Professional Documents
Culture Documents
IV Industrial Services
7 Offshore Substations
Edition 2013
The following Rules come into force on 1 October 2013.
Germanischer Lloyd SE
Head Office
Brooktorkai 18, 20457 Hamburg, Germany
Phone: +49 40 36149-0
Fax: +49 40 36149-200
headoffice@gl-group.com
www.gl-group.com
"General Terms and Conditions" of the respective latest edition will be applicable
(see Rules for Classification and Construction, I - Ship Technology, Part 0 - Classification and Surveys).
Table of Contents
Table of Contents
A Objectives
A.1 These Rules have been developed primarily to assist in the development of new installations
of offshore wind farm high voltage offshore substations.
These Rules are applicable to the design, fabrication, installation and commissioning of offshore renew-
able energy related platform installations like high voltage AC and DC substations and the associated
accommodation platforms.
B Definitions
B.1 Administration/Authorities
Administration or Authorities is the Government of the State whose flag the unit or installation is entitled to
fly or the State under whose authority the unit or installation is operating in the specific case.
B.4.3 Manning
The following types of manning have to be distinguished.
It is recognized that the category definitions below include a degree of judgment. The owner of the struc-
ture shall determine the applicable category prior to the design of a new structure or the assessment of
an existing structure and shall obtain the agreement of the administration where applicable
B.4.3.3 Unmanned
The unmanned category refers to a platform that is only manned for occasional inspections, maintenance
and/or modification visits. For categorization purposes, a platform shall not be categorized as unmanned
unless
• visits to the platform are undertaken for specific planned inspection, maintenance or modification
operations on the platform itself,
• visits are not expected to last more than 24 h during seasons, when severe weather can be ex-
pected to occur,
• the evacuation criteria for manned evacuated platforms are also met,
• under normal operating conditions the platform is capable of full autonomous and remotely operated
service.
A platform in this category may also be described as “not normally manned”.
B.5.1 General
A mode of operation is a condition or manner in which a unit or installation may operate or function while
on location or in transit. Distinction is to be made between the different modes of operation in connection
with safety factors and other safety-relevant criteria.
Insofar as the requirements of these Rules are concerned the approved modes of operation for a unit or
installation shall include the following:
C Certification
C.1 General
C.1.1 The main objective of GL’s Offshore Certification Services is the written confirmation and veri-
fication of compliance with the agreed codes, standards, rules and specifications. In order to perform
these services GL operates a world wide organisation employing qualified staff working according to GL’s
internal quality system which is kept updated and adequate to satisfy the client’s needs.
C.1.2 The Certification Service is understood as the control procedure and attestation by GL that the
design, and/or fabrication and/or installation, and/or testing of a mobile offshore unit or fixed offshore in-
stallation and/or components thereof, is in conformity with recognized codes, standards, rules and speci-
fications or an appropriate safety code agreed between the Operator/Owner and GL in the Certification
Service contract. The Certification procedure may be adjusted to the needs of an actual project. Extent
and format of the Certification may also depend on the request of an Administration.
Insofar as it is necessary to identify materials or components during the manufacturing process or possi-
bly also after commissioning, e.g. because of special properties of the material, a permanent mark is to
be made by means of a stamp.
The construction supervision, survey and/or final inspection of materials, parts supplied or installation
components, corresponding to the relevant specifications and GL Rules, shall be attested by the GL GL
Inspector concerned, either on special forms, or informally, as agreed in the individual case.
C.1.3 GL will not be able to successfully negotiate a contract for Certification Services, if the specifi-
cations or regulations or codes proposed to GL are in contradiction to GL’s professional understanding.
C.1.4 The Certification Services shall be confirmed in writing by issuing the different types of Certifi-
cates as it is defined in this Section.
––––––––––––––
1 "Sister Units or Installations” may have minor design alterations provided such alterations do not affect matters related to Certi-
fication.
C.2.2.1 The Rules, surveys performed, reports, Certificates and other documents issued by GL, are
not intended to replace or alleviate the duties and responsibilities of parties such as Administrations, de-
signers, building yards, manufacturers, repairers, suppliers, contractors or subcontractors, actual or pro-
spective owners or operators, charterers, brokers, cargo-owners and underwriters. GL cannot assume
therefore the obligations arising from these functions, even when GL is consulted to answer inquiries
concerning matters not covered by its Rules, or other documents.
C.2.2.2 The activities of such parties which fall outside the scope of the Certification as set out in the
Rules, such as design, engineering, manufacturing, and operation remain therefore the responsibility of
those parties, even if these matters may be given consideration for Certification according to the type of
unit or the installation.
C.2.2.3 The Certification-related services and documents performed and issued by GL do not relieve
the parties concerned of their responsibilities or other contractual obligations expressed or implied or of
any liability whatsoever, nor do they create any right or claim in relation to GL with regard to such respon-
sibilities, obligations and liabilities. In particular, GL does not declare the acceptance or completion of
commissioning of a unit or installation or any part of it, this being the exclusive responsibility of the owner
or other subcontractor.
C.2.2.4 During periods of construction, modification or repair, the unit or installation is solely under the
responsibility of the builder or the repair yard. As an example, the builder or repair yard is to ensure that
the construction, modification or repair activities are compatible with the design strength of the unit or
installation and that no permanent deformations are sustained.
C.2.2.5 Regarding the Owner’s responsibility for maintenance and operation of the unit or installation
in relation to the maintenance of the validity of the certificate see Section 4.
D Application
D.1 Scope
The Rules primarily apply to the Certification of the following fixed offshore installations:
• Transformer Stations
• Converter Stations
• Accommodation Platforms
D.3 Equivalence
GL reserves the right to consider designs for Certification which have similar configurations and modes of
operation to those described in these Rules, if they are deemed to be equivalent and/or suited for the
intended service, or alternatively, to impose more stringent requirements should these be deemed to be
justified.
In addition, evaluation must be made of possible loading conditions peculiar to the type of units or instal-
lations under consideration. Calculations sustaining the adequacy of the design are to be submitted to
GL.
D.4 Confidentiality
D.4.1 No information, whatsoever related to the Certification of the unit or the installation, will be
provided or confirmed to any third party, unless the appropriate request for information is duly completed
and signed by the party making the request and the authorisation of the current Owner is obtained.
D.4.2 GL maintains confidentiality with respect to all documents and other kinds of information re-
ceived in connection with the orders entrusted to GL. GL shall comply with the security procedures, if any,
agreed upon with the prospective Owner of the unit or the installation, and the building yard/manufacturer.
D.5 Interpretation
GL alone is qualified to decide upon the meaning, interpretation and application of the Rules and other
Certification-related documents. No reference to the Rules or other Certification-related documents has
any value unless it involves, accompanies or follows the intervention of GL.
D.6.1 Any technical disagreement with the GL Inspector in connection with the performance of his
duties should be raised by the Owner, building yard or other subcontractor as soon as possible.
D.6.2 The Owner, building yard /manufacturer or other subcontractor may appeal in writing to GL,
which will subsequently consider the matter and announce its decision according to its established proce-
dure.
scope of assignment or maintenance of GL certificates, or within the scope of interventions carried out on
behalf of Administrations, when so delegated.
Free access is also to be given to GL experts or/and auditors accompanying the GL Inspectors within the
scope of the audits as required in pursuance of GL’s internal Quality System or as required by external
organizations.
Owners, building yards or other subcontractors are to take the necessary measures for the GL Inspectors’
inspections and testing to be carried out safely. Owners, building yards or other subcontractor, irrespec-
tive of the nature of the service provided by the GL Inspectors or others acting on GL’s behalf, assume
with respect to such GL Inspectors all the responsibility of an employer for his workforce such as to meet
the provisions of applicable legislation. As a rule, the GL Inspector is to be constantly accompanied dur-
ing surveys by personnel of the Owner, building yard or other subcontractor.
The Certificate and/or other documents issued by GL remain the property of GL. All Certificates and
documents necessary to the GL Inspectors’ interventions are to be made available by the Owner, building
yard or other subcontractor, to the GL Inspector on request.
During the phases of design and construction of the unit or installation, due consideration should be given
to rule requirements in respect of all necessary arrangements for access to spaces and hull/structures
with a view to carrying out surveys. Arrangements of a special nature are to be brought to the attention of
GL well in advance.
E.3.1 The review and appraisal of design and construction particulars by GL will be exclusively
based on codes, standards, rules and specifications, agreed upon in the specification of the Certification
contract between the prospective Owner, the building yard/manufacturer or other subcontractors and GL.
E.3.2 In addition, statutory construction rules for units or installations as well as industry standards
such as API, NPD/NORSOK, ISO, etc., may be applied upon agreement with the relevant Authority and if
defined in the specification of the Certification contract between the prospective Owner, the building
yard/manufacturer or other subcontractor and GL.
E.3.3 The compliance of the units or installations with statutory regulations and legal requirements of
the respective Coastal or Shelf State is left to the responsibility of the prospective Owner, the building
yard or any subcontractor.
E.3.4 International Conventions, Resolutions, Codes, etc., such as IMO Codes and Resolutions,
may be applicable in certain cases and/or for certain aspects, e. g. pollution prevention, life saving appli-
ances, fire protection, etc. Details shall be clarified and laid down in the Certification specification in the
particular case.
A.1.2 Responsibility
The Certification Service shall be carried out by GL Head Office and/or GL Inspector, as it is described at
each type of Certificate. The GL Inspector may be delegated from the Head Office or from the local GL
representations.
EquipmentCertificate
CoE
Fabrication Certificate
CoFab
System Certificate
CoSys
Installation Certificate
CoI
Certificate of Fitness
CoF
The CoSt has a limited period of validity as defined by GL, typically 5 years. Maintenance of the certifi-
cate’s validity is subject to periodical inspections as defined in Section 4.
The CoF has a limited period of validity as defined by GL, and shall be aligned with the period of the un-
derlying Certificates (CoSt and CoTop).
A General
A.1.1 Scope
The design documentation shall be produced identifying design criteria and describing procedures to be
adopted in the structural design of the floating unit and/or fixed offshore installation.
Applicable codes, standards and regulations shall be identified at the commencement of the design.
Design documentation shall, as far as practicable, be concise, non-voluminous and should include all
relevant information for all relevant phases of the lifetime of the unit.
B Design Review
B.1 Extent of review
The design documentation shall include reports, calculations, plans, specifications, procedures and other
documentation, where applicable. The extensiveness of the submitted documentation is to reflect the
uniqueness of the structure or the lack of experience with conditions in the area, where the structure is to
be located.
B.2.1 Specifications
Following main specifications shall be prepared:
• design basis
• material specification
• cathodic protection/impressed current system specification
• coating specification, if applicable
• fabrication specification, if applicable
• specification for fire protection
• access and transfer concept
• operational concept
• evacuation concept
B.2.1.5 Fabrication
Details see GL Rules for Structural Design (IV-7-2)
B.2.2.6 Miscellaneous
A general description of other essential design information including:
• description of corrosion allowances
• in-service inspection criteria
• marine operations
B.2.5.2 The general scope of documents is defined in B.2.6 to B.2.10; the detailed scope will be de-
fined case by case. GL reserve the right to demand additional documentation, if that submitted is insuffi-
cient for an assessment of the unit or essential parts thereof. This may especially be the case for plants
and equipment related to new developments and/or which are not yet tested on board to a sufficient ex-
tent.
B.2.5.3 Once the documents submitted have been approved by GL they are binding on the execution
of the work. Subsequent modifications and extensions require the approval of GL before becoming effec-
tive.
B.2.6.1 General
Following drawings are required:
• general arrangements /layout/ plot plans
• plan indicating design loads for all decks
• equipment-layout in relation with the weight list/weight control report
B.2.7 Plans for machinery and electrical equipment and design data
B.2.7.1 General
Plans are to be submitted showing the arrangement and details of:
• general arrangement of machinery, installations and equipment
• general arrangement and particulars of the electrical installation
• High voltage installations
• Trial programs
B.2.7.4 Lighting
Following drawings/documents are required:
• Main lighting arrangement
• Emergency lighting
• Additional emergency lighting, if applicable
• Low-level escape direction system
• Marking of platform (IALA requirements)
• Marking helicopter deck/warning lights
B.2.10 Calculations
B.2.10.1 The calculations for the global design are typically to be documented in comprehensive design
reports, see B.2.4.
B.2.10.2 The calculations are to be submitted in conjunction with the scantling plans, as applicable.
B.2.10.3 Submitted calculations are to be suitably referenced. Results from relevant model tests or
dynamic response calculations may be submitted as alternatives or as substantiation for the required
calculations.
B.2.10.4 The choice of computer programs according to the “State of the Art” is free. It is recommended
to use computer programs which are approved by GL in advance as appropriate to solve the actual prob-
lems. If the computer programs to be used are not known to GL, it may be checked by GL through com-
parative calculations with predefined test examples. Reference applications, already achieved approvals
by other institutions and other relevant information shall be provided in advance. A generally valid ap-
proval for a computer program is, however, not given by GL.
The calculations have to be compiled in a way which allows identifying and checking all steps of the cal-
culations with regard to input and output in an easy way. Handwritten, easily readable documents are
acceptable.
Comprehensive quantities of output data shall be presented in graphic form. A written comment to the
main conclusions resulting from the calculations has to be provided.
B.3.2 The operating instructions will be subject to examination within the design review procedure
only insofar as they are related to the specified loads and load cases to be applied, and to other safety
matters covered by these Rules.
C Documentation
C.1 General
In the basic design phase all documents to be prepared with relevant details for final approval. These
documents are subject later on for fabrication, NDT requirements, additional required testing, inspection
and workshop drawings.
Entries/remarks from the Certifying Body are to be transferred into the revised documents.
C.2 Documentation
Documentation for following disciplines is required:
X Subsea
Y
Z Multidiscipline See Annex B
• material designation like type, thickness, size, diameter including the applicable standard or material
number
• welding details, type of weld e.g. for fillet welds leg length or a-measurement, etc.
• groove performance
• substructures with all relevant details for required foundations
• specific details required for cranes, life-saving appliances, winches, containers, pumps, transformers
or other heavy equipment
• basic calculations to be presented for the loads, i.e. environmental, static and dynamic loads, vibra-
tions and noise abatements
• details for lifting devices, e.g. padeyes and trunnions
A General
A.1 Supervision and testing during construction
During the design and construction phase of a fixed offshore installation the sequential steps of the ap-
proval procedure to obtain GL Certification shall be applied successively unless otherwise specified:
• design review/approval, see Section 3
• survey of materials and components, see B
• supervision of fabrication and installation on site, see C
• testing and commissioning, see D
A.2.1 In addition to the above periodical surveys, the installations are to be submitted to occasional
non-periodical surveys whenever the circumstances so require.
For example, occasional non-periodical surveys will be carried out at the time of:
• updating of Certification documents (e.g. change of the Owner, name of offshore installations per-
manently fixed to the seabed, etc.)
• damages or suspected damage
• repairs or maintenance work
• conversions
• extraordinary surveys as parts of GL's quality assurance system
• postponement of surveys or conditions of Certification
• non-periodical surveys for change of anniversary date, postponement or advance of surveys
GL reserve the right, after due consideration, to change the periodicity, postpone or advance surveys and
taking into account to particular circumstances.
A.2.2 The inspectors are to be given access at any time to the installation and/or to the workshops,
so that they may perform their duties.
The owner is to provide the necessary facilities for the safe execution of the surveys.
For their internal examination, including close-up surveys, tanks and spaces are to be safe for access.
For survey of the installations fixed to the seabed by internal structures, means are to be provided to en-
able the Inspector to examine the structure in a safe and practical way.
Tanks and spaces are to be sufficiently illuminated, clean and free from water, scale, dirt, oil residues,
etc. to reveal significant corrosion, deformation, fractures, damage or other structural deterioration.
Approved rescue and safety equipment is to be available.
In this connection all areas to be surveyed have to be cleared, cleaned and to be made free from gas, as
deemed necessary by the Inspector.
A.2.3 GL will inform the Owner or Operator about the status of Certification, indicating the last rec-
ognized surveys and the next due dates. However, even if not provided with such information, the Owner
or Operator is obliged to have the surveys stipulated by the present Rules performed.
A.2.4 GL may agree to testing and analysis procedures as a supplement to or equivalent substitute
for conventional survey and inspection such as by uncovering/opening up of components.
A.2.5 GL reserve the right to demand surveys to be held between the due dates of regular surveys,
if this is necessary, see E.7.
A.2.6 If an installation has to be surveyed in a location beyond the reach of a GL Inspector, also in
the events of force majeure or of armed conflicts, GL Head Office will have to be notified. Following a
review of the facts the process to be adapted will be decided by GL.
In extraordinary cases and with GL Head Office agreement, it is possible to call for an external expert,
whose report is subject to review by GL. GL will decide on whether or not the installation will have to be
re-surveyed.
A.2.7.1 The records of each survey, as well as any requirements upon which maintenance of the Cer-
tification has been made conditional, will be entered into the respective Survey Statement. The Inspec-
tor's signature on the Certificate and other documents only certifies what has been seen and checked
during the particular survey.
A.2.7.2 Where defects are repaired provisionally only, or where the Inspector does not consider im-
mediate repairs or replacements necessary, the Certification may be confirmed for a limited period by
making an entry in the Survey Statement to the Certificate of Certification. Cancellation of such limitations
will also have to be indicated in the Survey Statement.
A.2.8.1 Where surveys are required on account of international conventions and of corresponding
laws/official ordinances of a coastal state, GL will undertake them on application, or by official order, act-
ing on behalf of the Authorities concerned, based on the respective provisions; this includes surveys ac-
cording to:
• the related Conventions of the International Labour Organisation (ILO)
Where possible, such surveys will be carried out simultaneously with the Certification surveys.
A.2.8.2 GL will also undertake on request other surveys and checks stipulated by additional regula-
tions and requirements of the coastal state. Such surveys are subject to agreements made in each indi-
vidual case and/or to the regulations of the country concerned.
A.2.8.3 All activities as outlined in A.2.8.1 and A.2.8.2 and, where applicable, issuance of relevant
Certificates are likewise subject to the general conditions of Section 1.
A.2.8.4 If for some reason the Certification of an installation has expired or has been withdrawn by GL,
all statutory Certificates issued by GL, if any, will automatically become void. If subsequently the Certifica-
tion is renewed or re-assigned, the validity of these Certificates will be revived within the scope of their
original period of validity, provided that all surveys meanwhile having fallen due have been carried out.
B.3.1 General
Following Inspection items are generally required as applicable:
• visual inspection
• testing of mechanical and technological properties
• evaluation of non-destructive tests
• presentation of chemical composition
• additional test requirements extent according to specification
B.3.2 Identification
Every finished product shall be clearly marked by the manufacturer with following particulars:
• manufacturer's name or trade mark
• steel grade / material designation
• identification number, heat number or other marking which will enable the full history of the product
to be traced
• Purchaser's order number or other identification mark, if required
• identification particulars shall be encircled with paint or other wise marked to be easily recognizable
C.1.1 General
Supervision of the fabrication of individual components and of installation of the structure will generally
take the form of inspections by the authorized GL Inspector to the extent considered necessary by GL at
any given time.
Additionally all technical documents connected with the relevant construction project shall be made avail-
able to the Inspectors on request.
• test Certificates have been presented for components requiring approval (the fabricator will have to
ensure that any parts and materials requiring approval will only be delivered and installed, if the ap-
propriate test Certificates have been issued)
• where no individual Certificates are required, type- tested appliances and equipment are employed
in accordance with rule requirements
C.1.3.1 GL will assess the production facilities and procedures of the manufacturer/yard and other
fabricators as to whether they meet the requirements of GL Rules. In general, approvals based on such
assessment are conditional for acceptance of products subject to testing.
Materials, components, appliances and installations subject to inspection are to comply with the relevant
rule requirements and be presented for inspection and/or construction supervision by GL Inspectors,
unless otherwise provided as a result of special approvals granted by GL.
It shall be the duty of the fabricator to inform GL of the completion of important stages of the construction
or of trials and inspections due.
In order to enable the Inspector to fulfil his duties, he is to be given free access to both installation and
workshops, where parts requiring approval are fabricated, assembled or tested. For performance of the
required tests, the yard/fabricators are to give the Inspector every assistance by providing the staff and
equipment necessary for such tests.
C.1.3.2 The GL has to be familiarized with the production facilities of the manufacturer and/or of his
subcontractors. Following items shall be checked prior to starting of any fabrication or construction:
• management processes
• safety procedures
• comparison of performed constructions before to an actual project
In order to assess compliance with specified Rules, standards and regulations, the Society may require
additional documentation and carry out an assessment of manufacturer's processes, systems and per-
sonnel.
Therefore additional activities of builder's construction facilities and/or its subcontractors to be added and
evaluate the manufacturer's QA/QC-performance.
C.1.3.3 Prior to commencement of any newbuilding project, the fabricator and GL have to discuss at
the Kick-off meeting the survey activities, to fulfil the requirements.
All items are to be mentioned in a record including the areas of concern, which have to be closed as soon
as possible.
Following items to be checked:
• approval of workshop including range and workshop facilities
• subcontractors
• quality control system
• welding:
◦ supervision
◦ welders/operators
◦ welding procedures (WPS/WPQR)
◦ handling of welding consumables
◦ welding equipment
◦ welding environment
◦ non-destructive testing (NDT)
• steel preparation and fit-up:
◦ alignment, fit-ups, gaps
• steelwork progress:
C.1.3.4 Construction quality standards for the unit, piping, electrical, HVAC and other disciplines dur-
ing new building project to be properly listed, reviewed and agreed during the kick-off meeting.
C.1.3.5 Such a list or plan like a quality survey plan (QSP) covers survey activities and does not cover
the technical interpretation of the statutory requirements or approval of plans, designs and manuals re-
quired by the regulations.
C.1.4.1 Insofar as it is necessary to identify materials or components during the fabrication process or
possibly also after commissioning, e.g. because of special properties of the material, a permanent mark is
to be made by means of a stamp.
C.1.4.2 The construction supervision, survey and/or final inspection of materials, parts supplied or
installation components, corresponding to the relevant specifications and GL regulations, will be attested
by the Inspector concerned, either on special forms, or informally, as agreed in the individual case.
C.2.4 Installation
Installation procedures of foundations (e.g. drag embedded anchors, piles, suction anchor or dead
weights, etc.) shall consider relevant static and dynamic actions, including consideration of the maximum
environmental conditions expected for the operations.
The actions induced by the marine spread involved in the operations and the forces exerted on the struc-
tures utilised in positioning the unit, such as fairleads and pad-eyes, shall be considered for local strength
checks.
D.1.2 Pre-commissioning
Following items to be settled:
• punchlist of mechanical completion list to be cleared
• pre-commissioning procedures completed and signed
• verification of functional operability of equipment or system
• loop tests
• motor no load runs
• etc.
D.1.3 Commissioning
Following requirements shall be fulfilled:
• commissioning procedures completed
• functional testing of all systems by start-up priority
• testing of ESD/PSD and other alarms
• load tests
• equipment performance testing
• etc.
D.1.5 Trials
After installation at sea following items to be checked:
• major safety systems
• electrical performance for import and export
• equipment performance
• etc.
D.2 Program
An overall test or commissioning program including the complete, combined function of the installation as
well as partial tests of the different systems has to be established. The detailed requirements for the
overall function and the functioning of the different systems are defined in the following Chapters. The test
program has to be approved by GL.
D.4 Commissioning
Commissioning tests for verification of the proper function of all systems installed have to be performed at
the site location of fixed installations in presence of the GL Inspector.
Administration
Watertight integrity plan
Stability analysis
Damage stability analysis
Inclining test
Damage control plan
Freeboard plan
Freeboard calculation
Pollution plan
General items
General Arrangement Plan
Failure mode description
Installation manuals
Operational manual
Equipment list
Type approvals
Station operation manual
Test procedures: FAT/HAT/SAT
Inspection and test plans (ITP)
Inspection manual
Installation unit (Jacket/Topside)
Material
Welding
Instrumentation
Block diagram
Power supply
Cable routing
Instrumentation and equipment list
Control and monitoring system
Navigation
Equipment list (AIS, Radar, Sonar, etc.)
MED-List, if applicable
Communication
Block diagram
Power supply
VHF shipborne/airborne
Satellite radio
Fire protection
Sea water fire line
Fixed water spraying system for accommodation facilities
Local application water spray system for machinery spaces
CO2 detection systems, fixed
Helicopter deck foam system and fuel storage arrangement
Passive fire protection/structural fire protection(incl. draught stops)
Hazardous material
Safety matters
Fire detection and alarm system
Muster area and muster list
Risk analysis
Fire and control plan
Emergency analysis
Escape routing drawing
Escape and evacuation study
Hazardous areas
Personal safety equipment (PSE)
Mobile fire protection equipment
Life-saving appliances
Arrangement plan with life-boats, life rafts, fast rescue-boat and launching
appliances
Installation of HVAC/other vent systems
Accommodation facilities and galley
D & ID diagrams machinery spaces, hazardous stores, battery rooms, etc.
Penetration drawings
Duct routing
Ventilation control and monitoring system
Closing appliances
Helideck
Platform
Fuel system
Fire extinguishing system
Mobile equipment
Drainage
Emergency shut down system
Fuel system
Lubricating system
Geo-technology
Soil condition
Gravity foundation
Anchor foundation
Scour prediction/protection
Pile driveability
D.6 Report
A test or commissioning report has to be established by the fabricator or Owner and to be agreed with the
GL Inspector.
E.1.1 The periodical surveys listed in the following are to be conducted for the structure, machinery
including electrical installations as well as special equipment and installations included in the Certification
of the installation.
E.1.2 Where statutory regulations are applicable, which impose inspection intervals deviating from
the Certifier related intervals, where possible, the intervals will be harmonized in the individual case to
reduce the number of single surveys.
E.1.3 An inspection schedule agreed upon between Owner/Operator and GL will be set up for the
installation, in accordance with the indications described in this Section and adapted to the individual
service conditions.
E.1.4 For installations special diving devices, vehicles or diver assist systems have to be used,
which may be specially adapted to the configuration and conditions of the individual structure. The suit-
ability of such devices and systems and their deployment within the inspection scheme are subject to
approval and will be reviewed in the course of inspections carried out and experience gained.
E.1.6 When a survey results in the identification of significant corrosion, structural defects or dam-
age to structure, machinery and/or any piece of its equipment which, in the opinion of the Inspector affect
the Certification of the installation, remedial measures are to be implemented before the installation con-
tinues in service.
E.1.7 GL's survey requirements cannot be considered as a substitute for specification and accep-
tance of repairs and maintenance, which remain the responsibility of the Owner.
E.2.3.1 The annual survey will generally cover visual examination of all important structural elements
readily accessible, with regard to deformations, cracks, corrosion, etc. Where a special inspection plan
has been prepared, the corresponding indications have to be observed, e.g. for critical areas with stress
concentrations, locations with previous repairs, etc.
E.2.3.2 The type, location and extent of corrosion control, including coatings, cathodic protection sys-
tems, etc., as well its effectiveness and repairs or renewals, shall be reported at each survey, see also GL
Rules for Structural Design (IV-7-2), Section 5.
E.2.3.3 The structure within the splash zone shall be inspected visually with regard to corrosion, ma-
rine growth and damages, e.g. from collisions. Where damages are found which could extend further
downwards, diver inspections may be called for.
E.2.3.4 In areas where scour is supposed to occur, adequate control may be required on a yearly
basis or at closer intervals, especially for gravity type structures.
E.2.3.5 The exposed parts of the main structure, deck, deck house and structures attached to the
deck, crane substructure, accessible internal spaces and the applicable parts described in this Section
are to be generally examined and placed in satisfactory condition as found necessary.
E.2.3.6 Jackets, diagonal and horizontal braces together with any other parts of the upper supporting
structure as accessible above the waterline are to be checked.
Note
At the 1st annual survey after construction, the structures may be subject to examination of major struc-
tural components including non-destructive testing, as deemed necessary by GL. If GL deems such sur-
vey to be necessary, the extent should be agreed to by GL and the Owner or Operator prior to com-
mencement of the survey and incorporated in the survey schedule.
E.2.3.7 The GL Inspector is to be satisfied that no material alterations have been made to the installa-
tion, its structural arrangements, superstructure, fittings and closing appliances.
E.2.3.8 The scope for thickness measurements is to be defined in the survey schedule/special inspec-
tion plan, see E.6. For inadmissible corrosion, see E.1.6.
Note
See E.2.3.6
E.2.5.1 The machinery, including the electrical installations shall be subject to both the following sur-
veys and operating checks:
• general inspection of the machinery and boiler rooms, with special regard to fire and explosion
sources, and checking of emergency exits as to their free exits
• external inspection of boilers, pressure vessels with their appliances and safety devices
• inspection and checking of quick-closing/stopping devices of pumps, valves, ventilators, etc.
• checking of all communication systems
• inspection of bilge system
• checking of main and emergency power supply systems, including the switch-gear and other electri-
cal installations
• survey of explosion-proof installations
• checking of further permanently installed installations, e.g. cooling plant, air conditioning, incinerat-
ing plant, etc.
• fire-extinguishing and fir alarm system
• fixed fire-extinguishing systems, e.g. CO2 and foam system including pressure vessels, portable and
mobile fire-extinguishers and foam applicator units
E.2.5.2 Special equipment such as cranes, life-saving and other equipment are to surveyed according
to instructions issued in each individual case, if included in the Certification procedure.
In addition a general examination of hazardous areas, remote shut-down arrangements, piping systems,
etc. shall be made.
E.3.2 Scope
E.3.2.1 General
The Certification renewal surveys shall include, in addition to the annual surveys, the underwater inspec-
tion. The following examinations, tests and checks of sufficient extent to ensure that structure, equipment
and machinery are in satisfactory condition and that the installation is fit for its intended purpose for the
period of Certification to be assigned subject to proper maintenance and operation and the periodical
surveys carried out at the assigned due dates.
Special requirements for renewal of installations of unusual design, in out of operation status or in un-
usual circumstances will be determined on individual basis in the approved survey inspection programme.
E.3.3 Structure
One or more of the following crack detection test methods may be required if deemed necessary by the
Inspector:
• radiography test (X- or gamma ray)
• ultrasonic test
• magnetic particle test
• dye penetrant test
• eddy current test, etc.
If deemed necessary by the Inspector, defective grouting, asphalt covering or other coating is to be re-
moved. The steel works is to be examined before painting or before the grouting or other coverings are
renewed.
• internal examination and testing of void spaces, compartments filled with foam or corrosion inhibi-
tors, and tanks used only for lube oil, light fuel oil, diesel oil, or other non-corrosive products may be
waived provided that upon a general examination the Inspector considers their condition to be satis-
factory. External thickness measurements may be required to confirm corrosion control.
• structures such as crane substructure, jack-houses, deck houses, superstructures, helicopter land-
ing areas, raw water (sea water intake) towers and their respective attachments to the deck.
• structure/plate thickness measurements and non-destructive testing according to an approved in-
spection plan and/or on-the-spot decision where damages are suspected.
• effectiveness of the corrosion protection system (potential measurements, condition and anodes,
etc.)
• marine growth
• condition of foundations (changes in topography/scouring settlement)
• detailed measurements of scours as well as build-ups, if applicable
• debris in the area to be mentioned
Account may be taken of data recorded by instruments installed to monitor structural and foundation be-
haviour. Special attention shall be given to areas of stress concentration and of suspected or proven
damage, and to areas where repairs have been carried out previously.
Cleaning and/or uncovering of areas selected for close-up inspection and non-destructive testing may be
necessary.
• fittings and connections on main switchboards and distribution panels are to be examined, and care
is to be taken to see that no circuits are over-fused.
• cables are to be examined as far as practicable without undue disturbance of fixtures.
• all generators are to be run under load, either separately or in parallel; switches and circuit breakers
are to be tested.
• all equipment and circuits are to be inspected for possible development of physical changes or dete-
rioration. The insulation resistance of the circuits is to be measured between conductors and be-
tween conductors and ground, and these values compared with those previously measured.
• electrical auxiliaries installed for vital purposes, generators and motors are to be examined and their
prime movers opened for inspection. The insulation resistance of each generator and motor is to be
measured.
• the emergency remote switch-off devices of ventilators, fuel pumps, oil fired equipment and similar
equipment are to be tested.
E.3.8 Trials
Upon completion of the surveys for Certification Renewal, the Inspector must be satisfied that the entire
machinery installation, including the electrical machinery and equipment, is operable without any restric-
tions. In case of doubt, this may have to be proved by trials and/or operational test.
E.4.3.1 General
The procedures and conditions under which a properly conducted underwater inspection is to be exe-
cuted are defined in the following.
The diving firm assisting in underwater surveys must be approved by GL for this purpose. Validity of an
approval granted shall depend on the continued qualification for satisfactorily carrying out the work re-
quired. The approval shall be renewed after a period not exceeding 5 years.
E.4.5 Procedures
monitor screen must offer reliable technical information such as to enable the Inspector to judge the parts
and/or the areas surveyed. If applicable, the effectiveness of the corrosion protection system (potential
measurements, conditions of anodes, etc.), the marine growth and the conditions of foundations (changes
in topography/scouring settlement) are to be inspected.
E.5.1 Scope
The periodical surveys of individual machinery items or installations listed in the following are to be car-
ried out in addition to those prescribed for the Certification renewal surveys for maintenance of Certifica-
tion.
The following machinery items are to be surveyed:
• pressure vessels
E.6.1 General
E.6.1.1 The thickness of structural elements is checked by measurements, in order to assess whether
or not the values stipulated in GL Rules are observed, taking into account the admissible tolerances.
Unless severe corrosion has occurred owing to particular service conditions, thickness measurements will
not be required until Certification Renewal II.
E.6.1.2 Thickness measurements shall be carried out in accordance with recognized methods, by
authorized personnel or companies see E.6.2. Rust and contamination are to be removed from the com-
ponents to be examined. The Inspector is entitled to require check measurements or more detailed
measurements to be performed in his presence. The thickness measurements on board shall be wit-
nessed by the Inspector. This requires the Inspector to be on board while measurements are taken, to the
extent necessary to control the process.
The scope of thickness measurement as well as the reporting shall be fixed in a survey planning meeting
between the Inspector(s), representatives of the Owner and the approved thickness measurement opera-
tor/firm well in advance of measurements and prior to commencing the survey.
Thickness measurements of structures in areas where close-up surveys are required shall be carried out
simultaneously with the close-up surveys.
E.6.2 Authorization
E.6.2.1 The personnel or the company entrusted with thickness measurements, as well as the proce-
dure for documentation must be approved by GL for this purpose.
E.6.2.2 Validity of an approval granted will depend on the continued qualification. The approval will
have to be renewed after a period not exceeding 3 years.
E.7.2 Repairs
E.7.2.1 Where repairs to main structure, legs, columns or other structures, machinery or equipment,
which affect or may affect Certification, are planned in advance, a complete repair procedure including
the extent of the proposed repair and the need of the Inspector's attendance shall be submitted to and
agreed upon by GL reasonably in advance. Failure to notify to GL, in advance of the repairs, may result in
suspension of the Certification until such time as the repair is redone or evidence submitted to satisfy the
Inspector that the repair was properly carried out. This applies also to repairs on site.
E.7.2.2 The requirements of E.7.2.1 are not intended to include maintenance and overhaul to struc-
tures, machinery and equipment in accordance with recommended manufacturers' procedures and estab-
lished marine practice and which do not require GL approval. However, any repair as a result of such
maintenance and overhauls which affects or may affect Certification is to be noted in the log of the instal-
lation and submitted to the Inspector.
E.7.2.3 Surveys conducted in the course of repairs are to be based on the latest experience and in-
structions by GL. In exceptional cases advice is to be obtained from the concerned GL Head Office de-
partment, in particular where doubts exist as to the cause of damage.
E.7.2.4 For older installations, in the case of repairs and/or replacement of parts subject to Certifica-
tion, as a matter of principle, the Construction Rules in force during their period of construction continue
to be applicable.
This does not apply in the case of modifications required to the structure in the light of new knowledge
gained from damage analyses, with a view to avoiding recurrence of similar damages.
E.7.2.5 Regarding the materials employed and Certificates required, the requirements for new con-
structions are applicable, see E.6.2. and E.10.
E.7.2.6 Regarding damages or excessive wastage beyond allowable limits that affect the Certification
of the installation, see E.3.3.
E.11.1 Welding of steels, including higher strength hull structural steel, shall be to the satisfaction of
GL.
E.11.2 Welding or other fabrication performed on steels for special characteristics or repairs or re-
newals of such steel or in areas adjacent to such steel shall be accomplished with procedures approved
by GL considering the special materials involved. Substitution of steels differing from those originally in-
stalled shall not be made without approval by GL.
F Inspection Planning
F.1 General
Inspection is one of the dedicated activities within the offshore management that contribute to controlling
and minimizing of offshore risks. The role of inspection is to check/confirm whether degradation is occur-
ring, to measure the progress of that degradation, and to help ensure that integrity is maintained in accor-
dance with the design intent.
All inspection activities are subject to appropriate verification of its performance.
◦ visual technique
◦ ultrasonic technique
• flaw detection
◦ ultrasonic technique
◦ radiographic
◦ surface flaw detection
◦ liquid penetrant
◦ magnetic particle
◦ eddy current
• material characterization
◦ positive material identification (PMI)
◦ in-place metallography
G.1.1 The survey and inspection plan has the task to all areas of concern:
• granting of human live and avoiding of death
• protection of the environment
• saving of properties, operating interests and other economic aspects
G.1.2 This survey and inspection scheme gives an overview of periodical and non-periodical surveys
and inspections. The periodical surveys have to be performed on an annual basis, except the underwater
survey to be carried out 3 months later after installation of the jacket. The next underwater survey to be
performed after 9 months and is subject to the regular annual survey.
• marine growth
G.2.7.1 Crack detection of a surface breaking defect due to fatigue may be detected by the following
processes:
• magnetic particle inspection (MT)
For getting satisfactory results it is necessary to remove the painting before testing. After testing re-
installation of a proper painting is to be performed.
• Alternating Current Field Measurement (ACFM).
This is a non-conducting electromagnetic technique, which is used as a surface defect detection
alternative to magnetic particle in conducting material without removing the painting.
G.3 Documentation
G.3.1 General
For each survey and/or inspection a report to be prepared and one copy filed in the platform folder. The
Owner/Purchaser has to install a reporting system which is to handle practically and easily and in compli-
ance with the Classification and/or Certification.
H Risk-Based Inspections
H.1 Scope
Risk based inspection involves the planning of an inspection on the basis of the information obtained from
a risk analysis of equipment, system and/or structural item. The purpose of the risk analysis is to identify
the potential degradation mechanisms and threats to the integrity of the equipment and to assess the
consequences and risks of failure. The inspection plan can then target the high risk equipment and be
designed to detect potential degradation before fitness-for-service could be threatened.
H.2 General
The principles and practice of risk-based inspection shall apply for equipment and systems as well as for
structural components depending on Owner's/Operator's advice.
Risk-based inspection shall be understood to be inspection planned on a basis of information obtained on
the risk.
H.3 Application
I Condition Monitoring
I.1 Scope
The Condition Monitoring (CM) shall describe the principles, the functional requirements and guideline of
Condition Monitoring throughout their operative lifetime until the decommissioning for the complete struc-
ture including substructures and topside structures as well as machinery components.
Additionally a Survey Arrangement CM has to be concluded between Owner/Operator of the installation
and GL.
Following parts shall be covered in the Condition Monitoring system:
• in-service inspection
• maintenance planning
• implementation
• structural integrity evaluation
• documentation
I.3 General
A Condition Monitoring System is used in a frame of a monitoring and control system and/or safety sys-
tem, and apply to certified installation/units by Germanischer Lloyd, i.e. new or existing platforms. Rele-
vant international and national regulations shall comply with. Structures and other items, which are part of
this monitoring system, shall meet the codes and standards to which they were originally designed.
The objectives of Condition Monitoring for load-bearing structures and/or other systems, e.g. machinery
and associated systems, are to ensure, that an adequate level of structural integrity and/or mechanical
systems is maintained at all times.
I.7.1 Regarding deviations, distinction should be made between deviations from the regulations,
Company's project specific requirements, relevant codes and standards, professional publications, con-
struction non-conformance, and other deviations from the conditions reported in the design reports.
Particular attention should be given to any parts of installation's load-bearing structures that have been
damaged or repaired during construction phases and which may be significant to the structural integrity
and installation's functional performance.
I.7.2 A programme for condition monitoring shall comply with the regulation requirements relating to
planning of this type of activity. Structural design, technical solutions and areas requiring particular atten-
tion, for example accepted deviations from the presumptions described in and dealt with in I.4 mentioned
items, and the condition summary or the structural components significant to structural integrity and func-
tional performance, should be focused when requirements specifications for condition monitoring are
prepared.
I.7.3 Therefore a detailed description of structural matters for following items to be available:
• highly utilized areas, statically and in fatigue
• structures for which structural integrity, functional integrity of fatigue life is sensitive to design as-
sumption on exact functioning of specific elements
• prototype structures
• structural elements subject to progressive collapse/ non-redundancy
• materials selection
• corrosion protection
• recommendation for what should be inspected and which methods shall apply
• procedures for planned replacement and repair shall be contained in separate Operation Manuals
I.7.4 When operational limitations are introduced as a part of the mitigation measures resulting from
fitness for purpose assessment, the limitations may be included considering and overall safety level of the
installation in question.
further actions to maintain an adequate level of structural integrity should then be based on results of the
inspection and the other information available.
I.8.7 Accessibility
All parts/areas mentioned for both close-up inspection and non-destructive testing shall be prepared for a
safe access. For tanks, confined spaces and underwater inspections additional safety standards shall
apply and written procedures are available.
I.9.1 General
The Condition Monitoring should primarily be concentrated on discovering serious damage or defects on
the load-bearing structures. Also the potential defects and deterioration which may escalate into damage
significant to structural integrity and functional performance shall be inspected.
I.9.4 With regard to submerged load-bearing structures the Condition Monitoring should, in addition
to the parameters mentioned in I.9.2 consisting of a visual survey to detect, particularly, possible dam-
age/defects or conditions that may cause an obstacle to effective Condition Monitoring, including:
• marine growth
• damage to the structure
• scouring of the sea bed under or in the immediate vicinity of the installation or build-up of sea-floor
substance/sediments
• build up of cuttings or sediments if such build-up covers a significant part of the structure
• composition of the sea water and pH values
• temperature variations
• specific conductivity of sea water and bottom sediments
• biological activity
• movement in bottom sediment
• mechanical loads including anchoring
• cathodic protection conditions
I.9.8.1 It is of importance that the overall risks of the installation are focused during the assessment
process.
When inspection data becomes available or when an inspection work package needs to be revised, a
routine evaluation shall be conducted to:
• confirm that the acceptance criteria are met or that the ongoing inspection is suitable to the use
• recommend any remedial measures or a revision of the inspection plan
• initiate fitness for purpose assessment.
I.9.8.3 If the Condition Monitoring reveals an extent of damage of such serious nature that the safety
level may not be maintained, the consequences for the structural integrity of the installation shall be as-
sessed. Upon results of the assessment any remedial measures including operational limitations of the
installation shall be considered and initiated according to the regulations.
The fitness for purpose shall also be initiated, when significant deviations from the design, for example
significantly increased loading due to addition of facilities, are present.
The remedial measures to be initiated should then be considered relative to the risk so, that an adequate
safety level is maintained as is reasonably practicable. The remedial measures may be prevention meas-
ures such as structural strengthening, load reductions, change of Condition Monitoring Procedures, etc.
or mitigation measures such as disembarkation, evacuation procedures, etc.
I.10.3 In-service inspection plan shall, as a part of Condition Monitoring Process, be developed and
revised for each installation soon after receiving all relevant documentation relating design, fabrication
and installation and be periodically updated throughout its service life. The inspection planning shall focus
on condition verification of the structural components so that the structural integrity at any time will effec-
tively be secured.
In general, a jacket structure may, during its in-service life, have the following defects, damage or deterio-
ration:
• joint degradation due to repeated actions
• corrosion damages
• component failure due to overloading
• component damages due to accidental events
• other irregularities, such as marine fouling, scouring
• etc.
The damages/failures due to overloading or accidental actions will usually be taken care of by inspections
on special occasions, whilst existence and extent of the other damages/defects should be determined
during regular offshore inspections.
Special attention should be given to the joints of major importance to the structural integrity of the jacket
in and just below the splash zone.
No. Item
1 Arrangement drawing of the protected space with locations of nozzles and
release lines
2 List of volumes deducted from the gross volume
3 Calculation of the net volume of the space and required supply of
extinguishing gas
4 Isometrics and discharge calculations
5 Release schematic
6 Drawing of the release station and of the arrangement on the
installation/unit
7 Release instructions for display at the release station
8 Drawing of storage space (centralised systems only)
9 Alarm system schematic
10 Parts list
11 Installation/unit manual
Reuired
Remark
No. Item
1 Arrangement plans
1.1 General (GAP)
1.2 Engine room(s)
1.3 Tank plan
2 Equipment list
Maintenance manual
Operating manual
Certification
2.1 Winches
2.2 Hatch covers
2.3 Doors
2.4 Windows
2.5 Life-saving appliances
2.5.1 Free-fall boat
2.5.2 Lifeboat
2.5.3 Fast-rescue boat
2.5.4 Life rafts
2.5.6 Others
3 Fire-extinguishing components
3.1 Water fire-extinguishing
3.1.1 Fire pumps
3.2 CO2 or gas fire-extinguishing system