You are on page 1of 22

IV

Rules for Classification and Construction


Industrial Services

Offshore Technology

Guideline for the Certification of Blow-Out Preventers

Edition 2011

The following Rules come into force on May 1st, 2011


Germanischer Lloyd SE
GL Noble Denton
Brooktorkai 18, 20457 Hamburg, Germany
Phone: +49 40 36149-750
Fax: +49 40 36149-280
glo@gl-group.com
www.gl-group.com
"General Terms and Conditions" of the respective latest edition will be applicable
(see Rules for Classification and Construction, I - Ship Technology, Part 0 - Classification and Surveys).
Reproduction by printing or photostatic means is only permissible with the consent of
Germanischer Lloyd SE
GL Noble Denton.
Published by: Germanischer Lloyd SE, GL Noble Denton
Printed by: Gebrder Braasch GmbH, Hamburg

IV Part 6
GL 2011

Section 1
Certification of Blowout Preventers

Chapter 8
Page 1 of 20

Table of Contents
Section 1 ................................................................................................................................................................. 3
Certification of Blowout Preventers .................................................................................................................... 3
1.

Scope of Equipment.................................................................................................................................. 3

2.

Certification Process................................................................................................................................. 3

2.1

Basis for Certification............................................................................................................................... 3

2.2

Scope of Certification ............................................................................................................................... 3

2.3

Issue of Certificate.................................................................................................................................... 3

2.4

Operational Records ................................................................................................................................. 3

2.5

Validity of the Certification...................................................................................................................... 3

3.

Certification of BOPs Built under Witness of GL .................................................................................... 6

3.1

General Notes ........................................................................................................................................... 6

3.2

Witness during Manufacture..................................................................................................................... 6

4.

Certification of BOPs not Built under Witness of GL .............................................................................. 6

4.1

General Notes ........................................................................................................................................... 6

4.2

Certification Procedure ............................................................................................................................. 6

5.

Inspections to Maintain the Validity of a Certificate ................................................................................ 7

5.1

Types of Inspection................................................................................................................................... 7

5.2

Explanations and General Requirments.................................................................................................... 7

5.3

Performance of Inspections ...................................................................................................................... 7

6.

Quality Management and Workmanship .................................................................................................. 7

Section 2 ................................................................................................................................................................. 8
Principles, Normative References, Conditions, Documents .............................................................................. 8
1.

General Principles..................................................................................................................................... 8

2.

Rules and Regulations to be Considered .................................................................................................. 8

2.1

Rules of Germanischer Lloyd ................................................................................................................... 8

2.2

Internationally Recognised Codes and Standards..................................................................................... 8

3.

Safety, Environmental and Process Conditions ........................................................................................ 9

4.

Documents for Examination ..................................................................................................................... 9

4.1

Types of Documents ................................................................................................................................. 9

4.2

Components and Subassemblies ............................................................................................................... 9

5.

Failure Mode and Effect Analysis (FMEA)............................................................................................ 10

5.1

General.................................................................................................................................................... 10

5.2

Description of Subsystems Relevant for the Analysis ............................................................................ 10

5.3

Block Diagrams of Relevant Subsystems ............................................................................................... 10

5.4

Analysis of the Relevant Subsystems ..................................................................................................... 10

5.5

Tabular Worksheet.................................................................................................................................. 11

5.6

Assumptions and Defined Limits for the FMEA .................................................................................... 11

5.7

Management of Change .......................................................................................................................... 11

5.8

Conclusions ............................................................................................................................................ 11

5.9

FMEA-based Test Program .................................................................................................................... 11

Chapter 8
Page 2 of 20

Section 1
Certification of Blowout Preventers

IV Part 6
GL 2011

Section 3 ............................................................................................................................................................... 12
Design and Manufacture of Blowout Preventers.............................................................................................. 12
1.

Scope ...................................................................................................................................................... 12

2.

BOP Stack............................................................................................................................................... 12

2.1

Pipe Rams ............................................................................................................................................... 12

2.2

Blind Shear Rams ................................................................................................................................... 12

2.3

Annular BOP .......................................................................................................................................... 12

2.4

Connectors .............................................................................................................................................. 12

3.

Guide Frame Structure............................................................................................................................ 12

4.

Equipment under Pressure ...................................................................................................................... 12

5.

Control Systems...................................................................................................................................... 13

5.1

Design Review........................................................................................................................................ 13

5.2

Hydraulic Control Units (HCU) ............................................................................................................. 13

5.3

Electrical Control Units .......................................................................................................................... 13

5.4

Subsea Control Pods ............................................................................................................................... 14

5.5

Umbilicals............................................................................................................................................... 14

5.6

Accumulators.......................................................................................................................................... 14

5.7

Surface Control Stations ......................................................................................................................... 14

5.8

Control Station Locations ....................................................................................................................... 14

5.8.1

Control Station Functions ....................................................................................................................... 14

5.9

Control System Response Times ............................................................................................................ 15

6.

Contingency Systems.............................................................................................................................. 15

6.1

Remotely Operated Vehicles (ROVs)..................................................................................................... 15

6.2

Deadman System .................................................................................................................................... 15

6.3

Auto-Shear System ................................................................................................................................. 15

6.4

Acoustic Control System ........................................................................................................................ 15

7.

Choke and Kill System ........................................................................................................................... 15

Section 4 ............................................................................................................................................................... 16
Inspection and Test of Blowout Preventers ...................................................................................................... 16
1.

Inspections during Manufacture and Assembly...................................................................................... 16

1.1

Quality Plan ............................................................................................................................................ 16

1.2

Inspection and Test Plan (ITP) ............................................................................................................... 16

1.3

Non-Destructive Testing (NDT) ............................................................................................................. 16

1.4

Pressure Test........................................................................................................................................... 16

2.

Factory Acceptance Test (FAT).............................................................................................................. 16

3.

Site Integration Test (SIT) ...................................................................................................................... 16

4.

Annual Inspections ................................................................................................................................. 17

5.

Inspections for Re-Certification.............................................................................................................. 17

6.

Extraordinary inspections after Modification, Repair or Major Overhaul.............................................. 17

Appendix 1........................................................................................................................................................... 19
National Regulations........................................................................................................................................... 19

IV Part 6
GL 2011

Section 1
Certification of Blowout Preventers

Chapter 8
Page 3 of 20

Section 1
Certification of Blowout Preventers
1.

Scope of Equipment

These guidelines are applicable to the design, construction, and inspection of blowout preventers
(BOPs), which are to be certified by Germanischer
Lloyd (GL), including their power supply interfaces
and control and monitoring system.
Blowout preventers include:
Main body and various types of hydraulic rams
and/or seals and the guide frame structure,
which together form the BOP stack;

elements, and control, monitoring and interfacing


equipment.
2.3

Issue of Certificate

After successful completion of the certification


activities the certificate will be issued by GL. The
certificate shall be kept on the site where the BOP
is deployed.
2.4

Operational Records

Interfaces to connect wellheads and lower marine riser packages/risers;

A BOP is required to carry an operational record


file in which details of the operational history (site,
environmental and process parameters, maintenance, damages, repair) and BOP test reports are
entered. The operational records shall be submitted
to the GL inspector on request.

Interfaces to connect umbilicals for external


power supply, control and monitoring;

2.5

Hydraulic accumulators and electrical batteries


forming the subsea power supply system;

Interfaces to allow underwater manipulation by


a remotely operated vehicle (ROV);
Choke and kill system including manually and
remotely controlled valves;
Power Supply and Control System.

2.

Certification Process

The certification process comprises a design review


and various stage inspections during the manufacturing of components, the assembly of the BOP
stack and the commissioning of the completed system. Certificates issued need to be renewed and
reconfirmed in regular intervals, at least every five
years, after annual inspections have been regularly
conducted with success.
2.1

Basis for Certification

The following guidelines constitute the basis for the


certification of blowout preventers. For requirements not defined in these guidelines, other rules
and guidelines of GL shall be applied as far as they
are applicable. The latter include Rules for Materials and Welding as well as other Rules issued by
GL.In addition, internationally accepted codes and
standards form the basis of the certification. Details
are referenced in Section 2, para 2.2.
2.2

Scope of Certification

Certification covers the entire BOP stack, including


its machinery components, power supply, structural

Validity of the Certification

(1) The validity of a certificate is limited to five


years. The certificate will be maintained and extended in its validity as long as the BOP is subjected to all prescribed inspections and tests, and
any modifications and repairs found to be necessary
are carried out to the satisfaction of GL.
(2) If the BOP is not subjected to the prescribed
inspections and tests at their due dates the certificate will be suspended. However, when an inspection becomes due while the BOP is in use, the inspection may be deferred until the well is completed.
(3) If the BOP has sufficient damage affecting the
certification or if such damage may be assumed an
inspection and test shall be conducted before the
BOP is redeployed. GL shall be notified of such a
situation in due course.
(4) Where it is found that the BOP no longer
complies with the requirements on which the certificate was issued, and if the operator fails to carry
out the repairs or modifications considered necessary by GL within a specified period to be agreed
upon, the certificate will expire.
(5) If the repairs and modifications required by
GL have been carried out and the BOP is subjected
to a re-certification inspection or an extraordinary
inspection the original certification may be reinstated. The inspection is to be carried out in accordance with the scope for re-certification inspections
or extraordinary inspections respectively, refer to
section 4, para 5 and para 6.

Chapter 8
Page 4 of 20

Section 1
Certification of Blowout Preventers

(6) The validity of a certificate of a laid-up BOP


continues unchanged. On request, any inspections
which become due may be deferred until the BOP
is reactivated for service. In these circumstances,
the total scope and extent of inspections and test
required thereafter, shall be determined by GL on a
case-to-case basis.
(7) If a certificate has for some reason expired or
has been withdrawn by GL, such a certificate shall

IV Part 6
GL 2011

be returned to GL.
(8) Should the BOP and its systems have had any
form of modification since its initial delivery from
manufacturer, then a design review incorporating
said modifications shall be conducted.
(9) Any damage and subsequent repairs shall be
subject to design review with the same parameters
as a design review for modifications.

IV Part 6
GL 2011

Section 1
Certification of Blowout Preventers

Fig. 1.1 Graphical presentation of the certification process

Chapter 8
Page 5 of 20

Chapter 8
Page 6 of 20

Section 1
Certification of Blowout Preventers

3.

Certification of BOPs Built under


Witness of GL

3.1

General Notes

(1) The application for certification of a BOP is


to be submitted to GL in writing by the manufacturer or operator.
(2) A document register shall be submitted as
early as possible, indicating the specifications,
calculations, drawings and data sheets, which are
available, or will become available, for review in
the course of the project.
(3) All documents describing the BOP are to be
submitted in triplicate to GL in case of paper copies. Alternatively, a single electronic submission for
examination is acceptable.
(4) Alterations to documents and drawings approved by GL are subject to a repeated approval of
GL before any works commence.
(5) An Inspection and Test Plan (ITP) is to be
submitted to GL for approval and mark-up of intervention points (monitor, witness, hold) to be attended by a GL Inspector and the designated Inspection Office is to be advised in good time of
tests to be performed under the witness of GL.
(6) Upon the completion of the construction
works and successful testing of the BOP, GL will
issue the certificate.
3.2

Witness during Manufacture

(1) Materials for new constructions, replacements


and repaired parts shall be tested as defined in the
GL Rules for Materials, or other proven codes and
standards acceptable to GL.
(2) Parts of the BOP requiring inspection and
tests witnessed by GL will be checked during
manufacture for conformity with the approved
documents.
(3) The separate components of the BOP are to be
tested in the manufacturers premises for mechanical strength and, where appropriate, for functionality. For components of novel design which do not
yet have a proven track record when incorporated
into a BOP, GL may demand more extensive tests.
(4) The GL inspector will witness the assembly
of the BOP stack and the installation of the machinery, control, monitoring and interfacing components as per the quality control plans and inspection
and test plans. The workmanship will be examined
and the required strength, tightness and functional
tests shall be carried out in his presence.

IV Part 6
GL 2011

(5) Upon completion of the assembly, the BOP,


including all structural elements and assembled
components, shall be tested in accordance with the
details set out in section 4 of these guidelines.
(6) To enable the GL inspector to fulfil his duty,
he shall be granted free access to the BOP and to
the workshops where parts requiring inspection and
tests witnessed by GL are manufactured, assembled
or tested. The necessary staff and equipment shall
be provided.

4.

Certification of BOPs not Built under Witness of GL

4.1

General Notes

(1) The application for the certification of a BOP


not built under the witness of GL is to be submitted
to GL in writing.
(2) All documents related to the BOP are to be
submitted for examination with the application for
certification. The scope and depth of examination
will be in accordance with sections 2, 3 and 4 of
this guideline.
(3) Existing certification, its validity and any recommendations which have been made conditional
upon the existing certification, are to be submitted
together with the application.
4.2

Certification Procedure

(1) For admission to certification, the BOP shall


be inspected in accordance with the provisions of
an inspection for re-certification, refer to section 4,
para 5.
(2) If the BOP holds a valid certificate of another
recognised Classification Society, the scope and
depth of the inspections and tests of individual parts
may be deferred to the due dates for annual inspection.
(3) A certificate will be issued on the basis of
satisfactory results from the examination of documentation and on the basis of satisfactory inspection and test results witnessed by a GL inspector
and documented in relevant inspection reports.
(4) Once a BOP has received a GL certificate, the
same regulations will apply as for BOPs built under
the witness of GL.

IV Part 6
GL 2011

Section 1
Certification of Blowout Preventers

5.

Inspections to Maintain the Validity


of a Certificate

5.1

Types of Inspection

(1) A BOP, which is certified by GL is to be subjected to the following regular inspections, if the
validity of the certificate is to be maintained:
Annual Inspection, see section 4, para 4;
Inspection for recertification after five years, see
section 4, para 5;
Extraordinary Inspection, where the BOP or
some of its components have suffered damage
liable to affect serviceability and, therefore,
safety, see section 4, para 6.
(2) GL reserves the right to demand extraordinary
inspections. Such inspections may be credited
against prescribed regular inspections.
5.2

Explanations and General Requirments

(1) The designated inspection office is to be given


timely notice when regular inspections become due
or when it is intended to carry out repairs or modifications, so that the work can be witnessed.
(2) Equipment and components are to be arranged
so that they are accessible for inspections on board.
Where this is either not possible or would involve
inappropriate efforts, inspections may also be performed, upon application, in the manufacturers
works or in another authorised workshop.
(3) The results of each inspection together with
any special requirements upon which the maintenance of certification or its validity is conditional,
will be attached to the certificate.
(4) Where parts are damaged or worn to such an
extent that they no longer comply with the requirements of these guidelines or the applicable codes
and standards, they shall be repaired or replaced.
(5) Where defects are repaired on a temporary
basis or where GL agrees that repairs or replacements are not immediately necessary, the certificate
and its validity may be confirmed for a limited
period of time. Such limitation will be attached to
the certificate and will be removed once all the
necessary works have been carried out.

5.3

Chapter 8
Page 7 of 20

Performance of Inspections

All inspections are to be performed in accor-dance


with prescribed procedures against predefined acceptance criteria as outlined in inspection and test
plans approved by GL.
Where the operational and functional particulars
differ from the standard case, the scope of inspection shall be adjusted accordingly in coordination
with GL. The detailed scope of the inspections and
tests is addressed in section 4 of this guideline.

6.

Quality Management and Workmanship

(1) The manufacturer/supplier of a BOP shall


apply a valid quality management system, such as
ISO 9001 or equivalent.
(2) As far as required by such a QMS, all components shall be checked and inspected by the manufacturers own personnel for completeness, correct
dimensions and faultless workmanship during fabrication, assembly and completion.
(3) Afterwards, all components and equipment
shall be presented to GL for inspection in suitable
sections and with proper access; for pressure testing
normally in uncoated conditions.
(4) The GL inspector may reject components that
have not been adequately prechecked and may
require the resubmission upon successful completion of such prechecks and any resulting corrective
actions.
(5) All significant details concerning quality and
functionality shall be reflected in the manufacturing
documents and shall be presented to GL during
inspections.
(6) If, due to insufficient or missing information
in the detail documents, the quality and functional
particulars of a component are in doubt, GL may
require improvements. This is valid for supplemental or additional parts even when at the time of
document approval these were not required or could
not be required due to lack of available information.

Chapter 8
Page 8 of 20

Section 2
Principles, Normative References, Conditions, Documents

IV Part 6
GL 2011

Section 2
Principles, Normative References, Conditions, Documents

(1) BOPs are to be designed and constructed in


such a way that failure of single component cannot
give rise to a safety critical situation.

(2) GL reserves the right to impose demands in


addition to those mentioned in Rules and Guidelines in respect of all types of BOPs when considered necessary due to new knowledge or experience
becoming available or to sanction deviations from
Rules and Guidelines in specially justified cases.

(2) BOPs and their components shall be designed


to meet the service conditions stated in the specification.

2.2

1.

General Principles

(3) BOPs shall be designed and built to ensure


safe operation and facilitate adequate inspection,
maintenance and repair.
(4) A consistent set of codes and standards shall
be selected for the design and construction of
BOPs, avoiding overlaps, gaps and contradictions.
(5) The codes and standards applied should be the
latest revision available.

Internationally Recognised Codes and


Standards

Codes and standards applicable to the certification


of subsea well control equipment may include:
API Spec 6A/ISO 10423, Specification for
Wellhead and Christmas Tree Equipment;
API Spec 16A/ISO 13533, Specification for
Drill-through Equipment;
API 16C, Specification for Choke and Kill Systems;
API Spec 16D, Specification for Control Systems for Drilling, Well Control Equipment, and
Control Systems for Diverter;

2.

Rules and Regulations to be Considered

BOPs and their components shall always be designed, built, and operated to meet the national laws
and statutory requirements in force in the respective
countries where they are to be used. Some examples of relevant legislation are referenced in appendix 1.
2.1

Rules of Germanischer Lloyd

The following GL Rules are valid as additional


requirements for the certification of BOPs:
GL-Rules II - Materials and Welding, Parts 1 - 3
GL-Rules IV Industrial Services, Part 6 - Offshore Technology
GL Rules I Ship Technology, Part 5 Unmanned submersibles (ROV, AUV) and Underwater Working Machines
Designs differing from GL-Rules may be permitted, if they provide equivalent levels of safety.
(1) Where the design of a BOP or its components
is based on new principles or technologies, which
have not yet been sufficiently tested in practical
operation, GL reserves the right to demand additional submission of documentation and the execution of additional special tests.

API Spec 16F, Specification for Marine Drilling


Riser Equipment;
API Spec 17D, Subsea Wellhead and Christmas
Tree Equipment;
API RP 49, Recommended Practice for Drilling
and Well Servicing Operations Involving Hydrogen Sulphide;
API RP 53, Recommended Practices for Blowout Prevention Equipment Systems for Drilling
Wells;
API RP 59, Recommended Practice for Well
Control Operations;
ISO 13628-4, Petroleum and Natural Gas Industries - Design and Operation of Subsea Production Systems - Part 4: Subsea Wellhead and
Tree Equipment
ISO 13628-5, Petroleum and Natural Gas Industries - Design and Operation of Subsea Production Systems - Part 5: Subsea Umbilicals
ISO 28781, Petroleum and Natural Gas Industries - Drilling and Production Equipment - Subsurface Barrier Valves and Related Equipment
NACE MR 01-75, Petroleum and Natural Gas
Industries Materials for Use in H2SContaining Environments in Oil and Gas Production.

IV Part 6
GL 2011

3.

Section 2
Principles, Normative References, Conditions, Documents

Safety, Environmental and Process


Conditions

All safety, environmental and process conditions


shall be submitted with the application, based on
the codes and standards mentioned above. If information is not known or complete at time of submittal, GL shall be notified when such data can be
expected.

4.

4.2

(1)

GL reserves the right to request documents and/or


records in addition to those mentioned here below,
as needed, to confirm that equipment, systems, and
components under examination are in compliance
with statutory regulations, codes and standards, GLRules and other normative references for the specified operating conditions.
Types of Documents

Components and Subassemblies

The documents listed above shall be submitted for:

Documents for Examination

4.1

BOP stack comprising, but not limited to:


x

Annular BOP

Pipe Rams

Shear Rams

Bonnets

Actuators and Stems

Connectors to Wellheads and Lower Marine Riser Package

Guide Frame Structure

(2) BOP Control System comprising, but not


limited to:

The types of documents to be submitted to GL for


independent design review shall comprise, but not
be limited, to the following:

Overall Control System

Surface control Stations

(1) Design specifications and data sheets, including material specifications;

Accumulators

Actuators

Hydraulic Hoses

Valves and Fittings

Hydraulic Power Units

Control Pods

(2) Design drawings, schematics, calculations,


including general arrangement and assembly drawings;
(3)

BOP system configuration;

(4)

Quality Plan (QP);

(5)

Inspection and Test Plan (ITP);

(6)

Procedures for

Chapter 8
Page 9 of 20

(3)

Contingency Systems
x

Interface Panels for docking of and intervention by ROVs

Function Tests

Dead Man System

Factory Acceptance Test (FAT)

Auto Shear System

Site Integration Test (SIT)

Acoustic Signal Transmission System, if


installed

Pressure Tests (internal and external overpressure)

(7)

Material Test Records (MTR);

(8)

NDT Records;

(9)

Certificates of Conformance;

(10) Service History (if applicable) regarding:

(4) Choke and Kill System comprising, but not


limited to:
x

Valves and Fittings

Choke

Operation and Maintenance

Modifications and Repairs

Choke and Kill Lines

Preservation and Storage

Choke and Kill Hoses

Chapter 8
Page 10 of 20

Section 2
Principles, Normative References, Conditions, Documents

IV Part 6
GL 2011

5.

Failure Mode and Effect Analysis


(FMEA)

The system descriptions are to be complemented by


block diagrams as mentioned below.

5.1

General

5.3

(1) A FMEA shall be executed in an early stage


during the design in order to allow for system
modifications in due time. A tabular form, e. g.
according to IEC 60812, is to be used.
(2) The objective of the FMEA is to identify
possible failures in the total system, in subsystems
and in components of the complete BOP system,
and to describe the effects and consequences of
such failures. Additionally, the FMEA should highlight any measures proposed to be taken during the
design stage to alleviate the likelihood of occurrence and the severity of the effects of the respective failure modes.

Block Diagrams of Relevant Subsystems

For each relevant subsystem, a block diagram shall


be established. This block diagram shall contain the
essential information of the system, which is required for the failure analysis, and normally comprises:
Definitions of the subsystems;
All essential components of the subsystems;
Interfaces between the components of the subsystems;
Interfaces to or from other subsystems (typical
for hydraulics and controls);
Arrangements for control of the total system;

(3) Equivalent safety studies (e. g. HAZOP) may


be acceptable, provided an equivalent stringence
with regard to systematics and coverage can be
demonstrated.
5.2

Description of Subsystems Relevant for


the Analysis

(1) The FMEA shall represent an independent


document and be understandable without consulting
further documentation. This means that the basic
functions of all relevant subsystems shall be described together with details of the installed redundancies and especially the interfaces between the
subsystems.
(2) The description shall provide the operating
personnel with a good overview of the structure and
the functionality of the relevant subsystems of a
BOP. For all subsystems, typical failure modes and
their effects on the overall function of the BOP
shall be indicated. The corrective actions to manage
these failures and their effects shall be described.

Supplies from outside the total system;


Further aspects depending on the actual design
of the BOP stack.
5.4

Analysis of the Relevant Subsystems

The following essential aspects of each relevant


subsystem shall be analysed. Any further aspects
that are identified during the execution of the analysis shall also be analysed. See sample work sheet
(Table 2.1):
Failure of subsystems;
Malfunction of subsystems;
Failure of components in a subsystem;
Malfunction of components;

(3) For BOPs, the following subsystems are relevant for maintaining the overall functional integrity:

Interface failures between the subsystems, a


subsystem and its components as well as between components themselves. Interface analysis is of particular importance, as experience
shows that many failures are created due to lack
of information about data, medium and power
transferred or how failures are spread via the interfaces to other subsystems and components;

Guide frame;

Hidden failures and potential means to make


them self-revealing;

Systems for control and monitoring;


Vessels and apparatus under pressure;
Piping systems, fittings;
Umbilicals;
Electrical installations;
Emergency power supply;
Interface equipment for umbilicals and ROVs.

Practicality of alarms for certain failures and


arrangement of periodic testing where alarms
are not suitable or practical;
Failures initiated by external influences which
may lead to simultaneous failure of redundant
subsystems (common cause failures), like
changed environmental conditions and their
control, voltage and frequency fluctuations in
power supply, contamination of supply media,
etc.

IV Part 6
GL 2011
5.5

Principles, Normative References, Conditions, Documents

Tabular Worksheet

The analysis shall be documented in tabular form.


A typical work sheet is shown in Table 2.1. Similar

ID No.

Subsystem
Component

Type of
Failure

Failure
Cause

Failure
Detection

Chapter 8
Page 11 of 20

forms are acceptable as long as they are practical


and follow the formats laid out in IEC 60812. the
analysis shall consider all operational modes.

Consequences for
Total System

Consequences for
Subsytem or
Component

Failure
Correction

Remarks

1
2
3
4
Table 2.1 Sample FMEA Worksheet

5.6

Assumptions and Defined Limits for the


FMEA

For the FMEA, the assumptions are to be defined


which set the frame and define the limits. Typical
assumptions are:
The operating personnel are qualified and
trained to safely and competently operate the
equipment;
The settings and switching operations prescribed in the operations manual are followed
by the operating personnel;
The power supply system has a well defined
degree of availability through redundancy.
5.7

Management of Change

In case of changes, modifications, repairs to the


design and construction of the BOP, the relevant
sections of the FMEA shall be updated accordingly.

In case of changes of the environmental and process


parameters to values outside the design and operating envelope, the relevant section of the FMEA
shall be changed accordingly.

5.8

Conclusions

The FMEA shall contain a summary of the results


of the analysis for the BOP. In addition, it should
contain a listing of the main failures which may
occur during the operation of the BOP. Training
measures to handle events in case of such failures
are to be proposed for the operating personnel
aboard the drilling unit. A periodic check of the
FMEA including practical trials is recommended.
5.9

FMEA-based Test Program

A test program shall be established that is aligned


with the FMEA. The purpose of this program is to
verify the assumptions and the expected operational
behaviour of the BOP as defined in the FMEA.
The test program shall consider typical failure
modes in the relevant systems and components
including the worst case failure. All operational
modes of the BOP shall be considered.
The test program shall be agreed with GL and shall
specify in detail how the test will be carried out
and/or how the simulation is done as an alternative
for certain aspects of functional behaviour.
These specified tests shall be included in the factory
acceptance test procedure.

Chapter 8
Page 12 of 20

Section 3
Design and Manufacture of Blowout Preventers

IV Part 6
GL 2011

Section 3
Design and Manufacture of Blowout Preventers
1.

Scope

For the design of the BOP and all its additional systems and components, a detailed specification shall
be provided, which shall include the limiting pressure and temperature conditions.
Blowout preventers and additional pressurised
equipment shall be designed in accordance with API
RP 53 Recommended Practices for Blowout Prevention Equipment Systems for Drilling Wells and
additional subordinated recognised technical standards.
All materials for the construction of a BOP and all
its associated components shall be suitably selected
in accordance with the chemical and physical data of
the flowing media and shall comply with internationally recognised standards. All materials, which
may come into contact with the well fluid, shall be
suitable for sour service. The requirements outlined
in the NACE Standard MR0175/ISO 15156 are to be
observed accordingly.

2.

BOP Stack

In general, all elements of the BOP stack, including


flanges, valves, spools, adapters, clamps, etc. should
conform to the requirement of API 16A or equivalent with regard to design, fabrication, testing and
documentation.
2.1

Pipe Rams

The BOP stack shall conform to configurations illustrated in API RP 53. It shall consist of at least two
pipe rams with mechanical locking devices. Each set
of pipe rams shall be capable of closing and sealing
against at least one of the pipe sections in the hole.
Each BOP stack shall have at least one pipe ram
capable of closing and sealing against all pipe sections to be run through the BOP stack.

2.3

Annular BOP

Annular BOPs are usually mounted above the BlindShear Rams and consist of a synthetic rubber bladder reinforced with steel ribs.
Annular BOPs are either of Wedge Type or
Spherical Type. Either is acceptable insofar as they
conform to the requirements of API Spec 16A with
respect to design, fabrication, testing, and documentation.
2.4

Connectors

The BOP connectors that interface to the wellhead


and to the lower marine riser package shall conform
to the requirements of API 6A with respect to design, fabrication, testing, and documentation.

3.

Guide Frame Structure

The BOP guide frame, a four-post structure attached


to the BOP assembly, is a means for guiding the
complete BOP/LMRP assemblys primary alignment
onto the permanent guide base. The guide frame
structure also acts as the structural mounting for the
various components of the remote control system,
and the choke and kills connectors and stab subs.
The guide frame structure shall have sufficient
strength to protect the BOP stack from damage during handling and landing operations. However, the
guide frame structure should not be considered as
part of the well bore structure, because under operating conditions the BOP elements shall have the
required bending strength based on maximum riser
tension and angle.
The BOP guide frame is to be designed in accordance with AISC or another equivalent recognised
structural standard.

Pipe rams must be capable of suspending the weight


of a specified length of drill string when closed.

4.
2.2

Blind Shear Rams

Each blind shear ram must be capable in a single


operation of shearing, and sealing against pressure
from below, the largest section of the highest grade
pipe to be run in the well through the BOP when the
specified control system pressure is available.
Documentation shall be supplied verifying the fact.

Equipment under Pressure

Blowout preventers and all associated pressurised


equipment (vessels, piping, hoses, etc.) shall be designed in accordance with recognised technical standards, e. g. ASME, BS 5500, PED or equivalent.
Design conditions shall account for the maximum
working pressure and temperature.

IV Part 6
GL 2011

Section 3
Design and Manufacture of Blowout Preventers

Hoses to be connected and disconnected shall be designed with quick-release self-sealing couplings to
ensure a tight shut-off and sealing in operation and
easy handling by personnel.

5.

Control Systems

All equipment for the control and monitoring of a


BOP shall be designed and constructed in accordance with this guideline, the suitable standards (e.
g. API 6A and 16D or equivalent) and the specifications in accordance with the design and environmental conditions specified for the BOP and its
environment. Additionally, the guidance and recommendations put forth in API RP 53 should be
considered as part of the path to certification and recertification.
The BOP control system shall consist of a dual-pod
arrangement.
A second and independent system for intervention
by remotely operated vehicles (ROVs) shall be provided.

Chapter 8
Page 13 of 20

ity calculations, reservoir sizing, hydraulic and electrical analysis;


(7) Arrangements and details of control consoles,
including views and installation arrangements together with schematic plans and logic description for
all power, control and monitoring systems, including
their functions;
(8) Type and size of all electrical cables and wiring associated with the control systems, including
voltage rating, service voltage and currents, together
with overload and shortcircuit protection;
(9) Schematic plans and logic description of hydraulic and pneumatic control systems together with
all interconnections, piping sizes and materials,
including working pressures and relief valve settings;
(10) Description of all alarm and emergency tripping arrangements and functional layouts, and description of all special valves, actuators, sensors and
relays.
5.2

Hydraulic Control Units (HCU)

All equipment shall be designed, manufactured,


tested and commissioned according to the procedures of the equipment manufacturer approved by
GL and relevant regulatory requirements.

The Hydraulic Control Unit (HCU) supplies a stable,


regulated, filtered fluid. This fluid is supplied via a
system of hydraulic lines and an umbilical to BOP
mounted subsea accumulators.

5.1

The hydraulic system shall be robust and maintain


the specified pressure values and volume flows.

Design Review

The BOP Control and Monitoring System shall undergo a design review prior to the start of fabrication, which shall be conducted in accordance with
this guideline and all applicable codes and standards.
The design review of the Electrical, Instrumentation
and Control Systems shall include, but is not limited
to the following:
(1) Batteries including installation, arrangement
and details, where provided, to include charging
apparatus, ventilation and corrosion protection;
(2) Arrangement plans showing location of units
controlled, instrumentation and control devices;
(3) Specifications for control and instrumentation
equipment;
(4)

Set points for control system components;

(5) Appropriate elements addressed in the Failure


Modes and Effects Analysis (FMEA);
(6) Calculations for control systems demonstrating
the systems ability to react adequately to anticipated
occurrences, including transients. Documentation
shall include but is not limited to volumetric capac-

The HCU reservoir shall include provisions for obtaining, and maintaining, the specified cleanliness
requirement, such as drainage or circulation and
filtration capability, should the fluid become contaminated. Output fluid from the HCU reservoir
shall be prepared to a cleanliness level as defined in
SAE AS 4059. The selected cleanliness level shall
be according to the manufacturers written specification. Working fluid volumes shall comply with API
RP 53.
The HCU may be considered as a second control
panel.
5.3

Electrical Control Units

The electrical control units shall have a central control point. Alternatively, each control panel may
communicate directly and independently with each
control pod.
The electrical control unit shall be supplied with
electrical power from an uninterruptable power
supply (UPS). The UPS battery backup shall be
capable of running the system for at least two hours
after loss of main power supply. The UPS shall be
monitored from a remote manned location with, as a

Chapter 8
Page 14 of 20

Section 3
Design and Manufacture of Blowout Preventers

minimum, alarm reporting of main power supply


failure and internal UPS failure.
5.4

Subsea Control Pods

The BOP stack shall provide two completely independent and redundant control pods. Each pod shall
contain all necessary valves and controls to operate
the BOP stack functions. Each control pod shall be
colour coded (e. g. Yellow and Blue), suitable for
easy ROV identification subsea.
The failure of one subsea control pod shall not affect
the safe operation of the other pod and a means of
isolating the failed pod shall be provided.
The control pods may be retrievable or nonretrievable.
5.5

Umbilicals

In general, the subsea umbilicals ensure hydraulic


and electrical power supply, communications, and
control of the subsea control pods.

IV Part 6
GL 2011

Details of the specified drill string to be used after


BOP certification shall be used when evaluating accumlator performance, because metallurgical differences in drill string pipe from different manufacturers may require recalculation due to different shear
ram closing pressure.
A dedicated accumulator system with appropriate
volume and pressure shall be provided for BOP systems with a rapid secondary disconnect function.
Additionally, when the BOP system features a two
shear ram arrangement, volumetric calculations shall
include both sets of shear rams.
5.7

Surface Control Stations

There shall be at least two distinct and separate BOP


control stations for all BOP functions. The stations
shall be mutually independent of each other. Functions shall have physical barriers on the buttons to
prevent accidental activation of disconnect functions.
5.8

Control Station Locations

Some systems may combine hydraulic and electrical


services in one umbilical, while other systems may
separate the supply of hydraulic fluid into a rigid
conduit assembly on each riser joint.

The first control station shall be located adjacent to


the drilling console while the second control station
shall be located near the main hydraulic supply unit
for the BOP.

In each case, the electrical conductors and electrical


insulation as well as any hydraulic hose or tubing
assemblies shall not be used as load bearing components in the umbilical assembly.

If a third panel, which may have limited functionality, is installed for emergency operations, it should
be installed remote from the rig floor.

Two control umbilicals shall be provided, connecting to the two subsea control pods to the surface
control stations. Two methods of providing subsea
fluid power to the subsea pods shall be provided.
These systems may be rigid hydraulic conduits or
hydraulic umbilical hoses.
Umbilical strain relief and over-bending protection
shall be provided for the interface between umbilical
and subsea pod.
The umbilical shall be designed and fabricated in accordance with ISO 13628-5, Subsea Umbilicals, or
equivalent.
5.6

Accumulators

Accumulator systems are required for subsea BOP


stacks. The volume and pressure capacities for all
subsea accumulators shall be suitable to ensure that
specified valve closing times are met, in accordance
with API 16D or equivalent.
Accumulator calculations for Deadman, Autoshear
and some acoustic systems, which are classified as
rapid discharge systems, shall follow Method C in
API 16D.

Access to either control station shall not require personnel to cross the drill floor or cellar deck.
If any of the control stations is located in a designated hazardous area, it shall comply with the relevant codes and standards for exprotection.
5.8.1

Control Station Functions

Control station panels shall include, as a minimum


but not limited to, the following functions:
Close/open of all rams, annular preventers and
choke and kill valves;
Mechanical locking of rams;
Primary disconnect of the Lower Marine Riser
Package;
Emergency Disconnect (only on floating rigs);
Provision of audible and visual alarms for, as a
minimum, low fluid level in reservoirs, loss of
power supply and low accumulator pressure.
Enable buttons shall be provided on the panels for
all critical functions such that two-handed operations
are necessary. All functions on the panels shall be
clearly labelled.

IV Part 6
GL 2011

Section 3
Design and Manufacture of Blowout Preventers

Secondary additional protection against inadvertent


operation of riser disconnects and shear ram functions shall be provided on the control panels.
Further functions as per API 16D shall be considered.
5.9

6.2

Chapter 8
Page 15 of 20

Deadman System

A deadman system is defined as a safety system that


is designed to automatically close the blind-shear
rams in the event of a simultaneous absence of hydraulic supply and signal transmission capacity in
both subsea control pods.

Control System Response Times

For Subsea Blowout Preventers the following system response times shall be achieved under the consideration of the accumulator design and control
system internal delays:
Closing of each ram BOP shall be achieved in
less than 45 seconds;
Closing of an annular BOP shall be achieved in
less than 60 seconds;
Operating times for choke and kill valves shall
not exceed the minimum observed ram BOP
closing times;
The time to unlatch the Lower Marine Riser
Package shall not exceed 45 seconds.
For Surface Blow Out Preventers shorter times are
stipulated in API 16D and shall be observed accordingly.

Conventional measurement of response time begins


when the function is activated at any control panel
and ends when the read back pressure gauge recovers to its nominal setting. Response times are based
on fully charged accumulators, design water depth
and minimum temperatures.

6.

Contingency Systems

6.1

Remotely Operated Vehicles (ROVs)

All subsea BOPs shall be equipped with Remotely


Operated Vehicle (ROV) intervention capability.
The intervention provision shall be such that the
ROV shall be capable of closing one set of pipe
rams, closing one set of blind-shear rams, and
unlatching the lower marine riser package.

A multi-function ROV operating panel shall be


mounted in an accessible location on the BOP stack
and the panel shall be clearly marked for identification by the ROV cameras.

All ROV interfaces shall comply with the requirements of ISO 13628-8. Their markings shall comply
with the requirements of ISO 13628-1, Table B.1.

A deadman system shall be installed for BOPs used


on floating drilling units.
6.3

Auto-Shear System

An auto-shear system is defined as a safety system


that is designed to automatically shut in the well in
the event of an unplanned disconnect of the Lower
Marine Riser package (LMRP).
When the auto-shear system is armed, a disconnect
of the LMRP shall cause the auto shear system to
close the shear rams.
If, based on operator and rig procedures, the choke
and kill valves are not automatically closed in this
instance, which is an option based on API 16D, this
shall be explicitely mentioned and justified.
An auto-shear system shall be installed for BOPs
used on floating drilling units.
6.4

Acoustic Control System

Floating rigs may use an acoustic system, optionally,


in addition to deadman and auto-shear, as an emergency backup to control critical BOP functions. Accumulator requirements for this system shall meet
the recommendations for acoustic system subsea
accumulators in API 16D. Additional requirements
for this type of system can also be found in API 16D
and should be observed.

7.

Choke and Kill System

In general, all elements of the choke and kill system,


including flanges, valves, spools, adapters, clamps,
and chokes shall conform to the requirements of API
16C or equivalent.
Each of the choke or kill lines shall have two valves
of fail-to-close type, mounted in series close to the
BOP stack in a position which protects them from
dropped objects. They shall be hydraulically operated and opened against spring force.
For maximal valve closing times refer to 5.9.

Chapter 8
Page 16 of 20

Section 4
Inspection and Test of Blowout Preventers

IV Part 6
GL 2011

Section 4
Inspection and Test of Blowout Preventers
1.

Inspections during Manufacture and


Assembly

Inspections and test of BOPs shall be carried out according to the following documents, to ensure that
the BOP meets all design particulars approved by
GL:

points where the witnessing of a GL inspector is


required, he will sign the ITP once the activity is
successfully completed.
The qualifications of personnel performing NDT
shall be either included in the NDT documentation
or shall be traceable to equivalent records.

Quality Control Plan (QCP);


Inspection and Test Plan (ITP).
1.1

Quality Plan

The Quality Plan is a fundamental element of the


QA system of the BOP manufacturer.
The Quality Plan should outline all QA activities
that will be implemented within the design and fabrication procedure of the BOP and its associated
components.

1.4

Pressure test reports shall clearly show calibration


results, test medium, time of test at pressure, test
temperature, minimum test pressure required, and
actual test pressure attained. GL shall be invited well
in advance to witness pressure testing. Pressure
testing shall be performed in unpainted conditions.

2.
The quality Plan shall be specific for a project.
1.2

Inspection and Test Plan (ITP)

All inspections and tests to be carried out during


manufacture and assembly shall be listed in an Inspection and Test Plan. This ITP shall include and
outline all specific tests and inspections which have
to be performed during manufacture and assembly
with reference to test procedures, standards, specifications and acceptance criteria.
Furthermore, each test step shall provide information
about the requirements for reviewing the test documentation and the specific monitoring and witnessing points by GL.
The ITP shall be submitted to GL for review and
mark up of interventions (Monitor, Witness, Hold)
within a reasonable notification period.
1.3

Non-Destructive Testing (NDT)

All non-destructive test (NDT) reports and subsequent inspections shall be signed and dated, and be
provided as part of the BOP stack dossier. Inspection
reports shall include the name, qualifications, and
contact information of the personnel who performed
the testing. The scope of the NDT shall be as detailed on the inspection and test plan (ITP). All incidents and out of specification conditions shall be
documented along with the remedial actions taken to
correct the situation.
The ITP shall be signed and dated by the party performing the NDT, and by the manufacturer. At

Pressure Test

Factory Acceptance Test (FAT)

The BOP and all its associated equipment, including


the control systems and contingency systems shall
be subjected to a Factory Acceptance Test. All functions shall be tested during the FAT. Usually, this is
executed while the BOP stack is mounted on a
stump.
The scope of tests, the test conditions, procedures
and acceptance criteria shall be based on the service
and operating conditions and shall be submitted to
GL for review and approval well in advance.
The scope of testing shall also include those items
which result from the FMEA, refer to section 2, para
2.5.9.
Provided that certified evidence can be presented
about the capability of the shear rams to cut off the
drill string specified in the design documentation,
such a test needs not to be executed and a normal
function test of the shear ram operation is sufficient.
The FAT shall be carried out in presence of a GL inspector who shall be invited well in advance.

3.

Site Integration Test (SIT)

A site integration test shall be executed upon arrival


of the BOP at a drilling location for the first time
after completion of the FAT. The SIT has the objective to demonstrate that the BOP and all associated
control systems are fully functional on the location

IV Part 6
GL 2011

Section 4
Inspection and Test of Blowout Preventers

and are suitable for the specific well design and


drilling programme.
The SIT comprises a comprehensive stump test on
board of the drilling rig and an initial test on the seafloor.
The scope of tests, the test conditions, procedures
and acceptance criteria shall be based on the service
and operating conditions and shall be submitted to
GL for review and approval well in advance.
The initial test on the seafloor shall demonstrate, as
a minimum, that the rams, the annular preventers,
the choke and kill valves and deadman system are
functioning correctly.

Chapter 8
Page 17 of 20

with their associated control systems, including


deadman and auto-shear systems, shall be functiontested.
(11) The interfaces which allow a ROV to connect
and perform overrides shall be function tested.
(12) Hose assemblies shall be checked for visible
damages.
(13) The umbilicals shall be checked for visible
damages, cracks, deformations and corrosion.
(14) Where applicable, acoustic backup control systems shall be function tested.

The SIT shall be conducted in the presence of a GL


inspector who shall be invited well in advance.

(15) Upon successful completion of the Annual


Inspection, the validity of the certificate will be
confirmed.

4.

(16) When an annual inspection becomes due while


the BOP is in use, the inspection may be deferred
until the well is completed.

Annual Inspections

The Annual Inspection of a BOP includes at least the


following tests and checks, witnessed by GL:

5.
(1) Examination of the documents relating to the
BOP, including its surface control systems and scrutiny of the operational history with BOP test reports
and BOP maintenance records;
(2) Visual inspection of the guide frame, all fixtures, covers, lifting points, claddings, etc. for damage, cracks, deformation, corrosion attacks and fouling;
(3) Check of the measures for corrosion protection
(e. g. anodes);
(4)

The BOP is to be pressure tested on its stump.

(5) All vessels and apparatus under external or


internal overpressure, penetrations, valves, fittings
and relevant safety equipment are to be subjected to
external inspection.
(6) Check that insulation measurements have been
performed on the electrical equipment;
(7) Review of control systems and of the set points
of the alarm sensors;
(8) Change over from the main to the emergency
electrical power supply is to be tested.
(9) The accuracy of all essential instrument readings is to be checked.
(10) All rams and annual preventers and the disconnect system for the Lower Marine Riser Package

Inspections for Re-Certification

Every five years, an Inspection for Re-Certification


shall be carried out, witnessed by GL. In addition to
the annual inspections defined in para 4 above, the
following tests and examinations shall be carried
out:
(1) For vessels and apparatus under pressure,
which cannot be satisfactorily inspected internally or
for which their satisfactory condition cannot be fully
verified by internal inspection, another nondestructive test method shall be used or a hydraulic
pressure test shall be performed.
(2) Check shall be performed that accessories,
especially hose assemblies and compensators have
been changed according to the maintenance plan.
Upon satisfactory completion of the Inspection for
Re-Certification, the validity of the certificate will
be extended for another period of five years.

6.

Extraordinary inspections after


Modification, Repair or Major Overhaul

After modifications, repair or major overhaul, a BOP


shall be subjected to an extraordinary inspection,
witnessed by GL.
The scope and depth of the inspection shall be developed in close cooperation between the holder of
the certificate and GL.

Chapter 8
Page 18 of 20

Section 4
Inspection and Test of Blowout Preventers

Additionally, in case of modifications it will be


necessary to conduct a design review of those components and subsystems affected by the modifications.
The scope and depth of this design review shall be
determined by GL with the objective of confirming
the compliance of the overall system with this guideline.
The scope of inspections and tests shall be derived
from the original tests during manufacturing, the

IV Part 6
GL 2011

factory acceptance tests and the system integration


tests as outlined in para 1, 2, 3 above. Due consideration will be given to avoid the unnecessary
duplication of tests, where previous test results remain valid.
In case of repairs, the spares used shall be acceptable
to the original equipment manufacturer. Alternatively, non-OEM parts shall be subjected to a design
review and to tests as outlined in para 1, 2, 3 above,
and defined in a dedicated inspection and test plan
which shall be subject to approval by GL.

IV Part 6
GL 2011

Appendix 1
National Regulations

Chapter 8
Page 19 of 20

Appendix 1
National Regulations
This Appendix contains references to the national
regulations of some countries. These should not be
considered complete, but only as a possible starting
point for each license holder. Statutory requirements
may change any time, and should be investigated
from case to case to ensure that the references used
are current and complete.
In Australian waters, the regulators are the National Offshore Petroleum Safety Authority and also
the regions including Government of Western Australia, Department of Mines and Petroleum. Key
Regulations include, but may not be limited to:
Petroleum (Submerged Lands) Management of
Safety on Offshore Facilities Regulations 2007;
Petroleum (Submerged Lands) Management of
Well Operations Regulations 2004.
The approach requires good oil field practice supported by a Safety Case to ALARP, with independent verification.
In Brazilian waters, the regulators are Agncia Nacional do Petrleo, Gs Natural e Biocombustiveis
(ANP). Key Regulations include, but may not be
limited to:

The majority of the Drilling and Production Regulations are written in a goal- or performance-based
style with clear regulatory objectives or goals. Goaloriented regulation is a hybrid approach that includes prescriptive and goal- or performance-based
elements. The prescriptive elements are retained in
the management system elements, information requirements for reporting and in information requirements related to applications for authorisations
and well approvals.
In Danish waters, the regulator is the Danish Energy Agency. Key Regulations include, but may not
be limited to:
Offshore Safety Act No. 1424 of December 21,
2005 with subsequent amendments;
Executive Order No. 729 of 3rd July 2009;
Guidelines for the Design of Fixed Offshore
Installations 2009;
Guidelines for Drilling Exploration 1988
(2009), attachment to A Guide to Hydrocarbon
Licenses in Denmark.

Resolution No. 43;


Technical resolution Safety Management System
(SGSO);
CONAMA Resolution No. 23: Licensing of
drilling and production activities.
The approach is goal-setting, with reliance on industry standards and the requirement for risk analysis.
In Canadian waters, the regulators are the National
Energy Board, the Canada Nova Scotia Offshore
Petroleum Board and the Canada Newfoundland &
Labrador Offshore Petroleum Board. Key Regulations include, but may not be limited to:

The approach requires a Safety Case to ALARP and


the use of recognised standards.
In Indonesian waters, the regulator is effectively
BP MIGAS and the requirements are usually set in
Production Sharing Contracts.
It is understood that the approach requires best oilfield practice.
In Norwegian waters, the regulators are the Norwegian Petroleum Directorate (NPD) and the Petroleum Safety Authority (PSA). Key Regulations include, but may not be limited to:

Canada Oil and Gas Operations Act (COGOA);


SOR/2009-315 Canada Oil & Gas Drilling and
Production Regulations;
Draft Safety Plan Guidelines;
Draft Drilling and Production Guidelines.
Section 36.1 of the Safety Plan Guidelines lists Industry Standards and Practices that may be used;
these are mostly API, together with NACE Standard
MR0175.92m Item No. 53024 & NORSOK 010;

Regulations Relating To Design And Outfitting


Of Facilities Etc. In The Petroleum Activities
(The Facilities Regulations) Chapter IV-I, Sections 48 55 and Guidelines thereto. This references NORSOK D-001, D-002 and D-010, with
additional requirements to D-001;
Regulations Relating To Conduct Of Activities
In The Petroleum Activities (The Activities
Regulations) Section 9 and Guidelines thereto
Chapter 4 / Sect. 30a and Chapter 7 /Section 46;

Chapter 8
Page 20 of 20

National Regulations

Regulations Relating To Material And Information In The Petroleum Activities (The Information Duty Regulations) Chapter III Section 7 &
Guideline thereto. Refers to reporting according
to NORSOK D-010;
There are extensive references to other standards
(mainly API & NORSOK but some from ANSI,
ASME, ISO, NACE, NS & TBK).
An overall objective for drilling and well activities
will be the requirement that no single failure shall
entail a life threatening situation for the involved
personnel, or significant damage to material and the
environment. This applies to both operations errors
and to failure in connection with the equipment used
directly in operations, as well as equipment with
auxiliary functions. Safety systems are to be provided with two independent levels of protection to
prevent or minimise the effects of a single malfunction or fault in the process equipment and piping
system, including their controls. The two levels of
control are to be provided by functionally different
types of safety devices to reduce the probability of
common cause failures.
In UK waters, the regulator is the Health & Safety
Executive (HSE). Key Regulations include, but may
not be limited to:
SI 1996/913 The Offshore Installations and
Wells (Design and Construction, etc.) Regulations 1996 (DCR).
The approach uses a Safety Case to ALARP. The
Duty Holder must show that the Performance Standards are suitable and sufficient, which is done
through the application of industry standards or
alternatively more detailed assessment, to show that
the residual risk not removed by the safety system is
as low as reasonably practicable (ALARP). Wells
are covered by a separate Well Examination Scheme
under DCR requiring examinations by independent
and competent persons.

IV Part 6
GL 2011

In US waters, the regulator under the Department of


Interior (DOI) is the Bureau of Ocean Energy Management, Regulation and Enforcement (BOEMRE).
The BOEMRE has two separate functional bureaus:

Bureau of Ocean Energy Management (BOEM)


will be responsible for managing development of
the nations offshore resources;
Bureau of Safety and Environmental Enforcement (BSEE) for enforcing safety and environmental regulations.
Key regulations include, but may not be limited to:

30 CFR Part 250 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf;
NTL No. 2010-N10 US Department of the Interior BOEMRE, National Notice to Lessees and
Operators of Federal Oil and Gas Leases, Outer
Continental Shelf, "Statement of Compliance
with Applicable Regulations and Evaluation of
Information Demonstrating Adequate Spill Response and Well Containment Resources", November 08, 2010;
NTL No. 2009-G07, US Department of the Interior Minerals Management Service Gulf of Mexico OCS Region, National Notice to Lessees and
Operators of Federal Oil and Gas Leases, Outer
Continental Shelf, Gulf of Mexico OCS Region,
"Location of Choke and Kill Lines on Blowout
Preventer Stacks", May 1, 2009.
The regulations require adherence to a number of
API RP's and Specs.

You might also like