Professional Documents
Culture Documents
Figure 1. Locus plan showing recommended rehabilitation segments and sensitive receptors.
Route 9 Crossing: Section 52 crosses under 7. Minimize impacts to the environment during
Route 9, which has an Average Daily Traffic construction
volume of over 52,000 vehicles. The pipeline has
several vertical bends allowing it to pass beneath 8. Acquire remaining permanent easements
other utilities at approximately 15 feet below the along Section 52 within public Right of Ways
road surface. The pipe is also encased in concrete
9. Complete design and construction on
in this location, making pipe replacement in the
schedule and within budget
same trench impractical.
Project Team
Wetland/Environmental Impacts: Section 52,
between Sears Road and Goddard Avenue, is located Green International Affiliates, Inc, (Green)
beneath a significant wetland system and stream Westford, MA served as the prime consultant
crossing, such that open cut pipe replacement for this project under MWRA Contract No.
would have caused significant wetland disturbance. 6288 working with MWRA's Engineering and
Construction Division. Green was responsible
Easements through Private Property: Section for project administration, rehabilitation design,
52 passes through a number of residential properties. permitting, traffic remediation, and construction
The old MDC easement that the pipeline was administration services. The project team also
constructed in had not been maintained and included a number of highly qualified design
residents had installed fences and landscape features subconsultants and contractors as follows:
over or along the pipeline, making access difficult.
Weston & Sampson Engineers, Inc. (WSE),
Peabody, MA, had lead responsibility for the
Project Goals
geotechnical investigation/hazardous material
MWRA established the following goals for program and also for wetland services.
the Section 52 Phase 2 project:
GEI Consultants, Inc. (GEI), Woburn,
1. Provide redundancy to the Southern High MA supported Green and WSE relative
Service System to Geotechnical Investigations, including
excavation stability and groundwater control.
2. Maintain water supply to the Southern Extra
High Service System during construction CorrTech, Inc. Hopkinton, MA had lead
responsibility for the corrosion assessment of
3. Rehabilitate appurtenances to improve the existing pipeline and recommendations
operation and maintenance of the pipeline for future corrosion protection.
W. Walsh Company, Inc., Attleboro, MA the extent of corrosion on the inner pipe wall as
was the specialty cleaning and cement-mortar shown in Photo 1. These internal inspections
lining subcontractor for the project. were considered to be representative of the entire
pipeline length because water quality is consistent
Project Cost and Schedule over the length of the pipeline.
Design services began on September 10, 2002
and bids for the project were received on December
20, 2005. Green estimated the construction cost
to be $8.26 million and J. D'Amico's bid was
$7.59 million. Construction began in February,
2006 and the Section 52 pipeline was brought
completely back in service in August, 2007, four
months ahead of schedule. The balancing change
order at project closeout resulted in a credit to
MWRA of $63,750.60.
together above ground, maintaining the welded in place. During the design phase, it was
integrity of the insulator gasket. The insulators determined that the 15-foot change in elevation
were tested before installation and in the under Route 9 could develop enough hydrostatic
trench. The self-restrained assemblies were pressure during the grout injection process to collapse
then lowered into place and connected with the new steel liner pipe if it was not protected.
welded butt straps in order to accept minor Therefore, the Contract Documents required the
pipe deflection angles. The assemblies work contractor to "charge" or fill the new slip-lined pipe
better than couplings because they did not with water prior to injecting grout into the annular
require an additional restraining harness with space in order to counteract the grout pressure.
tie rods, which can come in contact with the The segmental sliplining and grouting operation is
pipe and short-circuit the insulator. shown in Photo 3 and Figure 3.
The biggest challenge of the project was Cement-mortar lining, reinforced with welded
successfully completing the complex work under wire fabric (WWF) was used for the segments of
Route 9. This crossing was accomplished by pipe that were in fair condition, but where the
segmental sliplining, which uses short can surrounding soil environment had the potential
sections of steel pipe approximately 3 to 5 feet to develop corrosion holes in the future. Use of
long to negotiate sharp bends. Each 36 diameter reinforcement prevents cracking of the lining as it
"can" was carefully lowered and maneuvered into makes the lining self supporting (semi-structural).
position with special rigging and then internally Placing reinforced cement-mortar lining on a
Figure 3. SEGMENT 2: Profile of segmental sliplining a 36 diameter steel pipe through multiple horizontal
and vertical bends of the existing 54 diameter pipe under Route 9.
riveted steel pipe created new challenges during requirements. Specific requirements were included
the design and construction phases. Several in the Contract Documents for the contractor to
layers of cement-mortar lining were used to build prepare and follow a site specific Confined Space
up sufficient thickness over the rivets before the Entry (CSE) Plan combined with their HASP.
WWF was placed. The WWF cage was rolled up,
installed, expanded and welded together inside Access manholes for new pipe closure pieces
the pipe before the final layers of cement lining and man-ways on half-cap access pieces of existing
were placed. The reinforced cement-mortar lining pipe were included in the design for use during
provided for a larger final internal pipe diameter construction. These access points were 2-feet in
when compared to sliplining, and thus provided diameter and located at each end of pipe sections
the hydraulic capacity that MWRA required (at being lined. Once the final pieces of pipe were
a lower cost than sliplining or replacement). The welded back in place, these man-ways provided
installation of the reinforced cement-mortar lining for convenient, safe CSE access for the contractors
is shown in Photo 4. and inspectors while they completed welding,
lining and final inspection work inside the pipe.
An independent, qualified CSE Rescue Team
was designated by the Contractor and kept up to
date of the progress of work at all times in case of
emergencies.
Summary
MWRA allowed the design team to
thoroughly explore trenchless technology options
in order to extend the life of the existing pipeline,
thereby reducing costs, environmental impacts,
neighborhood disruption and unnecessary waste
of water resources. Multiple rehabilitation
methods were selected ranging from non-
Photo 4. SEGMENT 6: Reinforced cement lining
structural rehabilitation (i.e. cleaning and cement-
with welded wire fabric cage.
mortar lining) to full structural rehabilitation
(i.e. sliplining). Segmental sliplining was used to
A Health and Safety Plan (HASP) was negotiate vertical bends under Route 9. Reinforced
developed for this project to protect the cement-mortar lining was used for areas where the
contractors workers and the engineers inspectors. pipe condition was fair but the pipe environment
The level of care executed on the HASP for this was more corrosive. The major innovative features
project exceeded those prepared for previous of the project included the Integrated Corrosion
MWRA water main projects because of the Protection System, Segmental Sliplining through
confined space entry requirements. Access inside deep-buried vertical bends and the use of reinforced
large diameter buried pipelines was needed to cement-mortar lining over riveted steel pipe.
perform rehabilitation work, as well as inspections.
All work inside the Authoritys water main was A thorough pipeline assessment and
conducted in compliance with OSHA 29 CFR engineering analyses were critical to ensuring
1910.146 Permit-Required confined space entry complete Contract Documents and minimal
change orders during construction. Engineering The multiple rehabilitation methods used on the
enhancements for the MWRA as a result of this project, combined with work under Route 9, work
project include the Rehabilitation Alternative through residential properties in Brookline, work
Selection Process Flow Chart, the innovative through Hellenic College, work under wetlands,
corrosion protection measures and the HASP and having to maintain water supply to customers
Planning. Complaints and neighborhood issues at all times made this a complex project. However,
were minimized during construction by keeping the the project was completed ahead of schedule,
public informed about the work during all phases under budget, and with minimal complaints or
of the project through neighborhood meetings neighborhood issues, while being located in a
and notices. The perception by abutters and the residential section of Brookline where abutters'
public during construction was that rehabilitation expectations for quality work were extremely high.
projects using trenchless technologies will MWRA was able to re-establish its easements and
minimize impacts to the environment compared provide redundancy to their system with minimal
to installing new pipe. environmental impact.