You are on page 1of 5

Coal Mining and Production

Industry Description and Practices (up to 25% reduction). Coal beneficiation is


based on wet physical processes such as gravity
Coal is one of the world's most plentiful energy separation and flotation. Beneficiation produces
resources, and its use is likely to quadruple by two waste streams: fine materials that are
the year 2020. Coal occurs in a wide range of discharged as a slurry to a tailings
forms and qualities. There are two broad impoundment, and coarse material (typically
categories: (a) hard coal, which includes coking greater than 0.5 millimeters (mm) that is hauled
coal (used to produce steel) and other away as a solid waste.
bituminous and anthracite coals used for steam
and power generation; and (b) brown coal (sub- Waste Characteristics
bituminous and lignite), which is used mostly
as on-site fuel. Coal has a wide range of Key impacts of surface mining are typically
moisture (2-40%), sulfur (0.2-8%), and ash massive disturbances of large areas of land and
content (5-40%). These can affect the value of possible disruption of surface and groundwater
the coal as a fuel and cause environmental patterns. In some surface mines, the generation
problems in its use. of acid mine drainage (AMD) is a major
The depth, thickness, and configuration of problem. Other significant impacts include
the coal seams determine the mode of fugitive dust and disposal of overburden/waste
extraction. Shallow, flat coal deposits are mined rock.
by surface processes, which are generally less In underground mines, the surface
costly (per ton of coal) than underground mines disturbance is less obvious, but the extent of
of similar capacity. Strip mining is one of the possible subsidence can be very large. Methane
most economical surface processes. Here generation and release can also be a problem
removal of overburden and coal extraction under certain geological conditions. If
proceed in parallel strips along the face of the groundwater systems are disturbed, the
coal deposit, with the spoil being deposited possibility of serious pollution from highly
behind the operation in the previously mined saline or highly acidic water exists. Impacts may
areas. In open pit mining, thick seams (tens of continue long after mining ceases.
meters) are mined by traditional quarrying The following table presents the levels of
techniques. Underground mining is used for liquid effluents, solid waste, and dust generated
deep seams. Underground mining methods for the major mining techniques.
vary according to the site conditions, but all Beneficiation plants produce large volumes
involve the removal of seams followed by more of tailings and solid wastes. Storage and
or less controlled subsidence of the overlying handling of coal generates dust at rates which
strata. can be 3 kilograms (kg) per metric ton of coal
Raw coal may be sold as mined or may be mined, with the ambient dust concentration
processed in a beneficiation/washing plant to ranging from 10 to 300 micrograms per cubic
remove noncombustible materials (up to 45% meter (g/m3) (above the background level) at
reduction in ash content) and inorganic sulfur the mine site.

341
Coal Mining and Production 342

Loads Per Unit of Production*


Surface mining Underground mining
Parameter (t/1000t coal produced) (t/1000t coal produced)
Mining Techniques Contour Area Conventional Longwall
Liquid effluents 0.24 1.2 1 1.6
Solid waste 10 10 3 5
Dust 0.1 0.06 0.006 0.01

Source: Based on Edgar, 1983


* (Note: Local conditions will form the basis for choosing the appropriate mining method)

Pollution Prevention and Control

Early planning and careful design of operations


are the key to minimizing pollution associated
with mining activities. Specific responsibilities
should be assigned for the implementation and
monitoring of environmental measures. Before
mining begins, a mining plan and a mine
closure and restoration plan must be prepared
and approved. These plans define the sequence
and nature of extraction operations and detail
the methods to be used in closure and
restoration. These plans should be updated
regularly (every three to five years) as mining
progresses.

Development Plan

This plan defines the sequence and nature of


extraction operations and details the methods to
be used in closure and restoration. At a
minimum, the plan must address the following:
343 Coal Mining and Production

Removal and proper storage of topsoil. The plan should include reclamation of open
Early restoration of worked-out areas and pits, waste piles, beneficiation tailings,
of spoil heaps to minimize the extent of open sedimentation basins, and abandoned mine,
areas. mill, and camp sites. Mine reclamation plans
Diversion and management of surface and should incorporate the following:
groundwater to minimize water pollution Return of the land to conditions capable of
problems. Simple treatment to reduce the supporting prior land use, equivalent uses, or
discharge of suspended solids may also be other environmentally acceptable uses.
necessary. (Treatment of saline groundwater Use of overburden for backfill and topsoil
may be difficult.) (or other plant growth medium) for
Identification and management of areas reclamation.
with high potential for AMD generation. Contour slopes to minimize erosion and
Minimize the of generation of AMD by runoff.
reducing disturbed areas and isolating drainage Plant native vegetation to prevent erosion
streams by avoiding contacts with sulfur and encourage self-sustaining development of a
bearing materials. productive ecosystem on the reclaimed land.
A water management plan for operations Management of post-closure AMD and
and post-closure including minimization of beneficiation tailings.
liquid wastes by methods such as recycling Budget and schedule for pre- and post-
water from tailings wash plant. abandonment reclamation activities.
Minimization of spillage losses by proper Upon mine closure, all shaft openings and
design and operation of coal transportation and mine adits should be sealed or secured.
transfer facilities. There is a need to reserve money over the
Reduction of dust by early revegetation life of the mine to cover the costs associated
and by good maintenance of roads and work with mine closure. The amount of money and
areas. Specific dust suppression measures may the type of financing required will depend on a
be required for coal handling and loading number of factors such as the projected life of
facilities such as minimizing drop distances, the mine, the nature of the operations, the
covering equipment, and wetting storage piles. complexity of environmental issues, the
Release of dust from crushing and other coal financial and environmental management
processing and beneficiation operations should capacity of the borrower/project sponsor, and
be controlled. the jurisdiction in which the mine is located.
Controlling the release of chemicals The mine reclamation and closure plan, the
(including floatation chemicals) used in timing of its submission, and its financing
beneficiation processes. should be discussed and agreed with the
Minimization of the effects of subsidence borrower/sponsor as early as possible.
by careful extraction methods in relation to
surface uses. Target Pollution Loads
Control of methane, a greenhouse gas, (to
less than one percent by volume) to minimize Implementation of cleaner production processes
the risk of explosion in closed mines. Recover and pollution prevention measures can provide
methane where feasible. When methane content both economic and environmental benefits. The
is above 25 percent by volume, it normally target loads presented in the Waste
should be recovered. Characteristics Section should be used as a
Development of suitable restoration and guide for pollution prevention purposes. The
revegetation methods, appropriate to the figures relate to each of the production
specific site conditions. processes before the addition of pollution
Proper storage and handling of fuel and control measures.
chemicals used on-site to avoid spillages. There is a need to reserve money over the
life of the mine to cover the costs associated
Mine Closure and Restoration Plan with mine closure. The amount of money and
the type of financing required will depend on a
344 Coal Mining and Production

number of factors such as the projected life of Liquid Effluents


the mine, the nature of the operations, the
complexity of environmental issues, the Settling ponds to catch stormwater and to
financial and environmental management reduce suspended solids should be provided for
capacity of the borrower/project sponsor, and all effluent before discharge from the site.
the jurisdiction in which the mine is located. Where treatment of AMD or other effluents
The mine reclamation and closure plan, the is required, the following effluent levels should
timing of its submission, and its financing be achieved during operation and after mine
should be discussed and agreed with the closure.
borrower/sponsor as early as possible.
Acid Mine Drainage and Liquid Effluents
Emission Guidelines from Coal Mining
Maximum value
Emission levels for the design and operation of milligrams per liter
each project must be established through the (mg/L) except for pH)
Parameter
Environmental Assessment (EA) process, based
on country legislation and the Pollution pH 6-9
Prevention and Abatement Handbook as applied to Total suspended 50
local conditions. The emission levels selected solids*
must be justified in the EA and acceptable to
Oil and grease 10
MIGA.
The following guidelines present emission Iron 3.5
levels normally acceptable to the World Bank Total metals 10
Group in making decisions regarding provision
* A level of 35 mg/L should be the monthly average.
of World Bank Group assistance, including
MIGA guarantees; any deviations from these
Ambient Noise
levels must be described in the project
documentation.
Noise abatement measures should achieve
The guidelines are expressed as
either the following levels or a maximum
concentrations to facilitate monitoring. Dilution
increase in background levels of 3 dB(A).
of air emissions or effluents to achieve these
Measurements are to be taken at noise receptors
guidelines is unacceptable.
located outside the project property boundary.
All of the maximum levels should be
achieved for at least 95% of the time that the
plant or unit is operating, to be calculated as a
proportion of annual operating hours. Ambient Noise
Maximum Allowable Leq
Air Emissions (hourly), in dB(A)

Controls may be required on individual sources Receptor Daytime Nighttime


such as ventilation exhausts if they have a 07:00 - 22:00 22:00 - 07:00
significant effect on ambient particulate levels.
If coal crushers or dryers are used, fabric filters Residential; 55 45
or other systems should be used to recover coal institutional;
and reduce particulate emissions to levels below educational
50 milligrams per normal cubic meter
(mg/Nm3). Industrial; 70 70
commercial

The emission requirements given here can be


consistently achieved by well-designed, well-
345 Coal Mining and Production

operated and well-maintained pollution control Develop and implement a comprehensive


systems. environmental and mine management plan
to include:
Monitoring and Reporting - Restoration and rehabilitation of disturbed areas.
- Minimize land subsidence.
Frequent sampling may be required during - Identification and management of AMD sources.
start-up and upset conditions. All wastewater - Water management for operations and post-closure
discharges from the operations should be conditions.
monitored weekly for pH, total suspended - Management and sealing of pyrite containing piles
solids, and oil and grease. A full analysis to reduce AMD formation.
covering iron and other trace metals should be - Develop and implement a post-closure plan to
carried out quarterly. Where salinity is a include:
potential problem, appropriate parameters Restoration of disturbed areas.
(chloride, total dissolved solids (TDS), Long-term geotechnical and geochemical stability
conductivity) should be monitored. of waste piles.
Ambient air levels of particulate material, Restoration of acceptable long-term surface- and
including PM10 (particles less than 10 microns in groundwater flow patterns.
size), in and around mining operations should
be measured quarterly. Methane levels should Further Information
be monitored where appropriate, at least
annually even after mine closure. The following are suggested as sources of
Monitoring data should be analyzed and additional information (these sources are
reviewed at regular intervals and compared provided for guidance and are not intended to
with the operating standards so that any be comprehensive):
necessary corrective actions can be taken.
Records of monitoring results should be kept in Edgar, T.F. 1983. Coal Processing and Pollution
an acceptable format. These should be reported Control. Houston: Gulf Publishing.
to the responsible authorities and relevant
parties, as required, and provided to MIGA if Hartman, Howard L. (ed.) 1992. SME
requested. Engineering Handbook. 2nd ed., Vol.2. Littleton,
Colorado: Society for Mining, Metallurgy, and
Key Issues Exploration.

The following box summarizes the key World Bank, Environment Department. 1996.
production and control practices that will lead "Pollution Prevention and Abatement: Coal
to compliance with emission guidelines. Mining." Technical Background Document.

You might also like