Professional Documents
Culture Documents
1)
1. Who should have access to the WPQRS?
2. How do we determine what the correct weld preparation (root face, root gap, Included Angle) should be?
3. How are the lengths of tack weld during assembly and fit-up determined?
8. Who has the responsible of ensuring the welder is using the correct polarity during welding?
a] the welder and welding supervisor b] store man and the welder
c] welding engineers d] the Q/A department
9. When would you measure the minimum preheat temperature?
10. During root welding which of the following would be the main cause of excess penetration?
a] the root gap is too small according with WPS b] preheat not sued
c] the current is too high d] root face is too large
11. The welders have increase the voltage on the SAW welding set, what would be the effect on the weld
appearance?
12. What is the maximum OCV allowable to initiate and arc when using A.C. current?
a] 1000 V b] 10 V c] 90 V d] 900 V
15. Why would visual inspection of the excess weld metal at the bottom of a cross country pipe line be
important?
a] it is the most difficult aria to weld b] it is dirtiest part of the pipe as it is near the ground
c] Welders always forget to weld the bottom d] it is the most difficult area to radiograph
16. why is it essential to clan the excess weld metal on completion of the production weld?
17. To assess the surface of a weld for direct inspection, the distance from the surface to the eye should be?
a] 200mm b] 600mm c] 60mm d] 6000mm
18. What is the recommended minimum range of illumination required by BS EN 970 for inspection of a
surface weld?
19. Who should select the specific welds for NDT, to cover the 10% contractual percentage required by the
specification / code?
20. In transverse weld tensile test , if the break was in the weld metal, the sample would be?
A] Rejected
B] Acceptable If the UTS is equal to or greater than the specified UTS of the plate
C] Retested
D] Acceptable if the UTS is between 80-90% of the specified UTS of the plate
21 In welder qualification testing of 45mm why are side bends used instead of root and face bends?
23 When examining a completed bend test , the angle of the bend was found to be 185. The testing
Calls for the sample to been formed through 180.
24 In a cross joint tensile test the following observation were made: Specification width: 20mm, material
Thickness: 20 mm, Max Load: 180kn, break position Parent plate. What is the UTS?
26 A butt weld has been made by MMA in a 50mm thick impact tested steel plate. The welding electrode
Used was a basic type,5mm diameter. The Measured welding parameters for one of the runs was 250amps,
24 volts, using DC+ve polarity, and a ROL of 180mm per min. What would be the Arc energy?
27 What is a typical ARC voltage setting when welding with the TIG(GTAW) process?
28 When MMA welding what will be the effect on the weld if the power source was changed from AC to
DC ve?
29 When using multiple SAW arc systems (twin wires etc), the arcs often have different polarities or use all
AC rather than DC polarity, this is to?
30 What is the mode of matel transfer for the TIG(GTAW) welding process?
32 Which of the following defects is usually associated with the MAG(GMAW) welding process when
Using DIP Transfer?
33 What would be the most likely SAW flux type for welding medium carbon steel which requires impact
Testing:
A] Visual B] Dye penetrant C] Magnetic particle using DC D]Magnetic particle using AC.
35 Which of the following commonly used radioactive isotopes has the longest half life?
36 For MPI using the prods method, which of the following statements is true:
A] Its inability to size defects accurately B] she physical size of the equipment
C] The skill level of the operators D] The harmful effects of ionizing radiation
39 Which of the following defects are unlikely to be detected by normal radiographic tecnoques?
A] higher carbon level B] higher chromium level C] lower carbon level D] lower chromium level
44 A post weld heat-treatment may also be of benefit in minimizing the risk of weld decay, the heat
Treatment would be called:
45 When welding medium carbon steel plates over 90mm in thickness would the basic electrodes require
Any pre-treatment before use?
A] None if they were in a vacuum pack B] None if they were used in a factory
C] Heat to 500 c for 2 hours if used outside D] Baked at 150c for 4 hour prior to use