You are on page 1of 77

Reports Catalog

Manufacturing

2010 Edition

1. REORDERING 2
2. ANALYSES 11
3. PRODUCTION DOCUMENTS 36
4. TECHNICAL DATA 52
5. VALUATION 72
Manufacturing p.2/77

Menu: Reports > Prints/group > Manufacturing > Reordering

1. REORDERING
1.1. MRP suggestions list (CBNSUG) 3
1.2. MPS suggestions list (PDPSUG) 5
1.3. Suggestion list ex-MRP (STOSUG) 7
1.4. Replenishment policy (TABREOPOL) 9

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.3/77

1.1. MRP suggestions list (CBNSUG)


This report displays the MRP suggestions list. The order types taken into account are customer order, supplier order, sub-contract material, sub-contract
service, work order, material requirement, inter-site order, inter-site request, sub-product, miscellaneous requests, miscellaneous resources, customer
reservation.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.4/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.5/77

1.2. MPS suggestions list (PDPSUG)


This report displays the MPS (Master Production Schedule) suggestions list. The order types taken into account are customer order, supplier order, sub-
contract material, sub-contract service, work order, material requirement, inter-site order, inter-site request, sub-product, miscellaneous requests,
miscellaneous resources, customer reservation.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.6/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.7/77

1.3. Suggestion list ex-MRP (STOSUG)


This report displays the ex-MRP (Material Requirement Planning) suggestions list. The order types taken into account are customer order, supplier order,
sub-contract material, sub-contract service, work order, material requirement, inter-site order, inter-site request, sub-product, miscellaneous requests,
miscellaneous resources, customer reservation.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.8/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.9/77

1.4. Replenishment policy (TABREOPOL)

Menu: Common data > Product Tables > Replenishment policy > File > Print > List

This report is used to print the replenishment policies corresponding to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 1. ERROR: REFERENCE SOURCE NOT FOUND p.10/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing p.11/77

Menu: Reports > Prints/group > Manufacturing > Analyses

2. ANALYSES
2.1. List of WOs (MFGHEAD) 12
2.2. List of WOs (MFGHEADE) 14
2.3. WO detail list (MFGHEADL) 16
2.4. Tracking list (MFGHEADTRK) 18
2.5. Material Yield (RENDMAT) 20
2.6. Operating Yield (RENDOPE) 22
2.7. Resource Yield (RENDRESS) 24
2.8. Late Order Analysis (RETPROD) 26
2.9. Time Analysis Report (TIMPROD) 28
2.10. Lead-time Analysis (DELPROD) 30
2.11. Resource Utilization Report (UTIRESS) 32
2.12. Work Load Listing (WORKLOAD) 34

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.12/77

2.1. List of WOs (MFGHEAD)

Menu: Manufacturing > Planning > Work Orders > File > Print > List

This report describes for each work order the information about the released product, operations and materials, in their progress status at the time of
printing.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.13/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.14/77

2.2. List of WOs (MFGHEADE)


This report is used to print the list of the WOs of a company, with or without break by site.
This print can either be sorted by WO no., WO start date or WO end date.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.15/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.16/77

2.3. WO detail list (MFGHEADL)


This report is used to print the list of the WOs of a company, with or without break by site.
This print can either be sorted by WO no., WO start date or WO end date.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.17/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.18/77

2.4. Tracking list (MFGHEADTRK)


This report describes the WO production tracking: released product tracking, operation tracking, material tracking.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.19/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.20/77

2.5. Material Yield (RENDMAT)


This report describes the results of the production analyses for the product dimension type and more precisely the material yield.
This report describes by site and product the data of the work order at the level of the material yield, the theoretical scrap (the product-site record) and
the actual scrap. An aggregation is achieved by product.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.21/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.22/77

2.6. Operating Yield (RENDOPE)


This report describes the results of the production analyses for the product dimension type and more precisely the operating yield.
This report describes by site and by work order the quantity yield, the time yield, the theoretical scrap (product-site record) and the actual scrap. An
aggregation is achieved by product.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.23/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.24/77

2.7. Resource Yield (RENDRESS)


This report describes the results of the production analyses for the resource dimension type and more particularly the resource yield (main work center
and labor work center).
This report presents by site and by work center the sum of quantities (planned and actual) and the reported scrap at the level of each work center, an
indication of the average yield and the average scrap. The results are totaled at the level of each work center.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.25/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.26/77

2.8. Late Order Analysis (RETPROD)


This report describes the results of the production analyses for the product dimension type and more particularly the late order analysis.
This report presents by site and product the data related to the work orders selected according to the number of early and late days, the achieved and
planned quantities (in release unit and stock unit). An aggregation is carried out by product (calculation of an early/late average, calculation of a total
quantity in stock unit).
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.27/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.28/77

2.9. Time Analysis Report (TIMPROD)


This report describes the results of the production analyses for the product dimension type and more particularly the production times.
This report describes the various productive times of the selected work orders, by site and by product: standard times, planned times, achieved times. An
aggregation is achieved by product.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.29/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.30/77

2.10. Lead-time Analysis (DELPROD)


This report describes the results of the production analyses for the product dimension type and more particularly the lead-time analysis.
This report presents by site and product the data of each selected work order, in other words: theoretical lead-time, planned lead-time, actual lead-time.
An aggregation is achieved by product.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.31/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.32/77

2.11. Resource Utilization Report (UTIRESS)


This report describes the results of the production analyses for the resource dimension type and more particularly the resource use (main work center
and labor work center).uuu
This report presents by site and by work center the hourly results with a comparison between the nominal capacity, planned times, achieved times, set-up
times and effective times. The results are totaled at the level of each work center.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.33/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.34/77

2.12. Work Load Listing (WORKLOAD)


This report displays the list of the work loads which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 2. ERROR: REFERENCE SOURCE NOT FOUND p.35/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing p.36/77

Menu: Reports > Prints/group > Manufacturing > Production Documents

3. PRODUCTION DOCUMENTS
3.1. Job tickets (BONTRV) 37
3.2. Material Issue notes (BSM) 39
3.3. Production folder (DOSFAB) 41
3.4. Routing sheet (FICHSUI) 42
3.5. Technical Sheet (FICHTEC) 44
3.6. Technical record answers (FICTECASW) 46
3.7. Stock labels (ETIQPROD) 48
3.8. Production Slip (RECETTE) 50

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.37/77

3.1. Job tickets (BONTRV)

Menu: Manufacturing > Planning > Work Orders > File > Print > Record

This report describes the production operations to be carried out by firm work order.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.38/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.39/77

3.2. Material Issue notes (BSM)

Menu: Manufacturing > Planning > Work Orders > File > Print > List

This report describes all the materials to be issued by work order firm and allocated.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.40/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.41/77

3.3. Production folder (DOSFAB)


The production folder is a grouping of reports. It comprises the following reports: Job ticket (BONTRV), Material issue slip (BSM), Routing sheet
(FICHSUI), Production slip (RECETTE) and technical sheet (FICHTEC).

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.42/77

3.4. Routing sheet (FICHSUI)

Menu: Manufacturing > Planning > Work Orders > File > Print > List

This report describes all the operations to be carried out at the level of the main work centers by firm work order.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.43/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.44/77

3.5. Technical Sheet (FICHTEC)

Menu: Manufacturing > Planning > Work Orders > File > Print > List

This report describes all the checks to be carried out on a released product at the level of an operation. It describes the questions asked for each
operation.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.45/77

Technical sheet

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.46/77

3.6. Technical record answers (FICTECASW)


This report displays the answers to the operating technical sheets corresponding to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.47/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.48/77

3.7. Stock labels (ETIQPROD)

Menu: Manufacturing > Production Tracking > Production Tracking > Option > Stock labels > Print

This report, that cannot be directly executed, is used to print the production labels corresponding to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.49/77

Stock labels

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.50/77

3.8. Production Slip (RECETTE)

Menu: Manufacturing > Planning > Work Orders > File > Print > List

This report describes all the operations to be carried out and the materials to be consumed by work order firm.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 3. ERROR: REFERENCE SOURCE NOT FOUND p.51/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing p.52/77

Menu: Reports > Prints/group > Manufacturing > Technical data

4. TECHNICAL DATA
4.1. Standard Operations Listing (ROUOPESTD) 53
4.2. Routing Listing (ROUTING) 55
4.3. Routing where used (ROUUSE) 57
4.4. Routing Code Listing (TABROUALT) 59
4.5. Weekly Structure Listing (TABWEEDIA) 61
4.6. Work Centre List (WORKCENTER) 63
4.7. Work Center Listing (WORKSTATIO) 65
4.8. Where-used Work centers (WSTUSE) 70

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.53/77

4.1. Standard Operations Listing (ROUOPESTD)

Menu : Manufacturing > Technical data > Routings > Standard Oprations > File > Print > List

This report is used to display a complete description of each standard operation as it has been defined in the site.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.54/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.55/77

4.2. Routing Listing (ROUTING)

Menu: Manufacturing > Technical data > Routings > Routings > File > Print > List
Menu: Manufacturing > Technical data > Routings > Routing where used > File > Print > List

This report displays the list of the routings which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.56/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.57/77

4.3. Routing where used (ROUUSE)

Menu: Manufacturing > Technical data > Routings > Routing where used > File > Print > List

This report displays the list of the routing where used which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.58/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.59/77

4.4. Routing Code Listing (TABROUALT)

Menu: Manufacturing > Technical data > Routings >Routing Codes > File > Print > List

This report displays the list of the routing codes which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.60/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.61/77

4.5. Weekly Structure Listing (TABWEEDIA)

Menu: Parameters > Manufacturing > Weekly Structures > File > Print > List
Menu: Parameters > Customer Relation > CRM Activity > Weekly Structures > File > Print > List

This report displays the list of the weekly structures: nominal capacity, number of actual hours and capacity factor.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.62/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.63/77

4.6. Work Centre List (WORKCENTER)


This report displays the list of the work loads which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.64/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.65/77

4.7. Work Center Listing (WORKSTATIO)

Menu: Manufacturing > Technical data > Work centers > Work Centers > File > Print > List
Menu: Manufacturing > Technical data > Work centers > Where-used Work centers > File > Print > List

This report describes the main work centers and labor work centers attached to a work center group.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.66/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.67/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.68/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.69/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.70/77

4.8. Where-used Work centers (WSTUSE)

Menu: Manufacturing > Technical data > Work centers > Where-used Work centers > File > Print > List

This report displays the list of the where-used Work centers which correspond to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 4. ERROR: REFERENCE SOURCE NOT FOUND p.71/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing p.72/77

Menu: Reports > Prints/group > Manufacturing > Valuation

5. VALUATION
5.1. WO cost detail (MFGCOST) 73
5.2. Cost Dimension Listing (WORKCOST) 76

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 5. ERROR: REFERENCE SOURCE NOT FOUND p.73/77

5.1. WO cost detail (MFGCOST)

Menu: Costing > Production Cost > Production Cost Inquiry > File > Print > Record

This report displays the detail of the Production Cost Price of the work orders corresponding to the following criteria:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 5. ERROR: REFERENCE SOURCE NOT FOUND p.74/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 5. ERROR: REFERENCE SOURCE NOT FOUND p.75/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 5. ERROR: REFERENCE SOURCE NOT FOUND p.76/77

5.2. Cost Dimension Listing (WORKCOST)

Menu: Common data > Costing > Costing Dimension > File > Print > List

This report fully describes the valuation dimensions defined at the site level.
The criteria are the following:

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage
Manufacturing > 5. ERROR: REFERENCE SOURCE NOT FOUND p.77/77

Reports Catalog - Sage ERP X3 version 6.2 - 2010 Edition - Sage 2010 - All rights reserved Sage

You might also like