12. Joe has now been released from his government job.

Based on his excellent performance, he


was able to land a job as a production scheduler in a brand-new custom refinishing auto
service shop located near the border. Technique have improved in the several years he was
out of circulation, so processing times are considerably faster. This system is capable of
handling 10 cars per day. The sequence now is customizing first, followed by painting.
Answer :

So, the optimal sequence is 10, 6, 2, 4, 1, 7, 3, 5, 9, 8


13. The Following table contains information regarding jobs that are to be scheduled through one
machine :
Job
A
B
C
D
E
F
G
a.
b.
c.
d.
e.

Processing time
(days)
4
12
2
11
10
3
6

Due
date
20
30
15
16
18
5
9

What is the first-come, first served (FCFS) Schedule?


What is the the shortest operating time (SOT) Schedule?
What is the the slack time remaining (STR) Schedule?
What is the earliest due date (DDate) Schedule?
What is the mean flow times for each of the schedules above?

A. First-come, First-Served (FCFS) schedule A-B-C-D-E-F-G

a. Waktu penyelesaian rata-rata :


= Jumlah aliran waktu total/jumlah pekerjaan
= 196 / 7 = 28 hari
b. Utilitas = Jumlah waktu proses total/ Jumlah aliran waktu total
= 48 / 196 = 24,29%
c. Jumlah Pekerjaan rata-rata dalam sistem
= Jumlah Aliran waktu total / waktu proses pekerjaan total
= 196/48 = 4,08 pekerjaan
d. Keterlambatan pekerjaan rata-rata
= Jumlah hari keterlambatan / Jumlah pekerjaan
= 113 / 7 = 16,14 hari
B. the shortest operating time (SOT) Schedule C-F-A-G-E-D-B

a. Waktu penyelesaian rata-rata :


= Jumlah aliran waktu total/jumlah pekerjaan
= 140/ 7 = 20 hari
b. Utilitas = Jumlah waktu proses total/ Jumlah aliran waktu total
= 48 / 140 = 34,28%
c. Jumlah Pekerjaan rata-rata dalam sistem
= Jumlah Aliran waktu total / waktu proses pekerjaan total
= 140/48 = 2,92 pekerjaan

d. Keterlambatan pekerjaan rata-rata


= Jumlah hari keterlambatan / Jumlah pekerjaan
= 51 / 7 = 7,28 hari