Professional Documents
Culture Documents
I. GENERAL
1. ISO 8528
2. ISO 3046
3. BS 5514
4. IS 4722 & IS 1460
B. All equipment and material to be furnished and installed on this
project shall be in accordance with the requirements of the
authorities having jurisdiction, and suitable for its intended use
on this Project
III. SUBMITTALS
1. Drawings and CD
2. Data Sheets
11. The shop drawings shall include, but not be limited, to the
following:
a. Provide dimensioned plan views on an E size drawing sheet of all
EPS equipment showing sizes, weights and anchoring.
H. The date of acceptance shall be the date of the final payment for
the work or the date of a formal notice of acceptance, whichever
is earlier.
V. WARRANTY
Diesel Engines
1. Perkins
2. Cummins
3. Caterpiller
4. MTU
5. Volvo
Alternators
1. Stamford
2. Leroy Somer
VII. DEFINITIONS
M. Starting Time: Maximum total time period for a cold start, with
ambient temperature at low end of specified range, is 10
seconds. Time period includes output voltage and frequency
settlement within specified steady-stage bands.
1. Radiator cooled.
K. The external surface of the entire exhaust flue pipe and silencer
shall be wrapped aluminum cladding not less than 0.8mm thick.
6. Overspeed shutdown.
G. Enclosure: Drip-proof.
XV. DOCUMENTATION
A. Submittal Drawings
XVII. TRAINING
C. Provide standard certified factory test results for all ATS. Owner
may choose to witness these tests.
F. Test all alarms that would remotely communicate via the BMS
interface. Coordinate this task with the BMS vendor. The EPS
system must be connected to a BMS System utilizing the BMS
interface. The BMS must utilize the same modules, panels,
computer, software, printer etc., that will be utilized at the
project site. BMS vendor will furnish all BMS equipment. When at
the factory, the EPS vendor shall provide a location(s) for such
BMS equipment and will provide all wiring to the BMS equipment.
BMS vendor will make all final terminations at the BMS
equipment
G. Oil/Coolant samples:
H. BURN IN TESTING
1. Overload
2. Output over voltage.
3. Output under voltage.
4. PLC STATUS
5. Logic power failure
6. Synchronizing status
6. Provide six copies of the test report to the Engineer for review no
later that 14 calendar days from the completion of the site test.
C. The vendor must complete the Functional test forms for the EPs
System.
1. The site acceptance test shall be conducted for the benefit of the
Engineer and Owner to observe that the EPS system being
provided for this project complies with all portions of this
specifications.
2. The acceptance test shall be conducted in accordance with a
detailed acceptance test procedures (ATP). Which shall be
submitted by the Contractor and reviewed and approved by
Engineer and/or 0wner. The ATP shall list all required tests in the
chronological sequence in which the tests shall be performed at
the site. The ATP shall detail the exact method of connections,
expected responses and acceptable range of value for each item
in the test. Test shall include, as a minimum, those specified
below and such other tests as are deemed necessary by the
Engineer and/or Owner to ensure a satisfactory and compliant
system.
3. The manufacturers designated Field Service (local start/up
personnel) shall be part of the team witnessing the site tests. All
equipment, devices, and instrumentation required for conducting
the tests shall be furnished by the EPS manufacturer. If the test is
interrupted for any reason, including component failure, or if the
equipment does not meet the requirements of the specifications,
the entire test shall be repeated after the defects have been
corrected. Once started, load tests must run continuously
without interruption with temperature and electrical data logged
every 15 minutes. The ATP shall list the trip settings of all
protective devices. No readjustments or changes to trip settings
shall be permitted once the testing has begun. Upon completion
of the acceptance test, manufacturer shall submit six (6) certified
copies of the test report. In the event that the acceptance test
reveals that certain portions of the specified objectives have not
been met, the test report shall include a section which describes
in detail any deviations from specified performance; all
exceptions or deviations from specifications shall be specifically
pointed out in the test report. In such event, a complete review
and a discussion of means to remedy the deficiencies event, a
complete review and a discussion of means to remedy the
deficiencies shall follow the submission of the test report at a
joint session attended by the Owners representative and the
manufacturers engineering personnel involved in the design and
testing of the EPS system. Such a session shall take place at the
Owners desired location, at a date selected by the Owner.
4. Provide all meters required to demonstrate that each generator
and the EPS system comply with all performance requirements of
this specifications. Al meters provided for testing have been
calibrated within the six months period to the factory acceptance
testing. The minimum acceptable number of meters will be as
follows:
b. One high speed strip chart recorder, for all transient step load
testing, complete with all the necessary current transformers,
voltage connections, wiring and channels to measure all three
phases of voltage current and frequency. This meter may be used
for both generator and EPS system level testing. An Astromed 8U
strip recorder shall be used for this purpose (manufacturer may
submit a substation meter for this test to the engineer prior to
testing.).
7. Test all alarms that would remotely communicate via the BMS
interface. Coordinate this task with the BMS vendor. The EPS
System must be connected to a BMS system utilizing the BMS
interface. The BMS must utilize the same modules, panels,
computer, software, printer etc. That will be utilized at the
project site. BMS vendor will furnish all BMS equipment. When at
the site, the EPS vendor shall provide a location(s) for such BMS
equipment and will provide all wiring to the BMS equipment. BMs
vendor will make all final terminations at the BMS equipment.
E. BURN IN TESTING
0% Balanced Load
0% Load
5% Load
50% Load
75% Load
TRANSIENT TESTING Transient tests will be performed on
each generator with all loads at unity power factor. During
these tests, the high speed Oscillograph recorder and line
disturbance analyzer shall be used simultaneously to record
three phases of critical load output voltage and current with
sufficient speed to identify each cycle.
a. Overload
b. Output over voltage
c. Output under voltage
d. Primary PLC failure
e. Logic power failure
f. Synchronizing status
G. DOCUMENTATION OF TEST
H. INSTALLATION CERTIFICATION