Radio Network Single Site Verification Service


Delivery Guide
(For internal use only)

Prepared by
Reviewed by
Reviewed by
Approved by

Zhuyu, Huangchaoping, Ana Gallego

Date
Date
Date
Date

2008-10-28

Huawei Technologies Co., Ltd.


All Rights Reserved

2008-12-24

All rights reserved

Page1 , Total19

Internal Open

Revision Records
Date

Version

Description

2008-10-28

1.00

Initial.

2008-12-24

Author
Zhuyu, Huangchaoping,
Ana Gallego

All rights reserved

Page2 , Total19

Internal Open

Contents
1 Overview of Radio Network Single Site Verification Service.............7
1.1 Objective............................................................................................................................................................7
1.2 Application Scope..............................................................................................................................................7
1.3 Intended Audience.............................................................................................................................................7

2 Delivery Guide..............................................................................8
2.1 Prerequisites.......................................................................................................................................................8
2.2 Workflow...........................................................................................................................................................8
2.2.1 Preparation................................................................................................................................................9
2.2.2 Verification Test and Analysis................................................................................................................12
2.2.3 Tuning for Problems...............................................................................................................................12
2.2.4 Report Generation...................................................................................................................................12

3 Deliverables...............................................................................13
4 Checklist....................................................................................14
5 Responsibility Matrix...................................................................16
6 Remarks..................................................................................... 17
7 Annex......................................................................................... 18
8 Related Documents.....................................................................19

2008-12-24

All rights reserved

Page3 , Total19

Internal Open

Key words
Single Site Verification

Abstract
This guide defines the prerequisites, workflow, deliverables, checklist for deliverables, and
responsibility matrix of the Huawei radio network single site verification service. It aims to
guide the related service delivery departments and personnel to get familiar with the service
delivery content and to deliver the service by following the standard flow, thus delivering the
service with a high efficiency and a good quality.

Acronyms and abbreviations:


Acronyms and
abbreviations

Full Spelling

SSV

Single Site Verification

DT

Drive Test

2008-12-24

All rights reserved

Page5 , Total19

Internal Open

Overview of Radio Network

Single Site Verification Service


1.1 Objective
This guide defines the prerequisites, workflow, deliverables, checklist deliverables, and
responsibility matrix of the Huawei radio network single site verification service. It aims to
guide the related service delivery departments and personnel to get familiar with the service
delivery content and to deliver the service by following the standard flow, thus delivering the
service with a high efficiency and a good quality.

1.2 Application Scope


This guide applies to the after-sales delivery of the UMTS network single site verification
service.

1.3 Intended Audience


This guide is used by the on-site delivery engineers, network planning project managers,
service managers, and marketing personnel of Huawei.

2008-12-24

All rights reserved

Page7 , Total19

Internal Open

Delivery Guide

The purposes of SSV include:

Installation quality Audit (such as cross cable)

Parameter Audit (such as PSC, frequency)

Hardware problem checking

Function Verification

2.1 Prerequisites
The prerequisites include:

2.2

60% of total sites integrated (depend on different project scenario)

Cell planning report and site database

SSV template approved

Tools Setup

Probe and Assistant

MapInfo format map

Handset, scanner

Workflow
Before Single Site Verification, make sure that 60% of the total sites are integrated in the
network. The purpose for this is to guarantee the efficiency. This threshold can be changed,
depending on different project, or sometimes the pressure from customer, but please keep in
mind:

Please assess the project schedule carefully, dont put all the teams at the beginning.
Otherwise, a lot of money will be wasted;

Normally, one week is required for the DT team to get know how to use Huawei DT
software and how to test SSV items.

There are four stages in the single site verification.

Preparation

Verification Test and Analysis

Troubleshooting

Report Generation

2008-12-24

All rights reserved

Page8 , Total19

Internal Open

After most of SSV of cluster or network are finished, the initial tuning will start.

2.2.1 Preparation
Good preparation will improve SSV efficiency extremely, which includes following parts:
Tools Setup
Test Tools should be discussed with customer, and reach agreement with customer.
Normally, for the aim of cost-efficiency, Huawei will propose to use Huaweis tools, including
software (probe/assistant) and hardware (handset/datacard/scanner).
Besides test tools, TL(Team Leader) should prepare a computer, acting as RF server to store
the SSV log files and reports. It is better that the server can be accessed by internet so that the
test team can put the log file into the computer as soon as they finish test.

2008-12-24

All rights reserved

Page9 , Total19

Internal Open

There is one equipment to be provided customer: FTP server. The FTP server should be
located near the SGSN. It is recommended to test the FTP server and make sure that the server
is totally ok before SSV start.

SSV template
The template should be agreed by both customer and Huawei. Huawei could propose the
template to customer. The simpler the template, the more efficient the SSV delivery.
There are some suggestions:
1, Its better not test handover between NodeBs. This is because of the fact that when testing a
site sometimes the sites around it are not on air. Bear in mind that since adding and deleting
neighbor list is a heavy work. And that normally handover is not a problem, then, neighbor list
is better to be optimized during initial tuning phase.
2, Its better not to test handover between 3G and 2G. The reason for this is because it is
difficult to find a suitable place to do this kind of test.
Drive Test Route Planning
The test routes for each sites do not need to be approved by Customer, but the principles for
SSV DT route planning must be defined together with customer.
Basically the routes should cover all the sectors of each sites, main roads and important areas
within each cluster.
Drive Test Methodology Definition
Before starting the drive test, Huawei need to define the test methodology with customer,
including:

Test Method: long call, short call, throughput test method, etc.

Test Period

File Size for Download and Upload (throughput) and ftp window size configuration

Training
It is very important to train the SSV test technicians in order to improve their efficiency.
Normally, for most of the projects, subcontractors are recruited to finish SSV. It is very
common that these technicians have not worked with Huawei testing tools before. Besides, the
SSV items in one project are usually different to those in any other project. Then, its important
to train the technicians so that they can get familiar with the tools, and also with the working
flow of SSV test. Please, find below one example of working flow, which defines the test step
by step and how to name the log files. Its very useful.
After the training, normally one team should be able to test 5 sites per day, providing that the
template is not so complex.

2008-12-24

All rights reserved

Page10 , Total19

Internal Open

Site Status Audit


Before SSV test, information about site status must be confirmed from the RNC engineer. The
target for site status audit is to make sure the test site is working normally, otherwise it must
influence SSV. It includes:

2008-12-24

Alarm audit; (pay attention to transmission related alarms)

Cell status;

HSDPA/HSUPA status

All rights reserved

Page11 , Total19

Internal Open

Neighbor list checking (if handover is required to be test)

Basic parameters

2.2.2 Verification Test and Analysis


Drive Test and Analysis
Drive test must follow the route defined and the methodology defined. It should also include
an analysis and record all the problems that may have arisen during the test.
The post-analyze engineer needs to analyze and record the problems, troubleshoot and output
the SSV report according to the template.
.

2.2.3 Tuning for Problems


When abnormal events happen during testing a site, the test & analysis engineer has to
analyze the issue, give a recommendation and record all of it. After the recommendation is
approved internally and after it has been implemented, the SSV engineer has do verify that
site again.
Most of the problems in SSV phase are related to installation and parameter problems, so RF
Engineer has to distinguish the problems and send the solution to different teams, apart from
monitoring the troubleshooting progress. It is recommended to propose that installation team
prepares one team to be dedicated to troubleshoot SSV.
A SSV control table is required to record all the SSV actions, including problems, test times,
test date.and by the SSV control table it is easy to get progress statistics
Attachment is a reference for SSV control table.

2.2.4 Report Generation


Once the test result is acceptable and problems are solved, generate the SSV report.
Refer to <SSV report template> for detail information and format.

2008-12-24

All rights reserved

Page12 , Total19

Internal Open

Deliverables

Deliverables of Model Tuning


Item

Description

Contents

SSV control table

Record all the SSV action

Single Site
Verification Report

test result according to the


template

2008-12-24

All rights reserved

Remark

Page13 , Total19

Internal Open

Checklist

Network Evaluation Checklist


Module

Category

Preparation

Item

Check
by

Probe and Accessory Ready

The Digital Map in MapInfo Ready


Tool Setup

FTP Server for throughput Test: provided or agreed by


Customer
RF server for store log files and report
SIM Card Provided by Customer

DT Route
Planning

Principles for Test route for SSV be defined together with


customer

The test routes should cover all sectors of each sites, main road
and important areas
all cells status is ok

Site Status
Audit

HSPA status is ok
Parameter check
No Alarm may influence SSV Test

DT

2008-12-24

Test Method Defined: long call, short call, data test, etc.

All rights reserved

Page14 , Total19

Internal Open

Methodology
Definition

SSV Report

2008-12-24

Single Site
Verification
Report

Test Period Defined


File Size for Download and Upload (throughput)
SSV Report template agreed by customer

Please refer to the template: <Single Site Verification Report


Template.xls>

All rights reserved

Page15 , Total19

Internal Open

Responsibility Matrix

Responsibility matrix is very important factor for service delivery; it should be rooted in
project contract or service quotation. The following table is a suggestion from Huawei, and
the final result should be based on customer requirements and the actual situation may vary in
each project.

No.

Task

Huawei

Customer

Tools Setup

DT Route Planning

DT Methodology

SSV Test

Data Analysis

Proposal and
Implementation

Report

2008-12-24

All rights reserved

Both

Page16 , Total19

Internal Open

Remarks

A.

In order to improve the efficiency, it is suggested to do SSV after more than 60% sites
integrated, except the swap project. This percentage should discuss with customer.

B.

Before SSV, make sure the site status is normal.

C.

SSV Test must follow the defined route and defined test methodology.

D.

When drive test and analysis, pay more attention on Cross Connection of antenna or
feeders.

2008-12-24

All rights reserved

Page17 , Total19

Internal Open

Annex

Annex 1 SSV control table template


Annex 2 UMTS Single Site Verification template

2008-12-24

All rights reserved

Page18 , Total19

Internal Open

Related Documents

<GU-Single Site Verification Guide>Describe the SSV working flow, how to test for
each item.
<W-Test Guide>: Describe how to do drive test.