Professional Documents
Culture Documents
8003 e PDF
8003 e PDF
ple, the foreshortening of jobsite precast concrete beams during prestressing may not conform to the designers
predictions. Also, the amount of
camber in prestressed concrete beams
is difficult to predict. In some cases it
might be possible to design a prestressed concrete structure to accommodate relatively large tolerances in
foreshortening or camber. A more
usual way of handling the problem is
to make a minor adjustment in the
form after job experience with
casting of beams has begun to show
what dimensions are actually being
achieved.
Realistic, practical tolerances
Phillip Birkeland, a consulting engineer, and Leonard Westhoff, a
28
It appears that no matter what sys3/16 inch per foot(4). ACI 301 allowtem
is used for specifying tolerances
ed a floor surface curvature of
(5)
there
will always be some parts of a
1/8-inch offset from a 10-foot
structure
that are unacceptable. The
straightedge. The investigators connumber
of
these instances can be decluded that curvatures up to -inch
(6)
creased
but
frequently at consideroffset from a 10-foot straightedge
able
cost.
It
is
simpler to plan to acmight be acceptable. Other measurecommodate
these
by repair.
ments on the building indicated that
the ACI 347 tolerance on intended
Guidance for those who
floor slab elevation was about the
specify tolerances
same as they were measuring in the
It should be possible for those
building. Tolerances on distances
directly concerned with construction
between columns required by ACI
to clearly interpret the tolerance re301 and 347 agreed fairly well with
quirements in the construction speciwhat they measured.
fications. Tolerances should be suffiAlthough designers often specify
ciently clear and specific not to give
unrealistic tolerances without questrouble to:
tioning the lack of realism in the data
the contractor who prepares the
they have access to, they also often
bid
accept the finished structure with all
the job superintendent who
its deviations from the specified toldetermines materials requirements
erances. It is likely that neither
and types of craftsmen needed
designers nor constructors know
the shift foreman who is responwhat tolerances are realistically obsible for setting lines and grades for
tainable; both think that the public is
formwork and embedments
getting structures that are more ac the inspector who checks formcurately built than they really are.
work for accuracy and strength
In Europe, realistic tolerances before concrete is placed
have been established by statistical
Several general guidelines can be
analysis of deviations. But in Europe stated for specifying tolerances.
considerable precasting is done,
Be certain that the design does
which makes it relatively easy to not demand tolerances that are
make dimensional measurements of unrealistic or unattainable.
elements and study them statistically.
Provide places where the inAnother important factor is the in- evitable variations can be absorbed.
volvement of the design engineer in
Choose construction concepts
the selection of construction meth- that will ensure that critical dimenods, a practice associated with in- sions are controlled directly and
dustrialization of the European check these out with builders to be
building industry.
sure they are free of bugs.
In the normal course of construc Dimension the drawing in such a
tion the deviations of any set of mea- way that the inspector can measure
surements from the intended value critical dimensions directly.
will fit the statistical normal distribu Emphasize or highlight critical
tion curve. By calculating the stan- dimensions in drawing so that they
dard deviation from a large body of are forcefully called to the attention
measurements it can be determined of the constructor.
how many measurements are statistiThe use of double dimensioning
cally expected to fall within given
on drawings inevitably leads to troulimits. If tolerances were established
ble and should be avoided. This is the
in statistical terms, thus acknowledgpractice of showing both the individing that a small number of measureual dimensions and the total dimenments will fall outside an acceptable
sion. It leads to uncertainty about
range, our tolerances might be more
which
dimension can best be allowed
realistic.
to float to meet all of the tolerance
requirements. This subject is well ex* Numbers in parentheses refer to metric
plained
in Reference 1.
equivalents listed with this article.
PROPOSED TOLERANCES
FOR PLANENESS OF FLOORS
AND OTHER FLATWORK
ACI Committee 302 is preparing a
new Guide for Concrete Floor and
Slab Construction. This has not yet
been either published or adopted, SO the
proposed tolerances given here have no
current authority and are still subject to
change. The new tolerances being suggested by the committee are for the
maximum depressions between high
spots in a floor or slab for four classes
of finish:
Class A finish
1/8 inch below a 10-foot(23)
straightedge*
Class A-2 finish
3/16 inch below a 10-foot(24)
straightedge
Class B finish
1/4 inch below a 10-foot(25)
straightedge
Class C finish
1/4 inch below a 2-foot(26)
straightedge
* The Committee states that the tolerance
for a Class A finish is extremely difficult
and expensive to achieve on large areas. [It]
should be specified only for critical areas
where such [a tolerance is] vital for the
operations that will take place in the area.
30
References
This article is based almost entirely on information from the following sources:
(1) Birkeland, Philip W., and Westhoff, Leonard J., Dimensional
Tolerances in a Tall Concrete Building, Journal of the American
Concrete Institute, August 1971, pages 600-607.
(2) Stevens, Alan, How Accurate is Building? BRE News, Building
Research Establishment, Garston, Watford, United Kingdom,
Number 36, Summer 1976, pages 11-13.
(3) Holbeck, Kai, and Andersen, Povl R., European Concepts of
Construction Tolerances, Journal of the American Concrete Institute, March 1977, pages 101-108.
(4) Stephan, Dean E., Jr., and Murk, Alan, Establishing Tolerances
in Concrete Construction, Journal of the American Concrete Institute, May 1977, pages 208-211.
(5) Graham, J.R., and Lindholm, E.A., Concrete TolerancesImportance and Achievement in the Bureau of Reclamation Construction, Journal of the American Concrete Institute, February 1978,
pages 49-54.
31