MIS 363 Additional Assignment 2

Due Mar 20, 10AM, on Moodle

This assignment will not be graded. The solution will be posted on Moodle.
Submission count for participation points equivalent to two class participation.

According to the table as below, draw the Project Network with Activity Slack and
Critical Paths. Node shall be annotated with id, duration, early start time, early finish
time, late start time, late finish time and activity float. Write down the critical path
Activity Time Predecessor
A 8
B 4 A
C 5 B,F
D 12 A
E 8 D
F 4 D
G 9 E,F
H 12 G
I 6 C,G
J 5 I
K 9 H
L 12 J,K