6M OD Tank Hamriya Free Zone Phase-I

10-Dec-16 10:31

Project Update From HFZ Phase-1 (QICL)

Activity Activity Name


ID

Original
Duration

Start

Finish

Q010

Project Start

0d

Q020

Project Finish

0d

Q030

Bottom Plate Prefabrication(Marking, Inspection, Cutting)

9d

26-Sep-16 A

05-Oct-16 A

100% Completed

Q040

Fitup, Inspection of Tank T550,T560

7d

26-Sep-16 A

03-Oct-16 A

100% Completed

Q050

Bottom Layout, Fitup, inspect &Welding

13d

05-Oct-16 A

19-Oct-16 A

100% Completed

Q060

Weld Visual & Radiography of Bottom

4d

19-Oct-16 A

23-Oct-16 A

100% Completed

Q070

Shell Plate Prefabrication(Marking, Inspection, Cutting, Rolling

21d

05-Oct-16 A

29-Oct-16 A

100% Completed

Q080

Shell Erection Ls(Longseam)joints Fitup,Inspection

26d

17-Oct-16 A

15-Nov-16 A

100% Completed

Q090

LS(Longseam) Joints Outside Welding

35d

18-Oct-16 A

27-Nov-16 A

100% Completed

Q100

LS Joints inside BacKchip, DPI& Welding

26d

22-Nov-16 A

25-Dec-16

88.46% In Progress

Q110

CS(Circumferenceseam) Joints Fitup Inspection & Welding

26d

01-Dec-16 A

25-Jan-17

15.38% In Progress

Q120

CURB Angle Fitup,Inspection

10d

01-Dec-16 A

12-Dec-16 A

Q130

CS (Circumferenceseam)Joints Shell Outside/CURB Angle Welding

28d

05-Dec-16 A

31-Jan-17

21.43% In Progress

Q140

Shell Outside Grinding/Cleaning

26d

08-Dec-16 A

02-Feb-17

11.54% In Progress

Q150

Shell Inside Grinding/Cleaning

15d

19-Jan-17

05-Feb-17

0% Not Started

Q160

Shell to Bottom Fitup, Inspection & shell inside welding

15d

16-Jan-17

01-Feb-17

0% Not Started

Q170

Oil Choke Test & Outside Weldig

13d

16-Jan-17

30-Jan-17

0% Not Started

Q180

Weld Visual & Radiography

10d

21-Jan-17

31-Jan-17

0% Not Started

Q220

Wear Plate Prefabriction Fitup,Inspection Welding

8d

21-Feb-17

02-Mar-17

0% Not Started

Q230

Anchorchair Prefabrication Fitup,Inspection & Welding

5d

21-Feb-17

27-Feb-17

0% Not Started

Q240

Project Close Out

1d

27-Feb-17

28-Feb-17

Q250

N1,N2,N3,N4,N9 Prefabrication of RF PAD

1d

16-Nov-16 A

16-Nov-16 A

Q260

N1,N2,N3,N4,N9 Fitup Flang to Neck

1d

02-Feb-17

02-Feb-17

0% Not Started

Q270

N1,N2,N3,N4,N9 Shell To Neck Marking, Cutting, Inspection

1d

02-Feb-17

04-Feb-17

0% Not Started

Q280

Nozzle to Shell Neck/RF PAD Fitup & Welding

2d

02-Feb-17

04-Feb-17

0% Not Started

Q290

N8 Prefabrication of RF PAD, Neck, Flang, Inspection

2d

04-Feb-17

06-Feb-17

0% Not Started

Oracle Corporation

Page 1 of 2

26-Sep-16 A

Activity % Activity Status


Complete
100% Completed

28-Feb-17

0% Not Started

100% Completed

0% Not Started
100% Completed

6.6M OD Tank Hamriya Free Zone Phase-I

10-Dec-16 10:31

Project Update From HFZ Phase-1 (QICL)

Activity Activity Name


ID

Original
Duration

Start

Finish

Activity % Activity Status


Complete

Q300

N8 Fitup, Inspection, Flang to Neck / Welding

3d

06-Feb-17

09-Feb-17

0% Not Started

Q310

Shell to Neck, N8 Marking, Inspection, Cutting,

3d

09-Feb-17

13-Feb-17

0% Not Started

Q320

Nozzle to shelll RF Pad/Neck, Suportbracket Fitup, inspection & welding

5d

13-Feb-17

19-Feb-17

0% Not Started

Q330

New Activity

6d

26-Sep-16

02-Oct-16

0% Not Started

Q340

N7 Prefabrication of (RF PAD, Bolting Flang, Cover & Neck)

1d

17-Nov-16 A

17-Nov-16 A

Q350

N7 Flang to Neck Fitup, Inspection & Welding

1d

19-Feb-17

20-Feb-17

0% Not Started

Q360

Nozzle to Shell Neck/RF PAD Fitup & Welding

1d

20-Feb-17

21-Feb-17

0% Not Started

Q370

Shell to Neck, N8 Marking, Inspection, Cutting,

1d

19-Nov-16 A

19-Nov-16 A

136d

26-Sep-16 A

02-Mar-17

Total

Oracle Corporation

Page 2 of 2

100% Completed

100% Completed