PROGRESS REPORT KHURAIS CAMP CONSTRUCTION

Date: 01-11-016
S,NO

Activity

1.0

Survey Work

Scope

Completed

Remaining

100%

__

UOM

Scope

Previous

Today

Cumulative

Percent Comlete

Civil Work
2

Ground Preparation

2.1

Backfilling mixed meterial with sand & rocks

m3

23500

23500

23500

100.00%

2.2

Rock Breaking

m3

3937

3937

3937

100.00%

2.3

Marl Caping for Camp Ploat 20cm

m3

6480

6480

6480

100.00%

2.4

Acces Roads outside camp fence Backfilling with sand

m3

2256

2256

2256

100.00%

2.5

Acces Roads outside camp fence Backfilling with Marl

m3

678

678

678

100.00%

2.6

Patrol Roads Backfilling with Sand

m3

710

710

710

100.00%

2.7

142

142

100.00%

Patrol Roads Backfilling with Marl

m3

142

2.8

Construction of Asphalt Roads inside camp fence

m2

5600

2.9

Construction of Walk Ways

m3

63

m2

2000

2.10
3

Construction of Acces Asphalt Roads


Backfilling of Trenching

1849

1849

1849

100.00%

Backfilling of Drainage trenching with Marl

m3

288.9

288.9

100.00%

Backfilling of Raw water trenching with sand

m3

1302

1302

0
0

288.9

3.3

1302

100.00%

3.4

Backfilling of Raw water trenching with Marl

m3

232.05

232.05

232.05

100.00%

100.00%

3.1

Backfilling of Drainage trenching with sand

m3

3.2

3.3.1
3.5
3.5.1

Installation of Valve Box

No

Backfilling of Fire Water Line with sand

m3

1019

750

Backfilling of Fire Water Line with Sand Behind A.hak Office up to Fen Staff Accommodation

m3
181.5

130

Backfilling of Fire Water Line with Marl

m3

3.6.1

Backfilling of Fire Water Line with Marl Labor Dinning Hall to Labor Accommodation

m3

3.6.2

Backfillng of Fire Water Line with Marl Labor Accommodation to Septic Tank

m3

3.6.3

Backfilling Of Fire Water Line with Marl Behind camp Office & Guard House

m3

3.6

4
4.1
4.2

100.00%

160

88.00%

Fence Installation
m3

Excavation & Rock Breaking for Fence Foundation


Concrete Post Foundation Installation

4.3

Line Post Installation

4.4

Fence Gates

269

Errection of Portacabins

5.1

A.hak office

5.2

Labour Accomodation

254

100.00%

19

100.00%

230

197

86.00%

QT

0.00%

Building

10

10

__

__

100%

12

40

12

40

__

__

100%

__

__

100%

Pieces

Pieces

19

QT

Pieces

Building

Building

254

m3

5.3

labour Dinning area

5.4

Guard house

__

__

100%

5.5

Laundry unit

__

__

100%

__

__

100%

5.6

Camp office

5.7

Clinic

__

__

100%

5.8

Mosque

__

__

100%

5.9

Recreational Building

__

__

100%

Junior staff dinning Area

__

__

100%

__

5.10
5.11

Fen staff accomodation

14

28

14

28

__

100%

5.12

Senior staff accomodation

22

22

22

22

__

__

100%

5.13

Senior staff dinning area

__

__

100%

__

__

100%
100%

5.14

Kitchen & Store

5.15

Toilets for Labour

__

__

5.16

Total Portacabins

64

132

64

132

__

__

100%

MEP Work

6.1

Trenching for Raw Water Line

m3

1547

1547

1547

100.00%

6.2

Trenching for Drainage Pipe Line

m3

1926

1926

1926

100.00%

m3

1210

1210

1210

100.00%

6.4

Installation of Drainage Pipe Line

LM

1303

1330

1330

100.00%

6.5

6.3

Trenching for Fire water Line

Installation of Raw water Pipe Line

LM

1247

1247

1247

100.00%

6.6

Installation of Fire water Pipe Line

LM

835

650

835

100.00%

6.7

Conections With Portacabins

6.8

Drainage Line Connections with portacabins

Con

52

45

96.00%

Con

52

39

88.00%

Con

29

29
12

13

100.00%

26

100.00%

6.8.1
6.9

Connecctions of FEN Staff Accommodation


Raw Water Line Connections with Portacabins

6.9.1

Connecctions of FEN Staff Accommodation

6.10

Fire Water Line Connections with Portacabins

6.11

Main Holes

6.11.1

Plastring of Main Holes

6.11.2

Backfilling of Main Holes with Marl

13

12

QT

13

m3

26

6.12

Communication System

6.13

Gen Set Installation

6.14

Electrical Trenches

600 LM

__

LM

600 Appx

530

40

30

95.00%

6.15

Grounding Work Trenches

900LM

__

__

LM

900

280

220

400

55.00%

6.16

MPD and DP installation

NYS

__

__

NYS

6.17

Installation of Electrical Cable

NYS

__

__

NYS

6.18

Electrical Connections

6.19

Solar Lighting System (street, bb court & fence)

6.20

Installation of Raw Water Tanks

67.00%

6.20.1
6.21
6.21.1

__

20%

80%

__

20%

80%

NYS

__

__

procured & delivered 100%

__

__

3 ea

Procured & 1 unit Delivered

2 units TBD

NYS

QT

3ea

Installation of Raw Water Tank on concerete pad


Installation of Septic Tank

1
3 ea

2 units installed

1 unit RTI

1 ea

20%

80%

Backfilling of Septic Tank With sand

6.22

Installation of Fire Water Tanks

6.23

Installation of Utility Area Pumps and Controls

6.24

Installation of Diesel Tanks

1 ea

6.25

Installation of HVAC system

185

__

QT

3ea

100.00%

m3

2143

1650

393

81.00%

QT

__
TBD
NO'S

6.25.1

Installation of Window AC Units

NO'S

80

50

20

10

6.25.2

Installation of Siplit Units AC

NO'S

185

84

16 INDOOR

85

6.25.3

Installation / Fabrication of External Concrete Pad for HVAC

NO'S

6.26

Installation of Kitchen Equipment

6.27

Installation of Office Furniture

6.28

Installation of Accomodation Furniture

6.28.1

Installation Beds For Labor Accommodation

6.28.2

Delivery Beds For Senior Staff Accommodation

6.28.3

Dilvery of Bed Matress For Fen & Labor Accommodation

70.00%

185
Appx

Ongoing

Appx

80.00%

Appx

ongoing

240 (160 Double,80 single)

NO'S

240 Pieces

240

22 Pieces

NO'S

22 Pieces

22

NO'S

90.00%

450

240

100.00%

22

100.00%

22

90%

LOOK AHEAD FOR WEDNESDAY 02 NOV


Activty Name
1

MEP connenction to Delivered Fen Staff Accommodation (Raw+Drain)

Installation of Furniture for A.HAK Office

Trenching For Electrical cables

Installation ofOut Door Siplit Units in (A.hak Office)

Dilvery Of Electrical Cables

Trenching For Grounding

Dilever of Furniture For Accommodations

10

Dilvery of Elecric Gyeser & Installation

2/11/2016

EXPECTATION Crew Actual % Complete


10 Buildings

15

Ongoing

600 metrs appx

20

Drainage line connection of FEN Staff Buildings complete

570 metrs complete


100 Indoor Units Install

AS Per Schedule
180 LM

500Lm Also Completed

AS Per Schedule
66 Units

(Central 8 pcs ,50ltr 30 pcs ,80 ltr 28 pcs)

ACTIVITIES FOR TUESDAY 1-Nov


Acivity Name
1
2
3
4
5
6
7
8
9
10
11

Start MEP connenction to Fen Staff . (Raw+Drain)


Installation Of A.HAK Temporary office
Trenching For Electrical cables
Installation of Siplit Units in (Fen Staff Accommodation)
Furniture Installation in A.HAK office
Dilevery of Kitchen Equipments

Date:01-11-016

Actual Complete

Crew

28 Units

15

600 metrs appx

16Units

Ongoing

Remarks
28 Buildings Connection Complete of Fen Staff Accommodation(Drainage complete , Raw 10 Remaining)

570 metrs complete


100 indoor units install ( 30 A.hak Office, 44 Senior Staff Accommodation, 26 Fen Staff Acco.)

Ongoing

900 metrs appx

Installation of kitchen Equipments,Material

Ongoing

(Freezer & Chiller Installation)

Dilevery of Staircase for Remaing Buildings

100%

(Install after Electrical Trenching)

Ongoing

Trenching/ Rock breaking For Grounding

Concrete Pad Installation for Outdoor AC units


Dilevery & Erection of RAW Water Tank

500 metrs complete(Trenching speed down due to rock area)

Name

S/N

KPE#

Designation

Syed Adeel

2408409387

MaSroor Husian
Muhmmad Bilal

Abdul Rehman

Muhammad Yaseen

2327571549

Safety Supervisor

M.Kaleem Mossa
M.Yousaf

2405397197

SR.Surveyor

Ashfaq Ahmed

2409572787

Sagir
Mazhar mehmood

Remarks

Project Manager

PAKISTAN

Chief Accountant

PAKISTAN

2397526126

Project Coordinator

PAKISTAN

P
P

2410451625

Planning Engineer

PAKISTAN

2412668689

Office Boy

PAKISTAN

INDIA
PAKISTAN

P
P

MEP Foreman

PAKISTAN

2378947978

Civli Labor

PAKISTAN

2412296390

Plumber

PAKISTAN

P
P

Qadeer
Godar khan
Jalauddin Kismat Ali

2398025859

Plumber

PAKISTAN

2367124134

Loader Operator

PAKISTAN

2414841755

JCB Operator

2276195548

Cat Excavator

17

M.Rustam
Iftkhar Ahmad

18

Yasir

2306561016

19

Rukhsar Ahmed
Azad

2384197675

Sadam Zameer
Arjun Singh
Sher Bahadur B.K
Nisar Ali
Ahmad Saleh

2360709816

BUS Driver

INDIA

2343503419

Low Bed Driver

INDIA

2398158671

Crane operator

PHILPNE

2238061978

Pre Feb Instalation Crew

YAMEN

Nsir Abbas
M.Anwar
M.Akram
Jamil Ahmad
Naveed Ahmed

SAQ-KPE-035

Pre Feb Instalation Crew

PAKISTAN

SAQ-KPE-036

Pre Feb Instalation Crew

PAKISTAN

SAQ-KPE-037

Pre Feb Instalation Crew

PAKISTAN

SAQ-KPE-038

Pre Feb Instalation Crew

PAKISTAN

SAQ-KPE-039

Pre Feb Instalation Crew

PAKISTAN

M.Mateen
Shaizad Mohammed
Muhammed Riyaz
M.Toseef
Usman Riaz
M.ASIM
M.Rizwan
Mubashir ALI
Naveed Ahmed
Viju Baby
Manjur
Syed Hassan Ahmad
Mohsin Shehzad
Abdul Malik
Sohail Anwar
Farhat Mehmood
Mohammad Ajmal
Muhammad Zahid
Usman Gul
Muhammad Ubaid

2333797617

MEP Installation Crew

PAKISTAN

2263003127

MEP Installation Crew

PAKISTAN

2411874312

MEP Installation Crew

PAKISTAN

220613098

MEP Installation Crew

PAKISTAN

2409660020

MEP Installation Crew

PAKISTAN

2398658241

MEP Installation Crew

PAKISTAN

2334571193

MEP Installation Crew

PAKISTAN

2307712568

MEP Installation Crew

PAKISTAN

2386098541

Kitchen Installation Crew

PAKISTAN

2404271179

Kitchen Installation Crew

INDIAN

2411017953

Kitchen Installation Crew

2312890086

Furniture Installation Crew

PAKISTAN

2334815145

Furniture Installation Crew

PAKISTAN

2247585272

Furniture Installation Crew

Bangali

2298240579

Furniture Installation Crew

PAKISTAN

HVAC Installation Crew

PAKISTAN

HVAC Installation Crew

INDIAN

HVAC Installation Crew

PAKISTAN

HVAC Installation Crew

PAKISTAN

HVAC Installation Crew

PAKISTAN

SAAQ SITE MANPOWER

10
11
12
13
14
15

20
21
22
23
24
25
26
27
28
29
30
31
33
34
35
36
37
38
39
45
46
49
51
52
53
54
55
56
57
58
59

24054404043

Indian

P
P
P

PAKISTAN

P
P

Boom Truck Driver

YAMEN

Dump Truck Driver

PAKISTAN

Diesel Tank Driver

PAKISTAN

P
P

Bopcat Operator

Water tank 4436

Indian

INDIA

NIPAL

P
P
A
P
P
P
A
A
A
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P
P`
P