EXTERNAL ALIGNHENT PROCEDURE
FoR
ROTARY KILNS, COOLER, DRYERS,
‘AND SIMILAR ROTATING MACHINES
FULLER COMPANY
124 BRIDGE STREET, CATASAUGUA, PA. 16032, USA.
SERRA gud to anne Sale esa naan ae nuns SOUTH amc» CURB OEE
728-75~1-8801
Sheet I of 13TABLE OF CONTENTS
INTRODUCTION.
REFERENCE MEASUREMENTS
SETUP FOR HORIZONTAL MEASUREMENTS
Checking for Pler Shifting. 4. + «+
Horlzontal Allgnment Check os 1 4s
Alternate Setup. + v-
SETUP FOR VERTICAL MEASUREMENTS , 445
VERTICAL ALIGNMENT 4... 0
CORRECTING ALIGNHENT
wae 3
sae 3
mg
sae 8
sae 9
wae 12
728-75-1-8801
Sheet 2 of 13INTRODUCTION
These procedures are Intended for use in checking shell alignnent.on a
rotary kiln, cooler, dryer, or simblar type of rotating machine from the
‘outside when benchnarks are not avallable as reference points.
A series of procedures are requl red to make a complete alignment check
by this method, It is Important to perform them all, to make accurate
setups, sightings, and measurements, and to recard data carefully. In
many cases, making skatches to depfct the conditions will clarify the
nature of an allgnnent problem and help determine the best course for
correcting It.
Refer to the machine's Installation, operation, and maintenance Instruc~
tions for additional pertinent alignment Information.
REFERENCE MEASUREMENTS
Prepare a sketch of the machine, showing and Identifying each riding ring
and support roller. Hake the following measurements and calculations,
recording them on the sketch:
+ Measure the circumference of each riding ring and calculate its
radius.
+ Heasure the circunference of each support roller and calculate its
radlus.
+ Measure the clearance between each riding ring and the pads on the
shell at the top of the machine.
Retain this Information for use In making calculations and in determining
appropriate corrections in shell alignment.
SETUP FOR HORIZONTAL MEASUREMENTS
In the setup procedure which follows, the object Is to accurately locate
a transit on a preselected horlzontal offset Ine which Is parallel to the
centerline of the machine, Once the Instrunent 13 in the desired posi-
tion, It {is left there unt!] all horizontal measurenents have been com
pleted. The first and last plers are used as reference points under the
assumption that nelther af them has shifted. Subsequent measurement may
Indicate this assumption to be wrong and require the selection of other
references.
Two horizontal measurements will be made on each pier. As shown In Figure
1, meagurenents for pier shifting will be made from the centerlIne nark on
each support frane and allgnment measurerents from the horizontal diameter
of each riding ring. The location of the offset, therefore, mst be se-
lected to permit a clear view of these points through the transit when it
Is set up on the firing floor. The offset may be to either side of the
728-75~ +8801
Sheet 3 of 13g OFFSET
MEASUREMENTS
FOR SHELL
ALIGNMENT
MEASUREMENTS
CENTERLINE FOR PIER
MARK ON SHIFTING
SUP PORT
FIGURE 1
HORIZONTAL ' MEASUREMENTS
machine. If any enclosures obstruct the line of sight, remove sections of
wall siding as necessary.
After selecting a suitable location for the offset, proceed as follows:
a, Set the transit on the firing floor at a location which gives a
clear view along the offset to each of the points where measurenents
will be made.
b, Select 9 straight rod or plece of wood approximately 2 inches by 2
inches and of sufficient length to reach from the center of a sup-
port mechanism to 3 point at least 6 Inches beyond the offset.
c. Measure the horizontal distance from the selected location of the
offset to the centerline mark on the support frame of the reference
pler at the discharge end,
728-75-1~8601
Sheet 4 of 13,From the squared end, measure an equal anount on the rod and make
a pencil mark.
fe. At the feed-end pler, carefully align the squared end of the rod
with the centefline mark on the support Frané.
f. Holding the rod horizontally hevel on the feed-end pler and par-
allel to the edge of the support beam, sight on its premarked re~
ference point and lock the transit to’ prevent Its turning. Hold a
pencl! point or small target at the reference point to facilitate
sighting.
g- Move the rod to the reference pier on the discharge end and" pos!~
tion It in the sane way.
fh. Without disturbing the transit except for elevation, sight on the
rod at the discharge~end pler and mark the polnt at which the line
of sight crosses it. Heasure the distance between this point and
the premarked reference point,
i, Adjust the position of the transit as necessary until the vert!-
cal hale falls on the reference mark when the rod is placed on
both reference plers.
Completion of this procedure locates the transit's line of sight to be
equidistant from the machine's centerline at the reference plers and es-
tablishes the offset from which the horizontal measurements can be made.
CHECKING FOR PIER SHIFTING
With the Instrument in the setup condition, perform the following at each
support. mechani s1
‘2. Hold the rod horizontally level and parallel to the edge of the
support frane bean. Nove it as necessary to allgn the reference
mark with the telescope's vertical halrline.
b. Heasure and record the distance from the squared end of the rod
to the centerline mark on the support frame. The measurement
indicates the anount the pler has shifted horizontally.
The Figures recorded will be used In determining the type and amount of
corrective alignment to be taken after all measurements have been taken.
Lf significant variations have been recorded, prepare a sketch showing the
relative positions of all support mechanism centerline marks. Analysis
Of the sketch may indicate that corrective alignnent can be minimized by
selecting one or two different reference plers.
The feed-end and discharge-end piers are used Initially because of thelr
being at the ends of the shell and because, with housings and and other
equipment attached to then, corrections are not as easily made at these
728-75~1-8801
Shest 5 of 13locations. If changing a reference point Is advisable, give special con=
sideration to the thrust pier. Usually it is desirable to avoid changes In
the mesh and alignnent of the drive and pinion gears or In the alignment of
the other drive components. In addition, the relationship of the thrust
roller centerline and the kt in canterline estab! shed'at Installation must
be maintained, and there Is little lateral adjustment which can be made to
a thrust roller.
HORIZONTAL ALIGNMENT CHECK
The object of the horizontal alignment check Is to determine the anount the
Shell's actual centerline deviates from Its true centerline In the horizon=
tal direction. Quarterpoint readings from the riding rings to the offset
are taken on each pler and compared with a sinilar dimension derived from
the preceding measurenents. The differences between then represent the
horizontal deviation of the centerline. Proceed as follows:
@ Square at least one end of a straight plece of 2 Inch, by 2 inch
wood, long enough to extend from the horlzontal diameter of the
shell to a point about 6 Inches beyond the offset.
5. Using a centerhead and level In the manner shown In Figure 2, deter-
mine and mark the horizontal centerpoint on the face of each riding
ring. Level carefully to obtatn an accurate mark.
c. Hold the squared end of the rod against the centerpoint mark on the
first riding cing, keeping It horizontally level and at right
angles to the ring.
dy With the transit still In its setup position, sight on the rod and
mark the point where the line of sight Intersects Tt. Measure and
record the distance from the squared end to the mark.
ce. Repeat steps c. and ¢. at each riding ring.
fF. Referring to Figure 3, determine for each riding ring the dimension
Z, by subtracting the calculated riding ring radius R In the ref-
erence measurenents fron the distance Cy, measured In the check for
pier shifting.
Compare the Z, distances measured In steps d, and e. with the Z,
Figures calculated in step f, Differences between the two Figures
at each pler represent the deviation of the actual centerline from
the: rue’ one.
fh. Rotate the shell 90, 180, and 270 degrees, making and recording Zy
measurenents for each riding ring at each quarterpoint.
I. Compare al! four quarterpoint measurenents at each riding ring to
determine if an average deviation dimension should be calculated
for any ring prior to using the figures In the realignment analysis.
728-75-1-8601
Sheet 6 of 13RIDING RING
CENTERHEAD
_e
FIGURE 2
RIDING RING HORIZONTAL CENTERPOINT
This completes the horizontal measurements. Proceed with the vertical
setup and checks.
728-75~1-8801
Sheet 7 of 13RADIUS R
g (Calculated)
FFSET
Zm (Measured)
Ze (Calculated)
Cm (Measured)
CENTERLINE
MARK.
FIGURE 3
HORIZONTAL MEASUREMENTS & CALCULATIONS
ALTERNATE SETUP
At sone installations it Is Impossible to sight the transit from the firing
roon Floor for horizontal measurements. In such cases, It is usually pos-
sible to make the setup ona corner of the pler at the discharge end and
gain a clear line of sight by renoving guards, rails, and other minor ob-
structions. To use this method, proceed as follows:
Select a polnt on the pler whlch will glve Hne of sight visibility
to each pier and riding ring. Mark the point with a punch,
Setup and align the transit with the punch mark, using the plumb
bob.
Measure the distance from the punch mark on the pler to the center
line mark on the support frame beam,
At the feed-end pier, establish a reference polnt on the pler the
exact distance from the centerltne mark measured in step c.
Sight the telescope on the feed-end reference mark and lock the
transit.
728-751-8801
Sheat 8 of 13This completes the setup. Use the procedure detafled in the preceding
paragraphs to make the horizontal measurenents,
SETUP FOR VERTICAL MEASUREMENTS
In the setup procedure for vertical measurements, the object 1s to eccur-
ately position the transit on a line parallel to’ the centerline of the
machine but offset above the shell. Once the Instrunent 1s at the de-
sired helcht and the telescope locked at. the machine's angle of slope, it
is left there until ail vertical meesuronents have been conpleted, — ThIs
Procedure uses the discharge-end and feed-end riding rings as reference
points,
Proceed as follows:
a, Set the transit on top of the firshood withthe, IIne of sight
along the centerline of the machine and at the shell's angle
of slope. Adjustments to this Initial setup wil! be made in
Subsequent steps. As necessary, renove panels from enclosures
to galn a clear view of each riding ring.
Square at least one end of a stralght plece of 2 inch by 2 Inch
wood, long enough for conventent use in making the measurements
described below.
¢. Using a centerhead and level In the manner IIlustrated In Figure
4, locate and mark, the top end of each riding ring's vertical
dianeter.
4. At the feed-end riding ring, use a, level to hold the wooden rod
plunb with the back edge of the squared ond against the center-
line mark in the manner shown in Figure 5.
fe. Sight on’ the vertical rod and mark the’ point where the tele~
scope's horizontal halr crosses the réd. Use a pencil polnt or
a small rectangular target to assist In sighting.
f. Repeat steps d. and'e, at the discharge-end riding ring
9. Hake @ correction to account for any differences In riding ring
radii which were calculated under the paragraph entitled REFER-
ENCE MEASUREMENTS. If one ring Is smaller than the other, add
the difference to the smaller and make 2 new mark on the rod for
that ring.
h, Adjust the position of the transit until the marks as corrected
instep g. both fall on the hortzontal hair without changing the
ingtrunent:: When alignment Is Sthieved, lock the transit. Mo
further changes in height or elevation will be made until all
vertical measurements have been conpleted.
‘This completes the vertical setup. The transit's Ine of sight Is now
728-751-880)
Sheet 9 of 13,vertical from and parallel to the machine's true centerline.
CENTERHEAD"
RIDING
RING
FIGURE 4
RIDING RING VERTICAL CENTERPOINT
728-75~1-8801
Sheet 10 of 13LINE OF SIGHT
LEVEL
—
CENTERLINE MARK
RIDING RING
FIGURE 5
TECHNIQUE FOR VERTICAL MEASUREMENTS
VERTICAL ALIGNMENT
The object of the vertical alignment check Is to determine the anount the
shell's actual centerline deviates from the true centerline In the ver~
tical direction. Quarterpoint readings fron the riding rings to the off-
728-75~1~8801
Sheet M1 of 13When makIng adjustments, keep the axis of each roller parallel to the
axis of the machine. Parallelism can usually be determined by using a
tranme! to measure from the center of the roller shaft to the center! ine
mark on the support frane. On floating klIns, reskew the rollers after
the machine Is back in operation,
728-75-1~8801
Sheet 13 of 13INSTRUCTION MANUAL
FOR
ROTARY KILNS, COOLERS, DRYERS,
AND SIMILAR ROTATING MACHINERY
FULLER COMPANY
A GATX COMPANY
P.0. BOX 25, CATASAUGUA, PENNSYLVANIA 18032, U.S.A.
otras 240 arcuRTES HPA FAIS» LONDON ENGLAND « SAN SRASTIN PA +
SEURIN nan’. "FoRanvo suo Mawrnest’canaon = ate acu bs nse ssOuannebena dui aS HCk SoaaN OAS Meet CoM at
726-75-1-8800-1
Sheet ! of 46TABLE OF CONTENTS
INTRODUCTION
INSTALLATION
Pre-installation Considerations
Foundations
Support Mechanisms | |
Shelve ee
Main Gear and Piaton " )
Drive Units ye ee
Electrical tnstailation | | |
Fre Hood vy eee ee
Feed Hood 6 yt
Nose Ring ve ee ay
Burner ve ee
Refractory Lining 21.
Check-Out vee eee
Drying Refractory 2 tft
Post-Installation tdie Time
OPERATING INSTRUCTIONS...
Sefetyse rete
Stopping vt
Emergency Shut=Bown | 2.
Power Failure eee see
fuxiary Drives 2d
Skewing Rollers 5 os ee
Cold Weather Operation.
MAINTENANCE ee ee
Checklists and Records =.
lubrication see... ce
Kiln Allgnnent So0u00
fuxi tary Orive Unit 2 2
Refractory se we tte
Haln Gear and Pinton |.
Support=Roller Bearings.
Thrust-Roller Sleeve Bearings
Erratic KIIn Rotation...
SPARE AND REPLACEMENT PARTS
au
26
Dog
27
28
23
29
30
Hu
on
+ 2B
ead
» 33
3
+ 3h
oH)
38
38
40
4)
ay
at
2
42
43
46
728-75~1~8800
Sheet 2 of 46INTRODUCTION
These instructions cover the Installation, operation, and maintenance
of Rotary Kilns, but because of the any similarities whlch exist, they
are also generally applicable to Coolers, Dryers, and other rotating
machines.
Machines of this type do not operate in an independent environment, but
are always part of a system which includes a nunber of other pieces of
equipment, all of which must function together under close control. The
systen can exist in many sizes and configurations depending on the appli-
catlon. The same Is true for these machines. In addition, the nature
of the fecd material and the results to be achieved determine the char-
acteristics of the process and the detailed design of the machine, For
these reasons, each machine varies as necessary to accommodate the appli-
cation, Regardless of these considerations, all of these rotary machines
are similar in basic design, function in the same ways, have the same
baste relationships with other elenents In the system, “and require the
same general considerations for installation, operation, and malntenance.
It Is these factors with which these instructions deal.
INSTALLATION
Installation is to be made In accordance with the drawings provided.
They define the physical arrangements, pertinent dimensions, nechani.cal
and electrical Interconnections, ratings, capacities, loads, and other
characteristics, data, and Information needed In the erection and instal le~
tion of all components supplied. The arrangement and assenbly drawings
designate al] parts by Item numbers. The parts IIsts are arranged In acy
cordance with these Iten nunbers and Identify each iten by Its proper name.
While there is a general, over-all sequence of installation which will be
followed, there are many’ details for which the sequence wil! be determined
by conditions existing on site, some of whlch will be determined by the
design and configuration of the machine itself, and others for which the
sequence can be determined by local preference. Also, nany different
methods and techniques can be used to achieve the desired results in a sat~
Isfactory manner. In those Instances where these instructions provide the
cetalls of a technique, the purpose is to suggest one whlch has been used
successfully rather than to indicate a mandatory course.
728-75-1~8600
Sheet 3 of 46This section of these instructions provides an overview of the Installa~
tlon and presents Important detal] on Individual assenblies, component:
and various other facets of installation which will be helpful in deters
mining and employing the sequences and techniques used at a speci fle site.
PRE-INSTALLATION CONSIDERATIONS
The Kiln Includes preciston bearings and a nunber of machined surfaces
and’parts, all of which require protection from adverse anbient condi
tlons.~ Although these conponents are adequately protected for shipment,
the protective materlels have @ relat Ively Im ted life and should not be
depended upon for extensive periods. At the tine that each of these con-
ponents Is to be Incorporated into the assently or mated wlth other parts,
Tt Is essential that It be cleaned and inspected thoroughly, .Bearings
must be cleaned, flushed, and lubricated, Coat all Internal surfaces of
bearings with bearing lubricating ol]. 0 not use grease. If the bearings
wil! be Idle for an extended period after cleaning, it Is suggested that
undiluted STP O71 Treatment or an equivalent product be used to form the
coating.
The Kiln 1s shipped In a disassembled state for erection on-site. The
shell is shipped In sections which must be positioned, aligned, and welded
together. Sefore Installing parts, renove the protective coatings applied
for protection during shipment. MachIned surfaces, oll passages and
pipes, water passages and pipes, and reservolrs must be free of all foreign
matter. Inspect all machined surfaces and screw threads to be sure they
are In proper condition for assenbly.
Whenever practical, the Kiln should be enclosed in a suitable structure to
protect It fromwind, rain, and snow, These elements tend to cool the
shel! and put compress! ve forces on the refractory which can cause It to
crack. Rotatlon of the Kiln cannot be. stopped In the presence of these
elements because the uneven cooling can cause serious warping which may be
both difficult and expensive to correct.
FOUNDATIONS
The Kiln and Its drive units are to be Installed upon foundations whi ch
728-75- 1-880
Sheet 4 of 46must be designed to support the waight of the equipment and the loads
Occurring during operation. These toads and the general foundation out~
lines are identified on the drawings, but the detailed design Is depend-
ent upon the nature of the geological substructure on which they rest at
the specific site. Particular attention must be given to avoiding con-
ditions which could result In settling. The ability of the Klin to retain
Its alignnent depends primarily upon the foundations renalning Fixed.
lt Is of particular Importance that the plers are properly located with
respect to elevation, spacing, and alignnent. The alignment of the Kiln
and center-to-center spacing Of various components depends on the precise
location of the foundations and foundation bolts. Thelr positions should
be checked and rechecked to ascertain that they renaln fixed. The top of
the foundat Ions should be left rough to provide good anchorage for grout.
To aid fiture Kiln alignment checks, permanent bench marks should be pro
vided on each pier. The bench marks should be brass plugs located on the
top of the plers on each centerline in the plan view. Bench marks for use
in checking for movement of the foundations should be established away
from the foundatlons.
The location of foundation bolts with respect to both plan and elevation
should be checked carefully agalnst certified drawings. Their location
with respect to those on other piers must also be checked. Frequently,
the longitudinal centerline through the piers Is obstructed, In such
case, run an offset line on the side avay from the drive and measure all
locations from it, Use diagonal measurements to verify that the bolts
have been located squarely. Make certain that allowance Is made for shins,
grout, equipment bases, and mountIng hardware.
SUPPORT MECHANISMS
After the foundations have been completed, the support mechanisms must be
assenbled on the piers. The frame is the first component to be mounted,
and it is positioned with particular care. The bearings and rollers are
then placed on the frame, located with respect to the Frane's centerline,
and aligned with respect to each other.
FRAMES
The Installation of the frames requires the use of shims. It Is recom=
728-75-1-8800
Sheet 5 of 46mended that the supply of steel shim stock for use on each pler consis!
of one plece each of 1/16-inch, 1/4-Inch, 3/8-Inch, and 1/2-Inch thick.
ness in 3-inch widths and 16-foot lengths; two pleces I-Inch thick by
elther 3 or 2 Inches wide and 16 feet long; and standard rolls of 6-inch
Wide stock In thicknesses of 1/32-Inch, .010 inch, .008 Inch, .006 Inch,
+004 inch, and .002 inch, Cut the shims’ to 4~inch lengths.
norice
SETTING THE FRAMES FOR THE SUPPORT ROLLERS 1S THE NosT
VHPORTANT AND TIME CONSUMING PART OF THE FNSTALLATION
PROCESS. IT MUST BE DONE WITH PARTICULAR CARE AND EACH
STEP CHECKED AND RECHECKED. THE FINAL CHECK I$ TO BE
MADE IN THE EARLY MORNING BEFORE DIRECT RAYS FROM THE
‘SUN AFFECT THE SETTING.
Each frame rests on stacks of shims which raise It to the speci ied ele-
vation. The stacks of shims are located on both sides of each foundation
bolt. The bottom shim in each stack Is usually of I-inch=thick stock, set
in grout, and leveled In the transverse direction but parallel to the slope
of the Kiln In the longitudinal direction. The bottom shim is set low
enough to allow additional shinming. The shin should be centered with re-
spect to the web of the support beams rather than the anchor bolts. The
anchor bolts pass through the sides of the bean flanges and using then as
a reference would result In the shins being Incorrectly located. The bot-
tom shim In each stack Is°set by placing a snail azount of grout under it,
then carefully positioning It. The grout should be allowed to set for one
to two hours, then the levelness and slope rechecked. After the shim has
been positioned accurately, wrap the grout in wet burlap and allow It to
set for 24 hours, After this period, recheck the shin's position.
Once the bottom shims have been properly positioned and verified, the
frane can be placed on them. The top can be Identified because it and the
Inner edges of the top Flanges have been machined. Sone franes are marked
to Indicate the feed side. When this mark Is present, set the frane so
that tt Is on the up-hIil side, Unless the KIIn Includes 9 hydraulle
thrust system, only one thrust frane will be provided. This frane is used
under. the riding ring closest to the girth gear. To assist In alignnent,
both centerlines of the franes are marked by saw cuts in the flanges.
Each frame must be set to the exact elevation, slope, and center-to-center
distance between plers specified, Add shims to each stack to raise the
frame to the specified elevation and set the centerlines of the frame to
the centerlines of the pler. A block tapered to the correct slope is pro-
vided for each installation. It should be used in conjunction with a
728-75-1~8800
Sheet 6 of 46nachinist's leve] to achleve the specified angle. The center-to-center
distance from one pler to the next Is measured with a tape. It is manda=
tory to use a spring scale to apply tension to the tape while the measu
tment is belng made and a thermometer to Indicate the tenperature of the
tape at the time of the measurement, The tape measurenent must be cor
rected to a temperature of 70°F.
hen the frame has been accurately positloned and bolted down, it is re~
checked. The center-to-center distance from one pier to the next should
be within plus or minus 1/16-inch. The tolerance on the elevation Is
plus or minus 1/16-Inch. The slope must be within 0,002 inch-per-foot,
and In the transverse direction it must be within 0.002 Inch-per-foot of
being level. The final check of the slope is made-on the rollers after
thay have been assenbled to the frame. At that time It may be necessary
to make minor adjustnents In the shimalng to keep the installation with
in the specified tolerance.
BEARINGS AND ROLLERS
After the frane Is in place and secured, the bearings and the rollers they
Support are assembled to it. The machined surfaces on the frame are lub~
ricated with @ graphited grease or sone other anti-seizing grease before
placing the bearings on It. When anti-friction bearings are provided,
they are assembled to the rollers at the factory. When sleeve bearings
are supplied, they aust-be assembled to the rollers on-site. They may be
assenbled In place or subassembled first then Iifted into piace.
If the bearings and the roller are assembled In place, one bearing Is
mounted on the frane, the end of the roller shaft slipped Into it, then
the other bearing slipped onto the other end of the shaft. The shaft must
be supported In position so that the second bearing can slide across the
frane and onto the shaft. Rollers are stamped to identify the feed ond
and must be positioned accordingly. It 1s also pernissable to subassenble
the roller, shaft, and bearings on the ground and lift then into position
as a unit.
When: lifting a bearing-roller subassenbly, it 1s mandatory that a proper
sling arrangement be used. Provide a sling for each bearing and use a
spreader bar, Hake certain that the roller shaft will be In constant,
full contact with the bearings and that the entlre subassembly will remain
level while tt Is being lifted.
CAUTION
DO NOT LIFT THIS SUBASSEMBLY BY THE ROLLER
728-75~1-8800
Sheet 7 of 46Set the bearings from tranmel measurements made between the rollers and
the centerline marks on the frame. If the Installation 1s being made from
an offset line, the roller nearest the line should be set from the line,
and the opposite roller set by a pin gauge batween the rollers. When the
bearings are properly set, both rollers will be parallel to each other and
to the longitudinal centertine. Check for parallelism by placing a stral ght-
edge across the machined edges on the ends of both rollers. It {s not In=
portant for the ends of the rollers to be In line with each other; only
that they be parallel.
Sleeve bearings are not secured to the frames, but provisions are made for
each anti-frictton bearing to be held down by four bolts,
After sleeve bearings and thelr rollers have been assembled arid positioned,
they must be checked for shaft end-play, Total space for movement of the
shaft must be not less than that shown below for the corresponding roller
size.
ROLLER DIAHETER MINIMUM END~PLAY
33 through 39-Inch 1/16-Inch
42 through 72-Inch 1/8 Inch
78 through 84~tnch 3/16 Inch
90 inch and up be inch,
If additional clearance is required, efther renove stock from one of the
thrust keys mounted between the bearing base and the support or Insert
gaskets behind one of the end covers.
ith the sieeve bearings and rollers set, the seals, oll elevators, and
other ancillary Items can be Installed when It Is convenient to do so. A
shaft seal Is installed on the side of the bearing nearest the roller and
held in place with a cover plate. Of1-Fill pipes for the bearings are in
two sizes. The longer up-right plpe belongs on the downhill bearing; the
shorter one up-hill. The threads on the oll fIII pipes should be covered
with pipe fitter's dope or teflon tape and screwed In tightly to avoid
leaks.
The bearing ené plate must be renoved to install the oll tray and the of]
elevators. Care must be taken in Installing the tray to allow clearance
for the elevator to rotate without striking It. In assembling the of]
elevators, make certain that lock washers are placed on the bolts and that
the bolts are secured tightly to the end of the shaft. It is possible to
install the elevators backwards. Check them with respect to the direction
of roller rotation and verify that they are Installed to fill with oll at
the bottom of the sump, lift It, then pour It at the top of the shaft.
Water must be piped to each bearing for cooling. A suggested piping
arrangement 1s shown on Figure 1 which also tadulates the quantity of
728-75-1-8800
Sheet 8 of 46Water required at each pler according to the size of rollers employed.
Drain lines should include an air-break and funnel to permit observation
of the flow and to make temperature checks, Because the movenent of the
bearing toward or away from the shell can range between four and five
inches, the inlet lines must Incorporate flexible sections. The funnel
for the drain Vines must bs of a design which will also accommodate such
movenent, Install a valve in each inlet line to permit control of the
Flow. Locate piping so that it doesn't Interfere with the use of the
bearing positioning screws. The piping and funnels are not normally sup~
plied as part of the Kiln.
After final assembly of @ bearing has been completed, fill its sump with
oil. Refer to the lubrication Instructlons In the MAINTENANCE Section,
THRUST ROLLERS
Thrust rollers are Installed before the shell sections are positione
Offset then 1/16 to 1/8 inch toward the donvard-turning side of the
shell so that when they are in contact with the rotating riding ring
there will be 2 small, downward thrust to keep then seated in thelr sup-
port brackets, There is an ofl-fII1 standpipe for each thrust roller.
The longer one goes on the down-hill roller; the shorter one up-hill.
Shims placed between the back of the brackets and the lug on the top of
the frame are used to achieve and maintain the specified spacing between
the thrust rollers and the riding ring, Thetr final Installation cannot
be completed until the shell Is Installed, welded, and the riding ring
is in its final location. After this has been accomplished, and If they
are included for this Installation, the bracket and block of graphite by
which the face of each thrust roller Is lubricated can be mounted,
On full thrust machines, only the dowo-hiT1 thrust rolfer has the full
thrust capability. If this thrust roller contains a sleeve bearing, it
will be water-cooled and it wlll be necessary to Install piping to and
from it. If a hydraulle thrust mechanism Is provided, refer to the sep-
arate Instructions for pertinent Installation information.
GROUTING
hen the mounting of the components of the support mechanism has been com-
pleted, the frame can be grouted. The shins must remaln In place. If
there is any grease or of! on the top of the pier, it must be renoved or
neutralized; otherwise, It will prevent the grout from bonding.
The rough top of the pler must be thoroughly saturated with water to
728-75-1+8800
Sheet 9 of 46 |s 2g
3g | aie 55
re thee | UL
ie | se
ae Pe 7
pee sbi ae Wg
3583 ei ist ES |
g2a% Sez | z
£ no &
z
eu: |
° 8
g
of
SIDE ELEVATION
Lf
UE
tL
728-75-1-8800
Sheet 10 of 46
FIGURE 1 SUGGESTED WATER PIPINGprevent absorption of water from the grout and to insure 2 good bond be~
tween the grout and the concrete. Keep the pler wet for at least 12
hours before grouting If the foundation Ts less than 28 days old and for
at least 24 hours ff it is more than 28 days old,
The grout should be dry-packed If practical, otherwise, concrete of 2-to~
Jrinch slunp can be used, If destred,.a metallic non-shrinking grout can
be used with standard cement. Use one part cement to one.part coarse,
clean sand. If the grout thickness specified on the drawing 1s 2-1/2
_ Inches or more, add one part 3/8-Inch or 1/2sinch clean stone.
Start from the outside of the beams and work from the Inside only when
grout from the outside appears on the Inside, Grout must fill the space
under the beams to Insure full bearing at all polnts. It is customary
ela ecfonte eee coi least the top surface of the bottom
ange.
‘The grout should set from 18 to 24 hours at tenperatures above 70°F be~
fore the forns are removed. If the temperature Is below 70°F, the follow
Ing applies: at 60°F, 2-1/2 days; at 40CF, 4-1/2 days. The grout should
be allowed to set for'at least 7 days before the equipment ts placed. in
operation. If the grout manufacturer's Instructions are available, however,
follow them.
After the forms are renoved, the edges of the grout should be kept damp
for several days, then a commercial curing compound app! ted.
‘SHELL
The shell is shipped in sectlons, the lengths of which are determined by
Himltations imposed by transportation and handling fecllities. Bracing
is welded inside each section for shipnent to help prevent distortion
while it Is belng handled. Depending on the dlaneter of the shell, the
riding rings may or may not be factory~assembied to their shell sections.
If they are not, they must be put on before the shell sections are posi-
tioned on their support rollers, After the sections are holsted into
position, they are aligned, then welded together. The alignment of the
shell 1s a critical aspect of the Installation and must be accomp! ished
with accuracy.
MOUNTING RIDING RINGS
All riding rings are not Identical, and there may be a difference between
the up-hil] and the down-hil1 side. It is necessary to check the drawings
728-75-1-8800
Sheet I of 46and the parts themselves to determine which ring mounts on a given shell
section and what Its orfentation should be,
Before assenbling a ring to Its shell section, clean the bore of the
ring and the mounting pads on the shell, then lubricate then with a heavy,
graphite-treated grease, The ring Is then supported, usual ly by avshing
threaded through the bore, and guided onto the shell. Position it between
the lines scribed on the pads. A third line Is also present, but It Is
offset for use in making measurements. in handling the rings, protect
thelr machined surfaces,
Because of variations which can occur at the Joints between sections, the
final positioning of the riding rings should not be made until after the
shell fs welded. Refer to the paragraph entitled SETTING THE RIDING RINGS.
SHELL ERECTION AND ALIGNMENT
Shell sections are usually 11fted onto the rollers by cranes, then suppor-
ted by sultable temporary structures. If erlbbing Is used, It should be
tullt carefully using only sound timbers. If A-frenes ‘are used, they must
be sturdy and rigid. Handle the shell sections ins manner which will pro~
tect them from distortion.
The shell section’ are to be positioned so that the longitudinal seams do
not form continuous lines. “When there are to seans, position each sectlon
so that ‘Its seams are about 90 degrees apart from those in the adjacent
section. when there Is only one seam, position each sectlon so that its
sean Is about 180 degrees apart from the one In the adjacent section.
Sonetines It 1s necessary to rotate the shell with a winch or, some other
source of power to secure this allgnment. If a cable is wrapped around
the shell for this purpose, keep It as close as practical to the riding
ring. Another technique 1s to sip a bar between the mounting pads under
the riding ring and loop the cable around It.
Provisions are normally made for the supporting structure to Incorporate
Jacks to adjust the position of the shell sections. Construct cradles
lihich will distribute the force from the Jacks over en area large enough
to avold distorting the shell. 0 not place a Jack In direct contact with
the shell.
With the sections supported In position as close as practical to each
other, remove the Internal bracing at the Jolnt ends. Do not disturb the
bracing at the riding rings. Because of handling and shipping, 1t may be
necessary to correct out-of-round conditions at the Joint ends to secure
proper mating for welding, A nunber of alignment fixtures are then tem-
porarily welded into position around the Inside of the shell at the joint
to draw the two edges together and align then with each other. Sone
728-75~1~8800
Sheet 12 of 46alignnent fittings are supplied, but generally the dogs, wedges, and
strongbacks must be fabricated in the field from plate suppifed for this
purpose.
A typical arrangement of fixtures at a Joint are shown in Figure 2. The
dogs and wedges are used to secure alignment; the strongbacks are then
welded in positton to retain it. Alignment fixtures renain In place until
the outstde of the Joint has been welded. Refer to the paragraph entitled
WELDING SHELL JOINTS for instructtons.
CHECKING ALI GNNENT
After all sections have been aligned through the use of the adjustment
devices, the overall alignment of the shell must be checked. The usual
procedure is to install a series of batter boards on the inside dianeter
of the shell at key locations, determine the center of the shell at these
locations, then use a transit to check the alignnent of this series of
centerpoints, Adjustments In the alfgnment of the shell sections are
then made as necessary. Several flxed lights are required in the KiTn,
along with a portable light which can be taken to any location through
out its length. Field telephones or two-way radios are Invaluable for
communication during the checking process.
CAUTION
UNEQUAL TEMPERATURES, EVEN A FEW DEGREES, WILL
CAUSE A KILN TO BOW. WHILE MAKING THE FINAL
ALIGNMENT OF THE SHELL, ADJOINING KILNS OR OTHER
SOURCES OF HEAT SHOULD BE SHUT DOWN, AND THE
WORK SHOULD BE PERFORMED ON A CLOUDY DAY OR AT
NIGHT SO THAT THE SHELL IS NOT HEATED UNEVENLY
BY THE SUN,
The internal metal bracing at riding ring locations should be renoved.
Batter boards, usually 2 x 8's, are set across the dianeter of the Kiln
728-75-1-8800
Sheot 13 of 46728-75-1-8800
Sheet 14 of 46and wedged tightly to prevent any movement. As shown in Figure 3,
boards should be located at both ends of each riding ring, near the Joint
between each section, and near the feed end. Position the boards at the
flelé Joints and feed end about 18inches to the down-hlll slide. Those
at the riding rings should be located close to the gauge blocks. The cen
ter of each board is located and a hole about two Inches In dianeter Is
bored through it at that point. A file card is then tacked over the hole
using two or three thunb tacks across the top edge and one to hold the
bottom edge in place.
At the feed end and at the field Joints, two sets of quarter points are
used to locate the center of the KIln on, the cards In the manner shown In
Figure 4.
The first set of quarter points - four points on the Inside of the shell
which are 90 degrees apart with respect to the center ~ are estabiIshed
Immediately to the downhill side of each batter board, A tranmel fitted
with a penct] and set to be about 3/4-inch longer or shorter than the in-
side radius of the Kiln is then used to swing an arc fron each of the
quarter points. These arcs will Inscribe a figure on the card which is
essentially, a square. Drawing the diagonals to this square will estab:
lish the center point of the Kiln as determined by this set of quarter
points.
Offset the second set.of quarter points 45 degrees from the first set and
use them In the sane way to determine the center point of the Kiln again.
If the two centerpoints do not colnclde, mark a point half-way between
them and Identify It as the center. Refer to Figure 4.
Only one set of quarter points 1s used at riding ring locations, and these
are established on the lower step of the gauge blocks Inside the shell.
Swing the arcs from them and draw the two diagonals to locate the center
point.
‘At the batter board on the down-hiII side of the riding ring closest to
the discharge end, drop a plunb-bob fron the center point on the card to
the shell. ark the point on the shell with @ center punch, then set
the length of the tranmel to be exactly equal to the vertical distance
from the punch mark to the center point. Remove the batter board from
this location, position a transit over the center nark, and set Its height
to equal the length of the tranmel. Refer to Figure 5. Set and level the
instrument carefully.
Remove: the thumb tack from the bottom of all cards between the transit and
the most distant riding ring, bend them upward, and secure then with the
tack so that the holes are unobstructed. Sight on the center point of the
second card at the last ring. This establishes the centerl Ine of the Kiln
against which the center point on each of the other cards is to be checked.
728-75~1~8800
Sheet 15 of 46-
FIRST SET OF QUARTER
= POINIS IDENTIFIED
BY ‘As: os “25° OFFSET
= SECOND SET OF at
GUARTER POINTS
IDENTIFIED aY "8s
- Ns,
> “CARD ON
BATTER BOARD
| an
” M he
ARCS AND DIAGONALS
FOR FIRST POINTS
‘ARE SOUID; DASHED
FOR THE SECOND SET
CENTER POINTS
7 SHELL
5
DETAILS ON CARD:
centersy |
|
oa
x cand
ae
SELECTED
CENTER |
CENTER BY |
FIRST SET
‘OF Quaerer
Ponts —
= FIGURE 4 LOCATING THE CENTER OF THE SHELL
728-75-1-8800
Sheet 17 of 46Without changing the instrunent, sight én each card In succession, in
Cluding the one at the feed end, and make a penci] mark at the precise
i S point where the line of sight through the Instrunent: Intersects It.
: Sight on the tip of a sharp pencil being maved across the card until It
is aligned with the crossed hairs. The objective of thls check 1s. to
determine the anount of misalignnent at each location so that corrections
can be nade to get the center point on each card as close to being co-
incident with the potnt established by the Instrument as It Is practical
fo achleve. Any adjustnent which can be made to inprove alignment should
- 1e made.
i At field Joints and at the feed end, the center point of each card must
be within 3/32-Inch of the point established by the Instrument. At the
riding rings the alignment Is particularly Important, and there are two
factors to consider. The offset at both locattons on each ring must be
reduced to a minimum, but they must also relate to each other in that
es any discrepancies which renain after adjustment has boen completed must
u fall within the same quadrant when viewed through the Instrument. If
one centerpoint 1s on the opposite side of elther centerline from the
other, there will be an undesirable notion in the ring sect lon when the
machine Is placed in operation.
Discrepancies at riding ring locations are corrected by adjusting the
rollers. If the frames and rollers were Installed carefully, any adjust
ment required should be minor. Misalignments at the other ldcatlons are
corrected by adjusting the Jacks used to support and position the Kiln
= sections, adjusting the alignment fixtures inside the Kiln at the joints,
or both.
If any adjustments are required, recheck the alignment of al! points
after they have been made. hen the alignnent has been satIsfactorlly
establ shed, leave the Instrument, batter boards, and alignment devices
- ( in place. Alignment Is checked after the Jolnts have been partlal ly
= welded and again after the welding has been completed.
- 7 WELDING SHELL JOINTS
When the alignment 13 satisfactory, the strongbacks are welded across the
Seams and a serles of tack welds are made on the Inside to maintain the
- alignment. The checking of alignnent, the welding of strongbacks, and the
tacking of joints should be accomplished In one night.
NOTICE
ee 00 NOT ROTATE THE SHELL TO FACILITATE WELDING DURING
‘THE ALIGNMENT AND TACK-WELDING PERIOD
- RELAY oP hefrior to welding, verify that the alignment fittings inside the Kiln are
Eights then weld elght or more I=Inch x 4einch x 20-inch strongbacks edge~
ise Across the Joints in the manner shown In Figure 2. With the stronce
backs In place, about § tack welds, each about 10 Inches long, should be
spaced around the Joint. Tacking should be done with 5/32 or 3/16-Inch
dlaneter Anertcan Welding Society (AWS) £ 6010 or 7OXX series electrodes.
After the tack welds are completed, recheck the allgnment. When It Is
satisfactory, the outside of the Joint canbe completely welded using
elther a manual or en automatic procedure. The weld must be cleaned of
Slag, loose deposits, and ail defects after each pass. In completing the
outside of the Jolnt, welding should be done In the down-hand or flat
position, preferably using AVS 7018 or 7028 series electrodes at least
W/4-inch In dianeter.
After most of the welding on the outside of the Joint is completed, the
alignment fittings, excluding the strongbacks, can be removed, The
strongbacks remain in place unt!1 all welding on the Joint 1s completed,
Prepare the inside of the joint by chipping or arc-alring Into the root
bead of the outside weld to Insure full penetration. Clear the joint of
Slag, loose deposits, and defects before starting to weld. Again, weld
In ‘the down-hand position and clean the Joint before starting each addi-
tlonal pass. The reinforcement on the butt welds shall be not less than
1/32-inch and not graater than 1/16-Inch. Best results are achieved if
the welding at each Joint is acconp! shed without interrupt ton.
After all welding has been completed, remove all of the strongbacks,
patch the scars, and grind the surfaces to be smooth and flush with’ the
shell.
Do not Weld when the surfaces of the Joint are wet, when rain or snow is
falling on then, or Ice has formed on then. If the temperature of the
base metal is lower than 32°F but higher than 50°F, an area extending 6
inches on each side of the seam should be heated to at least 60°F before
welding Is started, If the temperature of the metal is 50°F or lover,
Postpone the welding unt!! conditions Inprove.
Welding Stainless Steel
Sometimes the shells or certain other componants which must be welded are
stalnless steel. Usually, the pertinent drawings in such cases will
specify the electrode to be used. If they do not, the follouing tabula-
tlon can be used to make the proper selection, The electrodes should not
exceed 3/16-Inch diameter. Do not weave the bead or weld in excess of
the size stipulated on the drawing.
728-75~ 18800
Sheet 20 of 46JOINT METALS WELD METAL
Type 321 to Type 321 ESK7#E Or £309Cb
Type 321 to Type 304L EBN7H« or £30906
Type 304L to Type 304L E3081
Type 309 to Type 309 £309
Type 321 to Carbon Steel E310Cb*R or £310
Type 304L to Carbon Stee! E310Cb*R or £310
Type 309 to Carbon Steel £309 or £310
Type 3098 to Type 3098 309Cb
Type 3098 to Carbon Stee! E310Cb
%% Preferred electrode,
SETTING THE RIDING RINGS
After the shell joints have been completed thé tires are to be set temporary,
all except the thrust tire which Is set permanently. The riding rings are
to be temporarily located as per Fig. 6 and foundation drawing.
fillet weld
For temporary setting, weld (4) gussets 6" x 6" x 1d!" wi
on each side of the riding ring equally spaced between the pads.
When locating the tires with respect to the thrust, use a tape. Use a spring
scale to apply tension to the tape whlle the measurenent ts being made and a
thermoneter to Indicate the temperature of the tape at tine of measurenent,
correct measurement to 70°F.
The setting of the tires toa final location Is done to eliminate the error
Ta calculated expansions based on assumed temperatures. After the kiln has
operated and It has been decided how much to move each riding ring Into a
permanent position, locate and weld the retalners on the side In which the tire
Is to be moved. Weld In accordance with. the shell assenbly drawing. After
one side of the’ retalners have been welded, burn off the 6!" gussets on that
side and adjust rolls to move the tire In direction desired, After the tire
has moved, weld retainers on the other side with a 1/16" gap between tlre
and retainer with tire against the retalners on the other side.
Since the thrust ring Is permanently attached Initially, the shiamtng behind
the thrust rollers then can be adjusted to attain the specifle spacing between
them and thelr, riding ring.
MAIN GEAR AND PINION
In installing the main gear and pinion, the main gear Is sounted around the
shell, then the pinion is mounted on a base adJacent to It and posi~
728-75~1-8800-1
Sheet:21 of 6NOWV301 ONR ONTO 9 FuNOL
HONL % 7 St ONR HOW3 JO NOUY2OI aNLL NO 3ONYERTOL aH
“NIMH NOUWGNNOS 3HI NO G31IDRIS FRY GHIYDIONI SNOISNEWIO 3H
——
1
r
| Sil
Lt
ana
728-75-1-8800
Sheet 22 of 46tloned to mesh with It. Separate instructions are provided which detall
adjusting, aligning, meshing, and checking the gear and pinion instal la~
tlon. The main gear cones in two halves. The pinion shaft and tha two
bearings which support it are factory-assenbled. Sone Installations in-
clude two pinions Instead of one, but the sane techniques are used to
Install both of then.
MAIN GEAR
The maln gear is a precision component requiring careful handling and
precise Installation. At the tine of Installation, remove preservatives
and all foreign matter, then inspect the gear carefully.
The spring plates are attached to the halves of the gear while they are
stIll on the Floor, They must be asserbled to the gear in the direct ion
which will place them under tension while the KIIn is rotating during
normal operation. After the spring plates are attachod, tle than In
place, position the gear halves around the Kiln shell, and bolt them
fogethor. The halves are match-narked to identify mating surfaces. The
halves mist be dravn tightly together and closed properly before al ign-
Ing thé gear.with respect to the shell. Feeler gauges should be used to
verlfy that metal-to-netal contact has been secured, Improperly closed
Jotnts could resutt in raptd wear. Separate instructions are provided
to cover the assembly of the gear.
The gear must be located at the pofnt along the centerline speci fled by
the drawings, it must be perpendicular to the shell, and must be concen-
tric with it. They are not normally supplied as part of the Klin, but
many erectors fabricate Jacking frames of the type shown In Figure 7,
Four or ore frames are set between the shell and the gear at opposing
locations and are adjusted as necessary to position the gear.
Final centering and checking for radial and rim-face run-out must be
done with Indicators in accordance with the detailed procedures provided
seperately. When the gear is properly set, weld the spring plates to the
shell.
Start welding at the tengent point of the plates and work toward, then
across, the end. After all plates are welded, remove the jacking franes.
PINION
At Installation, it Is essential that both pinion bearings be opened, the
grease removed, and the bearings cleaned thoroughly. The grease with which
they are packed is for protection during shipment only and is not intended
728-75~1-8800
Sheet 23 of 46BWV¥d ONDIWT 2 2uNd!
Gaisino} smava Na suNM sniava EIA Wv3D=@ vans.
00 TRHS 1 OL 1n>—, | Spee
Hh aS
ub / Ge
NOt Via .z ¥Os LANGTEMA 390
NOH "via 72 Nana
SHOWASSY OL SLAM LITINA 2% DIV
ot/st-4 seazu GD
—®
a.
sae
|
|
728-75-1-8800
Sheet 24 of 46
BV WOU aaV siassno TY
NNVHD .9'91 81 S BWV
vam rind .9%.2 $1 108 WoLIOs
QvSYRL Ting “9 XK TeV SNOT IES
a9T/L |eaS an operational lubricant. A light coating of lubricant should be
applied to the bearings and to all machined surfaces. Depending on the
installation, these bearings can be elther oll or grease lubricated.
Mount the pre-assembled pinion assembly to the base with the fixed bear-
ing at the location specified on-the drawing. Set the shaft to the sane
slope as the Kiln, Shim es required, but shim over the: entire contact
area - not intermittently. Refer to the separate instructions provided
for details in securing proper allgnent, tooth contact, and the final
positioning of the pinlon assenbly with respect to the gear.
GEAR GUARD
Once the main gear and pinion are In thelr final positions, the gear
guard which encloses both of them can be installed. Before enclosing
them, however, .gIve the gear and pInton teeth a thin coating of gear
lubricant to prevent dry contact before the lubrication system has the
‘opportunity to cover them.
The part of the seal which gets welded to the shell must be positioned
first. The guard Is tn sections which heve been match-narked at the
factory to sinplify the assenbly procedure. Shins are placed under the
support legs of the guard to gain the proper concentricity of the mating
sections of the seal.
GEAR AND PINION LUBRICATION SYSTEM
The girth gear and pinion are lubricated either by a spray system or by
oi] Idlers, The Installation and adjustment of the gear spray system Is
to be accomplished in accordance with the manufacturer's instructions.
The spray panel is to be mounted on the gear guard in the manner shown
on the drawings. The other components of the system are located for con~
venlence at the site.
Wnen of} idlers are used, they are mounted on a bearing-supported shaft
In the gear guard under either the pinion or the gear. The bottom of the
gear guerd then serves as the ol! sump. A nunber of idler gears are pro~
vided. Place the first one near the end of the gear with which It meshes
s0 that ofl will run along the teeth during normal rotation, then locate
the others at about 10-inch intervals unless the drawings specify a diff
erent spacing. The Idlers are secured in place with set screws. Once
they are positioned, no further adjustment or alignnent 1s needed. In~
stall the of] fI11 standpipe to the gear guard,
728-75-1-8800
Sheet 25 of 46DRIVE UNITS
Uartous combinations of notors, speed reducers, couplings, and auxiliary
units are used to drive different Kilns. The manufacturer's Instructions
which are to be used in installing: each of the units provided will be
ube ited separately. The various units Included are identified on the
rawings
{n most installations, each unit has its own base which must be independ
ently set, aligned, end grouted, The entire drive train should be aligned
and bolted tenporarily unti{ final adjustments have been made on the gear
and pinton. At that polat, each base Is rechecked and adjusted as neces
sary to comply with final elfgnment tolerances. Anchor bolt sleeves may
then be filled with grout, The frames should be grouted on the following
day.
Occasionally, al! drive units are mounted on a common adjustable base
which, in turn, {s mounted on @ sub-base. This sub-base must be accur-
ately positioned, grouted, and have all anchor bolts sledged tight before
the base can be mounted to It, The base can be moved In or out to adjust
for backlash between the gear and pinion, but It can be moved only a small
anoint to improve tooth contact, so particular eare must be exercised in
setting the sub-base and base. ‘It Is Inportant that sub-base elevation
allows for additive shinning at drive components which are instal ted on
the main base.
ELECTRICAL INSTALLATION
The Installation of power, control, and Instrumentation devices and cir=
cultry are covered in separate Instructions which Include appropriate
Interconnection inforsation, instructions, and schematics. In many cases,
however, the detalled electrical Installation - conduit layouts, switch
locations, wire sizes, etc. - has not been designed, and the associated
safety switches, electrical wires, condult, and wiring devices are not
supplied, Select and install electrical devices and materials which are
compatible with the characteristics and ratings of the electrical equip~
nent which Is provided as part of the system. Electrical specifications -
voltage, frequency, phase, and current or power requirements - for the
equipment supplied are included on the drawings or in the literature fur-
nished. Follow the Instructions of the manufacturers for wiring all
728-75-1-8800
Sheet 26 of 46electrical devices provided. Make certaln that the speci fled rated vol
tage will be applied at the ternlnals of each plece of equipment under
al] operating conditions.
Design the electrical installation to conform to the requirements of the
National Electric Code and any applicable state and local codes. Pay
particular attention to the safety requirements and protective features
of all devices used.
Sone Installations include Instrumentation which Is mounted through the
side of the shell. In such cases, trolley wires which encircle the
shell and stand-off Insulators to support them are suppiled to pick-up
signals from the sensors. Pantographs and their supporting base are
supplied to transfer the signals from the rotating trolley wires to ex-
ternal circuitry. Drawings are provided with the Kiln which show the
Installation of the trolley wires, Insulators, pantographs, and base.
information on the sensors, instrumentation, and Interconnect ing circuitry
Js provided In separate electrical system Instructions
It is Important to braze and grind Joints in the trolley wires carefully
so that the transfer of signals is as effective as practical.
FIRE HOOD
The fire hood Is not put on until after the shell has been assembled and
aligned
There are many different kinds of fire hoods, but they are relatively
simple enclosures to erect and assenble In accordance with the drawings
provided. All fire hoods are refractory-lined. Most types are not
bolted down and many are equipped with wheels. Particular care must be
taken in assembling the seal between the fire hood and the shell.
FEED HOOD
The type and conf guration of the hood on the feed-end also varies a
great deal and depends upon the equipment which will be located at
728-75- t-8800
Sheet 27 of 46fat end to feed material Into the Kiln and to handle the hot gases
leaving it. °
While installation must be performed tn accordance with the drawings
Provided for the specific hood supplied, refer also to the Instruce
tlons for the interfacing equipment. They may include information
which will clarify the installation of the hood itself,
Special attention will be required in Installing the seal between the
hood and the Kiin shell. The type used varies according to the appl i=
cation. Some feed-end hoods require: a refractory lining.
NOSE RING
On the larger machines equipped with a nose ring for cooling, the cowl
and support sections must be welded on-site. On smaller machines, these
parts are assenbled to the shell section at the factory. In both cases,
the segments which close the area between the cowl and the end of the
shell are bolted into position on-site. All necessary holes and bolts
are provided,
If the cowl is welded on-site and 2 carbon seal is to be installed be-
tween the nose ring and the fire hood, It will be necessary to grind
the welds In the area where the seal plates will be in contact with the
cowl.
The fan is installed at a convenient location which will Init the
length of ducting, Refer to the fan manufacturer's Instructions for In-
Formation on providing a foundation for and installing the fan and its
drive. The ducts are to be supported Independently so that their wel ght
Is not carried by the fan housing.
BURNER
The burner and the equipment associated with it Is Installed in accord=
ance with its manufacturer's Instruct ions.
728-75~1-8800
Sheet 26 of KéREFRACTORY LINING
In most installations, the refractory lining required in the Kiln is
rot Included with the equipment provided. Separate arrangements are
usually made with other sources for procuring appropriate refractory
material and having it installed, Brick-retalning rings which are to
be welded inside the shell as the refractory is installed are provided.
One ring should be Installed 18 to 2h inches from the discharge end.
The Fost are usually equally spaced throughout the length of the Kiln.
Consult the refractory supplier for his preferences on the number and
location of rings with respect to the refractory being installed.
Usually, refractory Is Installed along the length of ‘the Kiln to a
ring location. The ring, which is In 4 or 6 segments, Is held tightly
against the brick while it is welded to the shell, Installation of
refractory then resunes. Welding the rings In position while the re~
fractory-is being Installed avoids the necessity of cutting refractory
to fit between previcusly Installed rings.
While the refractory is being installed, the Kiln Is rotated as neces
Sary to permit the work to be performed in the most advantageous posi~
tlon.
CHECK-OUT
Because the Kiln will be placed In limited operation to dry the refrac
tory lining, a thorough check of the instatlation should be made to verify
that it Is ready to be started and operated, This inspection should in
¢lude the following points:
All temporary forms and supports used during Installation of the
refractory have been rerpved.
Both the interior and the surrounding area have been cleaned;
they are free of all foreign matter and refuse - particularly
combustibles.
Components of the Kiln requiring It - riding rings, thrust
rotlers, bearings, reducers, motors, couplings, fans, etc. ~
have been properly lubricated, Lubrication systems are
operable.
728-75-1-8800
Sheet’ 29 of 46Controls and Instruments are ready for operation.
The rotation of al! motors Is In the required direction.
After the Inspection has been completed, the Kiln is rotated and its con
ponents checked to make certain they operate satisfactorily. The main
Gcive lg started at its lowest speed and the following condi tfons ave
veri fled:
The girth gear and pinton, bearings, and similar devices are
being lubricated,
* Cooling water Is flowing through the bearing on the support
rollers.
All rollers are in contact with the riding rings.
Drive units are properly adjusted,
The seals are making proper contact.
The speed is then increased [n steps up to the maximum, and all compon=
ents are observed for proper operation at each step. The Klin 1s stopped
after the check has been completed.
DRYING REFRACTORY
The refractory lining must be thoroughly dried before the Kiln Is placed
In service, During this process the burner Is started and run on slow
fire and the Kiln is rotated slowly, Drying normally takes about 48
hours, but instructtons will be avai lable from the manufacturer for the
refractory used on the Installation.
Initially, rotate the KIIn approximately one-half revolution every half
hour. As drying progresses and a little sore heat Is used, change the
rotation to be about one-third turn every 20 mfputes, then’ one-quarter
turn every 15 minutes. As the tenperature is Increased, the Kiln should
be run continuously at its lowest speed, The objectives are to heat
evenly, to dry the refractory uniformly, and to avold heating one side of
the Klln excessively so that a danger of warping exists.
728-75-1-8800
Sheet 30 of 46POST-INSTALLATION IDLE TIME
If the Kiln will be idle after installation has been completed, it should
be rotated for about 15 minutes each week to circulate ol! through bear
Ings, speed reducers, and simi lar components.
OPERATING INSTRUCTIONS
The satisfactory operation of a Kiin Is primarily dependent upon the ex-
perience and capability of the operator, {t requires a thorough know~
ledge of the process, of the material being processed, and of the equlpnent
itself. It also requlres skill at accurately Interpreting the state of the
material and influences of the many variable, Interacting conditions which
exist during operation and in achieving precise responses from the equip-
ment when adjustments are necessary.
The less sophisticated installations depend heavily on the operator exer~
cising direct manual control. As the complexity of the installation In
Greases and wore operations becone autonated, the emphasis Is shifted to
the operator establishing the control points to which the circuitry must
Fespond, monitoring the operation of the system, and being prepared to
Intervene in the event of @ malfunction,
The capabl lities offered end functions performed by the Instrumentation
and control system are covered in separate Instructions prepared for each
installation. The paragraphs which follow present general Instructions
and procedures concerned with the mechanical operation of the Kiln.
SAFETY
Because of the high temperatures, both Internal and external, the entire
Kiln must be treated as a dangerous area, Skin temperatures generally
range from a tou of about 300°F up to about 600°F,
1728-75-1-8800
Sheet 31 of 46WARNING
SAFETY PROCEDURES MUST BE OBSERVED AT ALL TIMES
Personnel working on the plers or other Jocatlons where they can cone
into contact with the shell must be safety conscious to avold Inadver-
nt contact.
Care must be taken in opening Inspection ports In the fire hood. Be~
cause the Kiln Is under suction, hot gases should not escape from an
open port when the KiIn Is operating under normal condi tions. There
should be an Inward flow of alr. However, hat dust from any kind of
puffing in the fire hood can be blown In the operator's face. Pro
tection for the face and eyes must be worn at these tines.
STOPPING
The primary concern In stopping the Kiln Is protecting the refractory
from the effects of sudden temperature changes,
Rotation of the Kiln Is continued at progressively lower speeds as the
temperature drops. When low temperatures are reached, the rotation can
be reduced to a fraction of a turn each hour, It should be stopped com
pletely only when the danger of creating local hot spots and warping of
the shetl no longer exist.
ENERGENCY SHUT-DOHN
The shut-down action to be taken In an emergency situation Is-dependent
upon the nature of the emergency and its anticipated duration and can be
determined only at the tine and on the basis of an evaluation of the
situatton by experlenced personnel.
728-75~1-6800
Sheet 32 of 46Host such situations arise because of a malfunction in another plece of
equipment in the system, and matertal cannot be processed through the kiln
until a repalr ts effected, in many Instances, a complete shutdown Is not
required. In all cases the priority of consideration must be first to the
safety of personnel, then to the protection of equipment, and Finally to the
Product or materfal In process. In considering equipment, the kiln is glven
a high priority because of the time and expense required to effect repairs
as well as its original cost.
POWER FAILURE
In the event of @ power fallure, It Is vital to the shell that the aux-
Mary drive be started Inuediately so that rotation can continue. Refer
to the separate Instructions provided for the auxillery drive to become
familiar with the starting sequence and control procedures. fallure to
keep a hot shell rotating results In dasage to the refractory and warping
of the shell. Any warping is sertous, but It can becone 50 severe that
corrective measures becone both difficult and expensive.
Most power failures occur during storms when there Is rain, wind, snow,
or various combinations of these elements, each of which has a signifI~
cant cooling effect on the shell. In addition to causing a rapid heat
transfer fron the lining, thts cooling of the shell tends to cause it to
contract and exert a compressive force on the refractory, causing it to
crack and loosen.
Should a situation arise where neither primary power nor the aux! lary
drive is avallable to rotate a hot shell, an improvised means of rotation
must be devised. A tractor to pull a cable wrapped around the shell or
hydraul 1c Jacks pushing agalnst bars placed between the pads under the
riding rings could be used, A warped shel! wilt alter proper gear and
Pinion mesh and could result In gearing fallure.
‘THE AUKILIARY DRIVE
Aside from emergency use to rotate the kIIn during a power fallure, some
operators use the auxillary drive to rotate the kiln slowly or Intermit~
tently during the early stages of heatIng or the later stages of cool ing.
If this procedure is followed, it Is inportant to make certain that the
lubrication system for the main gear remains in operation when the other
poner untts are stopped. The auxiliary drive Is an energency system only
and should not be used for continuous operation.
728-75-1-8800-1
Sheet 33 of 46WARNING
DO NOT USE THE MAIN DRIVE AND
THE AUXILIARY DRIVE TOGETHER
Attempting to use both drives to start a Kiln can exert much more torque
than the drive components can withstand. Personal injury and serious
danage to the installation can result.
SKEWING ROLLERS
Rollers are skewed on floating KiIns only. They remain parallel to the
centerline on full thrust Kilns and those equipped with a hydraulic thrust
mechanism. The purpose of skewing Is to cause the shell to operate In 3
position where It, is floating between the thrust rollers rather than rest-
ing agalnst either of them. By setting the rollers at slight angles to
the shell they exert a thrust on it which is adjusted to counteract Its
tendency to move down-hill. Figure 8 shows the direction that rollers are
to ba skewed for both directions of rotation.
At the time of installation, all rollers were set with their centerlines
parallel to the centerline of the Kiln so that when the KiIn {s first
Placed In operation, no roller wilt be exerting a thrust in either the up-
AEM or down-hil! direction, While the rollers are in this neutral posi-
tion, the adjusting bolts should be marked so that the amount each one Is
subsequently turned to skew a roller can be seen. It 1s necessary to skew
all rollers slightly and in the same amount so that although each roller
Is at an angle to the Kiln, each set of rollers Is parallel with the other
sets of rollers.
NOTICE
ONE PERSON SHOULD MAKE ALL ADJUSTHENTS
TO ALL ROLLERS ON THE KILN.
Adjustments are made In small Increments, ali réllers must be adjusted the
728-75-1-8800
Sheet 34 of 46ana cag ona oaas
——_{—__, —_—
orive
FIGURE 8 SKEWING ROLLERS
LOWER THRUST ROLLER
728-75-1-8800
Sheet 35 of 4¢
ONS 39KVHOSIC Na 39WVHOSIaSame amount, and they must share the load equally. In addition, one per-
Son becomes familiar with the Kiln and knows the change an adjustment wi 11
effect. For these reasons, one ind! vidual should be assigned to make all
roller checks and adjustments on the Kiln, He should maintain records of
adjustments and alignment checks to ald in future adjustments and alignment
corrections.
Skewing and making adjustments to the skew are performed while the KiIn Is
In operation and at its normal operating tenperature. Hoving the rollers
Inward with the Kiln stopped would be extremely difficult mechanically.
Also, the adjustment should be made after the KIIn has completed its ther=
mal expansion.
WARNING
BECAUSE ROLLERS ARE ADJUSTED WHILE THE MECHANISM
18 IN MOTION, PERSONNEL NUST EXERCISE CAUTION
TO AVOID INJURY
Although the parts are rotating at relatively low speeds, danger does ex-
Ist. Personnel must exercise particular caution In keeping'-thenselves
and their clothing well clear of the moving parts. In addition, the exter-
for surface of the shell will be hot enough to cause burns. If the guards
are renoved to make the adjustment, make certaln they are re-installed pro~
perly afterward.
Rollers are skewed through the use of the adjusting screws mounted in the
support Frame and pressing aginst the base of each bearing. Turning @
sérew moves the assoclated bearing, and the angle at which the rol ler
addresses the riding ring is changed a corresponding enount. On Kilns equip~
ped.with the larger sizes of rollers, hydraulic cylinders operated by a hand
ung are mounted on the frame to move the bearing. The screw Is then used
to retain the bearing in its new position. The hiold-down bolts on anti-
Friction bearings must be loosened while their roller 1s being skewed.
When It Is desired to move the KIIn up-hill, the bearing on the up-hill side
of the roller on the upward-turning side of the Kiln is moved toward the
riding ring as Illustrated In Figure 8. The down-hiTl bearing on the down-
ward-turning side of the Kiln would then be moved toward the ring the sane
azount. Moving the other pair of bearings would result in the Kiln moving
down-hill, but this is rarely desirable, A small amount of up-hill thrust
is usually needed,
728-75~1-8800
Sheet 36 of 46The direction e roller ts thrusting can be determined quickly by striking
the end plates of the bearings with a small hamer, When a roller Is
skewed to hold the Kiln up-hill, the bearing plate on the doun-hill bear-
Ing wil] have-a solld sound when it is struck, and the up-hil! bearing wil]
Sound Hollow. The opposite Is also true. If the roller Is set to move the
Kiln down-hill, the up-hill bearing will have @ solid sound and the one
down-ht}] WITT’ sound hol low.
Adjustments are made in snall Increments which are rarely larger than one-
Sixteenth of a turn of the screw. They should be made to all rollers in
the sane anount so that the thrust Is divided equally between all piers and
between both rollers on each pler. One roller is never set to thrust In
the opposite direction from its mate, nor is any pair set to thrust In the
opposite direction from the others.
When the rollers are first skewed from the neutral position, a period of at
least 6 to 8 hours should elapse before the riding ring contacts the upper
thrust roller. If the shell moves uphill In less tine, the rollers have
been skewed too-much and must be adjusted to avoid unnecessary wear. Depend-
Ing on the’ size and speed of the KIIn, a pertod of from 2 to 8 hours may be
required for the Kiln to adjust itself to a change made in the skew angle.
Once the skew of the rollers has been set and the load balanced anong them,
additional adjustment should not be required for 9 long time. Some move~
ment of the Kiln may occur from time to time, but the change should be ob=
served for @ while to see If the condition corrects Itself, if the change
is too small to warrant an adjustment, or if an adjustment Is desirable.
COLD WEATHER OPERATION
For Kilns located In areas subject to freezing weather, precautions must be
taken to prevent cooling water from freezing In the bearings or piping.
During shut-down periods, drain the water fron the bearings.
MAINTENANCE
Maintenance of many components of the Kiln, such as anti-Friction bearings,
728-75-1-8800
Sheet 37 of 46drive units, and the gear spray system, Is to be performed In accordance
with the instructions of their Individual manufacturers. In those Ine
stances, the Information available from the manufacturers 1s provided
Separately. The Instructions contalned in this section pertain to con
Ponents not otherwise covered or are supplenental to the separate mater~
jal
CHECKLISTS AND RECORDS
Check! ists should be prepared which fnclude a routine for examining, Jub
ricating, adjusting, and otherwise servicing the various elements of the
Installation so that nothing is Inadvertently overlooked,
Complete and continuous records should be maintained for the repair and
replacement of the refractory IIning. The record should Indicate the
date, make, and exact location of refractory material installed. This
record can assist in deternining when to replace sections of the lining
and to identify the type of material which has proven to be the most de-
sirable for the application.
Records should also be kept of shel! alignment measurements, roller adjust
ments ,-ané gear chacks,
The burner daily report should Include the current or power being drawn by
the Kiln motor. An Increase In power consumption may Indicate misalign-
ment of the rollers.
LUBRICATION
Table | is a lubrication schedule which Identifies the types of lubsicants
to be used with the bearings and gears on the Kiln.
The 11 In all bearings on the Kiln = support, thrust, and pinion = should
be changed after the first month of operation, then every 6 ronths unless
the anount of contamination to which it is subjected requires that it be
changed more frequently. The same applies when oil idlers are used to
lubricate the girth gear and pinion. Although the gear spray system does
not retain or re-use its lubricant, it does produce a sludge which accum~
lates in the bottom of the gear guard. Periodically, the door near the
728-75-1-8800
Sheet 38 of 46TABLE [
KILN, COOLER, AND DRYER
LUBRICATION’ SCHEDULE
cone:
110 - Engine O11
120 - Turbine or Circulating O11
220° ~ Extreme Pressure O1T (Lead-Naphthenate)
235 - Gear Lubricant (Residual Compound ~ With Di lutent)
370 - High Tenperature E,P, Grease
Tex cove SPECIFICATIONS APPROX.
No. SAE, NO,
Roller Support Bearings:
(1) O11 lubricated + 120 1650 $.5.U,/100°F,
(2) Grease lubricated > 370 NUGE #2
(3) Anti-friction ofl type 120 800 $.$.U./100°F
Thrust Roller Bearings:
(1) Sleeve, ol! lubricated = 120 1650 $.8.U./1009F. 50
(2) Anti-friction, olf type - 120 1850 S.S.U./1009F. 60
Pinion Shaft Bearings:
(1) anti-friction, grease type - 370 NLGI #2 ~
(2) anti-Friction, of] type - 120 800 $.5.U./100°F, 40
(3) Sleeve, grease type = 370 NLGL #2 =
(4) Sleeve, of type = 120 1850 $.S.u./100°F, 60
Girth Gear and Pinion: (- 235 3000/8000 s.3.U./210°F,
(1) Intermittent spray system (+ 220* 500/800 S.S.U,/2100F.
(2) Oil Ing Idler = 220 400/500 $.S.U./210°F.
Speed reducer)
coup! ings) ~ See Manufacturer's Instructions
Gasoline Engine)
Extreme pressure lubricants are not necessary in Kiln sleeve bearings.
If the user prefers £.P. lubricants they should be chosen to be stable at
temperatures over 200°F, Some of the more recently prepared lubricants do
have this stabl lity.
#Preferred
728-75~1~8800
Sheet 39 of 46bottom of the guard should be opened and a hoe-type tool used to scrape
the sludge out.
A graph ted grease of the sams type used at Installation should be used
to lubricate between the riding rings and thelr mounting pads. A hand
gun with an extended nozzle can be used.
‘The faces of the riding rings and rollers are lubricated only by the
solid graphite plate mounted on one of the rollers in each support mech”
anism.
The graphite, held against the roller by Its own weight, provides ade-
quate lubrication, 00 not use ofl, water, or other lubricants. The face
OF each thrust roller and the side faces of Its riding ring are also lub-
ricated by a graphite plate held against the thrust roller, No other
type of lubricant should be used on these surfaces.
If the bearings on the support rollers are of the sleeve type, the caps
should be opened periodically while the Kiln is in operation to Inspect
the Interior and to deternine if the bearing is being lubricated ade-
quately. Keep the of1-f111 pipes on both the support and thrust bearings
clean. Under some conditions, dirt can accumulate In these pipes and, if
not cleaned out, can give a false indication of the of! level. Inadequate
lubrication leading to bearing fallure can result. Check the of! level
regularly, adding of! as necessary.
‘The contact Faces of labyrinth and rubbing-type alr seals should be lub-
ricated with a graphited ol! mixture. Seals which are effected through
the use of graphite blocks will require perfodic replacement of the blocks
but no lubrication.
KILN ALIGNMENT
Kiln alignment should be checked periodically and corrected as necessary
to avoid excessive wear on rings, rollers, gears, bearings, and seals
and to restrict cracking of the lining, The preferred method of check~
ing allgnment Is performed inside the Kiin along the centerline. The pro-
cedure Is much the same as that used during Installation except that
checks are made only at ring locations, Refer to the paragraph In the
INSTALLATION Section enti tTed CHECKING ALIGNHENT. There are instances
where this technique canrot be employed and It is necessary to check the
alignment from measurements made on the outside, Outside alignment is
quicker, but not as accurate. A procedure which can be used Is available
from the factory.
728-75-1-8800
Sheet 40 of 46Sench marks established while the Kiln was belng’ Installed should be used
to check the piers for shifting or settling which could cause misalign-
ment.
AUXILIARY DRIVE UNIT
The components of the auxlIlary drive mst be checked regularly to maln~
taln them in a condition where they wlll start inediately when needed.
Most are engine driven, and the engine should be started and run dally.
The oil level and fuel level should be kept at the full mark. Haintaln
2 full charge on the starting battery, keep the terminals clean and tight,
and add water as necessary to keep the cells full. The discharge-charse
cycie'of starting and running the unit regularly is advantageous to good
battery life. Refer to the manufacturer's instructions for these units.
REFRACTORY
The refractory lining should be inspected whenever an opportunity arises
and: any damage repaired. Unusual operating conditions sometimes cause
the refractory to crack and to break loose from the interior while the
Kiln Is in operation, resulting In hot spots on the shell which can glow
and warp. In such cases it Is necessary to shut down as quickly as pos-
sible to repatr the IIning and patch the distorted shell.
Whenever the Kiln Is relIned or repairs are made to the lining, time must
be allowed to permit thorough drying before the Kiln is returned to ser~
vice. Refer to the paragraph entitled DRYING REFRACTORY in the INSTALLA-
TION Sectlon.
MAIN GEAR AND PINION
The main gear and pinion should be Inspected periodical ly to ascertain
that they are receiving adequate lubrication and that good contact end
proper clearance exists between them, An annual check of backlash con~
ditions should be made and the results recorded, Refer to the gear in~
stallation and alignment Instructions provided separstely. Wear on the
riding rings and support rollers will change the mesh of the gears. Even-
72-75-1880
Sheet 41 of 46tually, adjustments In the location of the support rollers may be neces~
sary to maintain proper clearance.
The roller-to-race clearance on the pinion shaft bearings should also be
easured once each year. An appreciable increase in the clearance will
Indicate the necessity for changing these bearings. 8 sure to record
the measurements for future reference.
SUPPORT-ROLLER BEARINGS
Periodically, roller end-play should be checked to determine the amount
the thrust washer has worn, Heasure and record the change’ in. end-play
from when the thrust washer was new. Replace It when the measurement in-
dicates that the oll grooves are worn away. Refer to the paragraph en~
titled INSTALLING BEARINGS AND ROLLERS,
If sleeve bearings are used, check for excessive wear of the bronze half-
sleeve. Replace as necessary, Wear of the coverplate on the roller side
of the bearing would Indicate excessive wear of the sleeve, The seal on
the roller side will also wear and should be replaced when it begins to
leak.
To replace a sleeve, take the load of the Klin off of the roller by sup-
porting the shell in a cradle watch can be Jacked up the amount necessary
to unload the roller. Support the roller tn a sinflar manner. Remove
the end cover fron the bearing, unbolt the sleeve, and slide it out the
end. Lubricate the new sleeve so that there can be no Initial dry con-
tact, slide It Into position, and bolt it,
Regardiess of the type of bearing, this sane technique of supporting the
shell and roller is used If an entire bearing aust be renoved and replaced.
On Kilns equipped with anti-Friction bearings, measure the roller-to-race
clearance once each year. An appreciable Increase In the clearance will
Indicate the necessity for changing these bearings. Be sure to record the
measurements for future reference.
THRUST-ROLLER SLEEVE BEARINGS
Wear of the sleeve bearing on a thrust roller and the thrust
1728-75-1-8800
Sheet 42 of 46the roller should be checked pertodically.’ Wedr of the bearing can be de-
termined by measuring the amount of lateral-movement of the roller, The
amount. of thrust ring wear will be evident From successive neasurenents
made from the frane to the. top of the thrust roller.
The bearing sleeve Is press-fit Into the bracket with only enough inter
ference to hold it in place. One screw through the side of the bracket
and Into @ hole in the wall of the bearing prevents rotation. To replace
the sleeve, remove the bracket fron the frame, lift the roller from it,
remove the screw, then draw or press the old sleeve out. In pressing ‘the
new sleeve in, allgn-it with respect to the screw'In the side.
Once the roller has been removed, the thrust cing can be removed and
replaced without disassembling any other parts.
ERRATIC KILN ROTATION
Properly Installed, operated, and maintained Kilns rotate smoothly and
steadily. Erratic rotation - bumping, jerking, or bouncing ~ can be
caused by a number of conditions, The: following paragraphs discuss causes
of irregular motion.
WARPED KILN SHELL
Warping unbalances the weight distribution of the Kiln such that the con~
vex zone is heavier. As this zone moves upward, rotation can stop momen-
tartly es each pinion tooth moves away from the meshing girth gear tooth
causing the next pinion tooth to bump against the next girth. gear tooth.
Warpage can also cause the shell to rub Inside the fire hood, feed end
housing, or at any point where rigid structures are set close to the shell.
This added pressure can Increase the gear bunp mentioned above, overload
the drive motor to cause speed fluctuations, and force the shell to flex
with each bump of the gear. In combination, these conditfons can cause
the shell to bounce with enough force to be seen and felt,
SEAL RING PRESSURE
Air seals may bind or choke. When this happens, a chattering form of
vibration can be started which will be transmitted throughout the Kiln,
728-75~1-8800
Sheet 43 of 46The condition will be aggravated If it begins before the Klin has ex-
panded fully, Continuing expansion will place severe pressuré on the
rubbing surfaces.
IMPROPER LUBRICANT VISCOSITY
When the lubricant is not of the proper wal ght or classification or is
dirty and sludge-filled, it can cause drag which will overload the motor
and, in severe cases, damage-the roller shaft.
WORN THRUST WASHERS OR BEARING LINERS
After these parts have worn to the polnt that the effectlveness of the
O11 grooves has been serlously diminished, the resulting Inadequate lub-
rication can cause a chatter or vibration and an overload condition for
the drive.
INADEQUATE COOLING
‘An inadequate flow of water to the bearings or blocked water passages
within the Jackets or piping can result in over-heating, affect the tubri~
cation, and cause the shaft and bearing to seize and result in drag and
chatter.
EXCESSIVE BACKLASH
Excessive backlash will cause the Kiln to jerk as It rotates.
GEARS MESHING TOO DEEPLY
Improper gear alignment or KIIn alignment may place the gears too deeply
in mesh causing the teeth to bottom and resulting in a sever bunp as each
tooth passes. With a warped shell, the mesh can alternate between belng
too deep and too shallow on each révolution,
WORN RIDING RING PADS
Full-Floating rings require small amounts of clearance which pe!
them
728-75~1~8800
Sheet 44 of 46to slip. Eventually, this space may becone excessive, the center Ine
Wi} Toner, and the girth gear will mesh too deeply with the pinion.
IMPROPER ROLLER ALIGNMENT
Aside from encouraging rapid wear, Improper roller alignment can result
in several forms’ of irregular movement including flexing of the shell and
too deep gear meshing accompanied by reactions which range from light
vibration to severe bumping. If, in a floating Kiln, .the rollers..are
not properly skewed, excessive pressure on either thrust roller can cause
a chatter-type vibration. Minor shifting, settling, or tilting of the
plers will appear as Improper roller alignment.
UNDERSIZE DRIVE MOTOR
At times and under certain conditions, the Kiln Is operable under feed and
load conditions greater than those of ‘the original design. If a propor-
tlonatly larger notor and drive Is not installed, the small motor will, at
least, tend to have a Fluctuating speed which Is’ transmitted to the Kitn
as erratic rotation.
LOOSE FITTINGS AND UNITS
Loose fittings or components can result in 2 vartety of vibrations and
erratic motions.
UNUSUAL MATERIAL CONDITIONS
Certain materials will shift in an erratic manner rather than sliding or
tumbling In the usual way. Such motion will affect Kiln rotation, At
tlmes, material accumulates to form slabs on the refractory lining and
have the same results as a warped shell,
LoW VOLTAGE
Low voltage at the drive motor can cause the speed to fluctuate and result
in erratic rotation.
IMPROPERLY POSITIONED THRUST ROLLERS
Thrust rollers are set 1/16- to 1/8-inch off the centerline of the Kiln
toward the invard-running side of the Kiln to permit the riding ring to
contact the roller rim on the down-sweep and keep the thrust roller seated
728-75*1-8800
Sheet 45 of 46in its housing, If the thrust roller Is set to the up-sweep side It
can be IIfted to rub against the ring retaining band and, In combination
with the up-sweep pressure, cause vibration.
SPARE & REPLACEMENT PARTS
Parts lsts and l!sts of recommehded spare parts are provided separately.
In ordering parts from the factory, be certain to specify the quantity,
description, and part nunber for each one, include the serial nusber of
the machine'on ail orders and related correspondence.
728+75- 18800
Sheet 46 of 46