Samsung C&T India Pvt. Ltd. ie isin Tone Tor Bh ig No DLL Cyber ip: Phase i100 won Ref, RVIPL/CE-1081 /QAQC/161 1/002 Dated: 19.11.2016 To Ruskin Titus India Pvt.Ltd. Plot No.25 & 26 Sector 2A HSIIDC IMT Manesar Gurugeam, Haryana-122050, Kind Attn Mr. Vineet Gupta, M.D, Subject Contract CE-10&CE-11 Lot, DMRC Phase IL Bulging in Attenuators. Ref + Whatsapp dated 31.10.2015 mail dated 15.10.2016, Dear Sir, Please refer to pies sent to Mr.Pankaj Saxena thru whatsapp on 31.10.15 and our recent mail dated 15.10.16 regarding bulging of attenuators modules. Pics are re-attached, It is almost a year now for complaining about bulging modules but no action is taken so far by Ruskin, You are once again requested to look into this matter and resolve the issue within 15 days. Please note at few locations DMRC has denied measurements on account of this flow. Thanking You, Yours faithfully, For and on behalf of Samsung C&T India Pvt. Ltd. Hark Project Leader Enel: As stated above