You are on page 1of 10

MWRAs Heath Hill Water Main Rehabilitation Project

with the Innovative Use of Trenchless Technologies


By Michael Pelletier, P.E.,* Peter A. Richardson, P.E.,** Milan Horbaczewski, P.E.,*** and
Kevin OBrien, P.E.****
Presented April 1, 2009

seams and joints that was constructed in 1927-


Abstract 1928. The pipeline extends from the Chestnut Hill
The Heath Hill Section 52 Phase 2 project High Service Pumping Station located on Beacon
consisted of rehabilitating 2 miles of an 80-year Street in Boston, through Brookline, and then back
old, 54-inch diameter steel water main in Brookline into Boston where it connects to MWRA's Section
and Boston for the MWRA. The pipeline had 19 at the Arborway in Jamaica Plain (See Figure1).
experienced leaks from corrosion and is a critical In addition to being a major water transmission
component of MWRAs transmission system. main for the MWRA's Southern High Service
Detailed pipeline and environmental assessments Area, Section 52 is one of the primary supply mains
were conducted and trenchless technologies were for the two booster pump stations that service the
used to develop a sustainable rehabilitation approach. Authority's Southern Extra High Service System.
A combination of conventional and reinforced Prior to the Phase 2 Rehabilitation project, this
cement-mortar lining, as well as sliplining and an critical pipeline had already exceeded its design
innovative Integrated Corrosion Protection System life and was experiencing leaks from corrosion.
were implemented to overcome the challenges of In 1997, approximately 800 linear feet of Section
construction work in Route 9, residential properties, 52 located in Heath Hill Road was replaced due
Hellenic College, and wetlands. to excessive leaks and corrosion. The remaining
11,500 linear feet was rehabilitated under the
Introduction Phase 2 project, which was completed in 2007.

Project Description Design Issues and Challenges


The Heath Hill Section 52 Phase 2 The pipeline route presented a number of
Rehabilitation Project consisted of design and design issues and challenges as follows:
construction services for more than 2 miles of
water transmission main in Brookline and Boston Abutters and Mature Street Trees: Roadways
for the Massachusetts Water Resources Authority along a large portion of the pipeline route are
(MWRA). Section 52 is a 54-inch diameter steel residential streets with healthy mature shade trees.
water main with a mixture of riveted and welded Trench excavation near root systems of these large
trees would have likely caused damage to them.
*Senior Associate, Green International Affiliates, Inc.,
Westford, MA Maintain Service to Newton Street Pump
**Vice President, Green International Affiliates, Inc., Station: MWRA Sections 19, 76 and 96 are all
Westford, MA fed by Section 52. Section 19, as well as either
***Senior Program Manager, Massachusetts Water
Resources Authority, Chelsea, MA 76 or 96, had to remain in service at all times
****Director, Massachusetts Water Resources during the project, such that Section 52 had to be
Authority, Chelsea, MA rehabilitated in two phases.

140 Journal NEWWA June 2010


Michael Pelletier, P.E., Peter A. Richardson, P.E., Milan Horbaczewski, P.E.,
and Kevin OBrien, P.E.

Figure 1. Locus plan showing recommended rehabilitation segments and sensitive receptors.

Journal NEWWA June 2010 141


MWRAs Heath Hill Water Main Rehabilitation Project with the Innovative Use of
Trenchless Technologies

Route 9 Crossing: Section 52 crosses under 7. Minimize impacts to the environment during
Route 9, which has an Average Daily Traffic construction
volume of over 52,000 vehicles. The pipeline has
several vertical bends allowing it to pass beneath 8. Acquire remaining permanent easements
other utilities at approximately 15 feet below the along Section 52 within public Right of Ways
road surface. The pipe is also encased in concrete
9. Complete design and construction on
in this location, making pipe replacement in the
schedule and within budget
same trench impractical.
Project Team
Wetland/Environmental Impacts: Section 52,
between Sears Road and Goddard Avenue, is located Green International Affiliates, Inc, (Green)
beneath a significant wetland system and stream Westford, MA served as the prime consultant
crossing, such that open cut pipe replacement for this project under MWRA Contract No.
would have caused significant wetland disturbance. 6288 working with MWRA's Engineering and
Construction Division. Green was responsible
Easements through Private Property: Section for project administration, rehabilitation design,
52 passes through a number of residential properties. permitting, traffic remediation, and construction
The old MDC easement that the pipeline was administration services. The project team also
constructed in had not been maintained and included a number of highly qualified design
residents had installed fences and landscape features subconsultants and contractors as follows:
over or along the pipeline, making access difficult.
Weston & Sampson Engineers, Inc. (WSE),
Peabody, MA, had lead responsibility for the
Project Goals
geotechnical investigation/hazardous material
MWRA established the following goals for program and also for wetland services.
the Section 52 Phase 2 project:
GEI Consultants, Inc. (GEI), Woburn,
1. Provide redundancy to the Southern High MA supported Green and WSE relative
Service System to Geotechnical Investigations, including
excavation stability and groundwater control.
2. Maintain water supply to the Southern Extra
High Service System during construction CorrTech, Inc. Hopkinton, MA had lead
responsibility for the corrosion assessment of
3. Rehabilitate appurtenances to improve the existing pipeline and recommendations
operation and maintenance of the pipeline for future corrosion protection.

Other support subconsultants included: Howe


4. Provide hydraulic capacity to meet present
Surveying Associates, Inc., Timelines, Inc.
and future needs for its service area
(Historic Assessment), and Conover & Company
Communications, Inc. (Public Relations).
5. Improve dewatering operations in order to
drain any pipe segment in six hours or less J. D'Amico Inc., Randolph, MA was the
general contractor for the project. They were
6. Minimize impacts to abutting properties and the low bidder and were subsequently awarded
the general public during rehabilitation MWRA Construction Contract No. 5194.

142 Journal NEWWA June 2010


Michael Pelletier, P.E., Peter A. Richardson, P.E., Milan Horbaczewski, P.E.,
and Kevin OBrien, P.E.

W. Walsh Company, Inc., Attleboro, MA the extent of corrosion on the inner pipe wall as
was the specialty cleaning and cement-mortar shown in Photo 1. These internal inspections
lining subcontractor for the project. were considered to be representative of the entire
pipeline length because water quality is consistent
Project Cost and Schedule over the length of the pipeline.
Design services began on September 10, 2002
and bids for the project were received on December
20, 2005. Green estimated the construction cost
to be $8.26 million and J. D'Amico's bid was
$7.59 million. Construction began in February,
2006 and the Section 52 pipeline was brought
completely back in service in August, 2007, four
months ahead of schedule. The balancing change
order at project closeout resulted in a credit to
MWRA of $63,750.60.

Discussion of Pipeline Assessment


The key to the success of this project was
the thorough pipeline assessment that was
undertaken during preliminary design. The
pipeline assessment ensured that the contract
documents were complete and included the proper
rehabilitation techniques for different pipeline
segments, avoiding costly change orders. The
pipeline assessment included a hydraulic modeling Photo 1. SEGMENT 1 & 2: Internal physical
analysis, which involved development of modeling inspection and cement-mortar lining.
scenarios and parameters. Simulations were run on
the Authoritys water distribution system model to In addition, a structural analysis was performed
analyze the effects of the rehabilitation techniques. on a coupon taken from the Section 52 pipeline and
a Closed Circuit Television (CCTV) inspection
A critical part of the pipeline assessment was the was performed by MWRA's Operations Division
external pipe inspections performed by CorrTech. along 1,200 linear feet of pipe. Lastly, a thorough
environmental assessment was performed relative
Nine (9) large test pits were excavated in order to
to hazardous materials, traffic, wetlands, and
expose and analyze 1% of the pipeline exterior.
mature shade trees on residential streets.
The inspections included measuring depths
of surface pitting, taking ultrasonic thickness
measurements and performing a statistical analysis
Results of Rehabilitation Design
to determine the probability of future leaks. Soil Based on the results of the field testing
corrosivity, stray current and pipeline electrical work, the corrosion evaluation, the structural
continuity were also analyzed. In addition to the evaluation and the hydraulic analysis, the existing
external inspections, portions of the pipeline were pipeline was divided into six segments with varied
dewatered and two 50-foot long detailed internal pipe conditions and future corrosion potential.
pipe inspections were also performed to determine Specific levels of rehabilitation were proposed for

Journal NEWWA June 2010 143


MWRAs Heath Hill Water Main Rehabilitation Project with the Innovative Use of
Trenchless Technologies

each segment according to the condition of the


pipeline and its environment. Applying specific
rehabilitation methods to different segments
reduced the overall project cost and environmental
impact when compared to complete pipeline
replacement. Segment specific rehabilitation also
allowed hydraulic capacity to be maximized, as it
would have been reduced by sliplining the entire
length of pipeline.

A detailed Rehabilitation Alternative Selection


Process Flow Chart was developed to select the
appropriate rehabilitation method for each segment.
The recommended levels of rehabilitation were
based on the American Water Works Association
(AWWA) Manual M28 Rehabilitation of Water
Mains, 2nd Edition (2001), as follows: Class I
linings (Non-Structural); Class II and III linings
(Semi-Structural); and Class IV (Fully-Structural or
Structurally Independent) linings (or replacement).
The flow chart for one of the representative
Photo 2. SEGMENT 4 & 5: Sliplining new 48
segments is shown in Figure 2. Per M28, the type diameter steel pipe near mature shade trees and
of rehabilitation methods used for each segment, as estate properties.
shown in Figure 1, were as follows:

SEGMENT 1: Cement-mortar lining with a In addition to using trenchless technologies,


double-pass thickness to cover rivets (Class I) some new pipe sections were also installed by open-
cut methods to complete the rehabilitation, improve
SEGMENT 2: Segmental sliplining new 36 interconnections and modify the alignment.
dia. steel pipe (short pieces) with welded joints
(Class IV) An Integrated Corrosion Protection System
(ICPS) was developed and implemented for the
SEGMENT 3 Phase I: Pipe replacement rehabilitation of Section 52, using techniques
with new direct-buried 54 dia. steel pipe (by that are normally reserved for new pipes only.
MWRA) Corrosion protection materials were integrated
into many aspects of the design details to create
SEGMENT 4 & 5: Sliplining new 48 dia. a stronger barrier against future corrosion. The
steel pipe with welded joints (Class IV) as ICPS included the following items:
shown in Photo 2.
Insulating Flange Assemblies were designed
SEGMENT 6: Reinforced cement-mortar and used instead of restrained insulating
lining with multiple passes to cover rivets couplings. The flange assemblies are
(Class II and III) approximately 2-feet long and were bolted

144 Journal NEWWA June 2010


Michael Pelletier, P.E., Peter A. Richardson, P.E., Milan Horbaczewski, P.E.,
and Kevin OBrien, P.E.

together above ground, maintaining the welded in place. During the design phase, it was
integrity of the insulator gasket. The insulators determined that the 15-foot change in elevation
were tested before installation and in the under Route 9 could develop enough hydrostatic
trench. The self-restrained assemblies were pressure during the grout injection process to collapse
then lowered into place and connected with the new steel liner pipe if it was not protected.
welded butt straps in order to accept minor Therefore, the Contract Documents required the
pipe deflection angles. The assemblies work contractor to "charge" or fill the new slip-lined pipe
better than couplings because they did not with water prior to injecting grout into the annular
require an additional restraining harness with space in order to counteract the grout pressure.
tie rods, which can come in contact with the The segmental sliplining and grouting operation is
pipe and short-circuit the insulator. shown in Photo 3 and Figure 3.

Grout with a corrosion inhibitor was used to


fill the annular space between the new slip-
lined pipe and the existing pipe for the first
time on an MWRA project. The atomizing
inhibitor provides a barrier between the new
steel and the old steel, reducing the potential
for corrosion.

Concrete encasement with a corrosion


inhibitor was used to protect sections of
new direct buried pipe that were removed
for internal access points, as well as around
insulating flange assemblies and around
connections of slip-lined pipe with new direct
buried pipe. Heat shrink sleeves were also
used at each end of new pipe segments to
prevent future corrosion from stray current.

Sacrificial anodes were used in addition to


tape wrapped pipe on new pipe sections and
also added to one section of existing pipe Photo 3. SEGMENT 2: Segmental sliplining and
(Segment 3) to supplement the system. annular space grouting under Route 9.

The biggest challenge of the project was Cement-mortar lining, reinforced with welded
successfully completing the complex work under wire fabric (WWF) was used for the segments of
Route 9. This crossing was accomplished by pipe that were in fair condition, but where the
segmental sliplining, which uses short can surrounding soil environment had the potential
sections of steel pipe approximately 3 to 5 feet to develop corrosion holes in the future. Use of
long to negotiate sharp bends. Each 36 diameter reinforcement prevents cracking of the lining as it
"can" was carefully lowered and maneuvered into makes the lining self supporting (semi-structural).
position with special rigging and then internally Placing reinforced cement-mortar lining on a

Journal NEWWA June 2010 145


MWRAs Heath Hill Water Main Rehabilitation Project with the Innovative Use of
Trenchless Technologies

Figure 2. Rehabilitation Alternative Selection Process Flow Chart

146 Journal NEWWA June 2010


Michael Pelletier, P.E., Peter A. Richardson, P.E., Milan Horbaczewski, P.E.,
and Kevin OBrien, P.E.

Figure 3. SEGMENT 2: Profile of segmental sliplining a 36 diameter steel pipe through multiple horizontal
and vertical bends of the existing 54 diameter pipe under Route 9.

Journal NEWWA June 2010 147


MWRAs Heath Hill Water Main Rehabilitation Project with the Innovative Use of
Trenchless Technologies

riveted steel pipe created new challenges during requirements. Specific requirements were included
the design and construction phases. Several in the Contract Documents for the contractor to
layers of cement-mortar lining were used to build prepare and follow a site specific Confined Space
up sufficient thickness over the rivets before the Entry (CSE) Plan combined with their HASP.
WWF was placed. The WWF cage was rolled up,
installed, expanded and welded together inside Access manholes for new pipe closure pieces
the pipe before the final layers of cement lining and man-ways on half-cap access pieces of existing
were placed. The reinforced cement-mortar lining pipe were included in the design for use during
provided for a larger final internal pipe diameter construction. These access points were 2-feet in
when compared to sliplining, and thus provided diameter and located at each end of pipe sections
the hydraulic capacity that MWRA required (at being lined. Once the final pieces of pipe were
a lower cost than sliplining or replacement). The welded back in place, these man-ways provided
installation of the reinforced cement-mortar lining for convenient, safe CSE access for the contractors
is shown in Photo 4. and inspectors while they completed welding,
lining and final inspection work inside the pipe.
An independent, qualified CSE Rescue Team
was designated by the Contractor and kept up to
date of the progress of work at all times in case of
emergencies.

Summary
MWRA allowed the design team to
thoroughly explore trenchless technology options
in order to extend the life of the existing pipeline,
thereby reducing costs, environmental impacts,
neighborhood disruption and unnecessary waste
of water resources. Multiple rehabilitation
methods were selected ranging from non-
Photo 4. SEGMENT 6: Reinforced cement lining
structural rehabilitation (i.e. cleaning and cement-
with welded wire fabric cage.
mortar lining) to full structural rehabilitation
(i.e. sliplining). Segmental sliplining was used to
A Health and Safety Plan (HASP) was negotiate vertical bends under Route 9. Reinforced
developed for this project to protect the cement-mortar lining was used for areas where the
contractors workers and the engineers inspectors. pipe condition was fair but the pipe environment
The level of care executed on the HASP for this was more corrosive. The major innovative features
project exceeded those prepared for previous of the project included the Integrated Corrosion
MWRA water main projects because of the Protection System, Segmental Sliplining through
confined space entry requirements. Access inside deep-buried vertical bends and the use of reinforced
large diameter buried pipelines was needed to cement-mortar lining over riveted steel pipe.
perform rehabilitation work, as well as inspections.
All work inside the Authoritys water main was A thorough pipeline assessment and
conducted in compliance with OSHA 29 CFR engineering analyses were critical to ensuring
1910.146 Permit-Required confined space entry complete Contract Documents and minimal

148 Journal NEWWA June 2010


Michael Pelletier, P.E., Peter A. Richardson, P.E., Milan Horbaczewski, P.E.,
and Kevin OBrien, P.E.

change orders during construction. Engineering The multiple rehabilitation methods used on the
enhancements for the MWRA as a result of this project, combined with work under Route 9, work
project include the Rehabilitation Alternative through residential properties in Brookline, work
Selection Process Flow Chart, the innovative through Hellenic College, work under wetlands,
corrosion protection measures and the HASP and having to maintain water supply to customers
Planning. Complaints and neighborhood issues at all times made this a complex project. However,
were minimized during construction by keeping the the project was completed ahead of schedule,
public informed about the work during all phases under budget, and with minimal complaints or
of the project through neighborhood meetings neighborhood issues, while being located in a
and notices. The perception by abutters and the residential section of Brookline where abutters'
public during construction was that rehabilitation expectations for quality work were extremely high.
projects using trenchless technologies will MWRA was able to re-establish its easements and
minimize impacts to the environment compared provide redundancy to their system with minimal
to installing new pipe. environmental impact.

Journal NEWWA June 2010 149

You might also like