings.
Requirement for existing system
345.37 KW
2.887 MU/Yr#1
281.76 KW
2.417 MU/Yr
CT pumps.
CT fans.
2x25=50 KW#3
Total requirement for new system(Option C)
0.47MU/Yr
#2:
#3: This is a tentative value. This value has been assumed after
comparing the flow capacity with existing Cooling towers fan rating of
other generating stations.
Financial analysis:
Investment required:Cooling tower and auxiliaries.
New CT pumps.
Total
Approx .annual savings by implementation of new system
(Option-C): Rs/-28.2 lakhs
Simple payback period:
CONCLUSION:
The design specification of the CT fan and overall cost of this project is
under consideration of the cooling tower manufacturer and MMDSouthern Generating Station.
Condition for economic viability of the project
Project will be viable if the power saving achieved through this
project is paid back within 24 months.
# Use of the existing CCW pumps in the CT based cooling system
can add on to the enhancement of the payback period of the project.