BILL OF QUANTITIES
Item 1: Project Information
Project Title M2 Building Renovation
Purpose Design,Budget and Implementation of M2 Building Renovation
Requesting BU JVMC
Location Road 3 Bo.1 Koronadal City
Item2: Quantities
Particulars Qty Unit Amount Total
Materials
Cement ( Mayon ) 166 bags 250.00 41,500.00
Washed Sand 9 cum 230.00 2,070.00
Gravel 3/4" 18 cum 620.00 11,160.00
G.I Wire # 16 1 roll 1,838.00 1,838.00
Welding Rod N55 5 kgs 98.00 490.00
10mm DRB 196 L 102.00 19,992.00
12 mm DRB 16 L 176.00 2,816.00
16 mm DRB 12 L 300.00 3,600.00
Total Materials 83,466.00

PROJECT ESTIMATOR PROJECT COORDINATOR PROJECT CONTROL CLERK PROJECT IMPLEMENTOR PROJEC

____________________ _____________________ ______________________ __________________ _______________________


Signature over Printed Name Signature over Printed Name Signature over Printed Name Signature over Printed Name Signatu