ID Task Task Name Duration Start Finish 23 Jan 13 Feb 06 Mar 27 Mar 17 Apr 08 May 29 May 19 Jun

Mode Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed
1 REHABILITATION OF WATER STORAGE TANK IN SHELL R.A 87 days Mon 20/02/17 Tue 20/06/17
SUB-STATION 4
2 ENGINEERING/PROCUREMENT 17 days Mon 20/02/17 Tue 14/03/17
3 Site survey 2 days Mon 20/02/17 Tue 21/02/17
4 Material procurement 5 days Tue 21/02/17 Mon 27/02/17
5 PRE-STARTUP AUDIT 7 days Tue 28/02/17 Wed 08/03/17
6 Kick-off meeting 1 day Tue 28/02/17 Tue 28/02/17
7 HSES Provisions 3 days Wed 01/03/17 Fri 03/03/17
8 Quality Assurance 3 days Mon 06/03/17 Wed 08/03/17
9 PREMOBILIZATION ACTIVITIES 3 days Fri 03/03/17 Tue 07/03/17
10 Premob inspection 3 days Fri 03/03/17 Tue 07/03/17
11 SITE MOBILIZATION 9 days Mon 10/04/17 Thu 20/04/17
12 Transport of materials to site 6 days Mon 10/04/17 Mon 17/04/17
13 Mobilization of personnel/equipment 3 days Tue 18/04/17 Thu 20/04/17
14 EXECUTION PHASE 43 days Tue 18/04/17 Thu 15/06/17
15 Erection of scaffolds 4 days Tue 18/04/17 Fri 21/04/17
16 Dismantling of existing Braithwaite Tank 7 days Mon 24/04/17 Tue 02/05/17
17 Fabrication of internal bracing,cleats and other accessories 11 days Wed 03/05/17 Wed 17/05/17
18 painting 3 days Thu 18/05/17 Mon 22/05/17
19 Assembling of Braithwaite Tank 8 days Tue 23/05/17 Thu 01/06/17
20 Final painting 4 days Fri 02/06/17 Wed 07/06/17
21 Dismantling of scaffolds 3 days Thu 08/06/17 Mon 12/06/17
22 Commissioning 1 day Tue 13/06/17 Tue 13/06/17
23 Report writing 2 days Wed 14/06/17 Thu 15/06/17
24 DEMOBILIZATION 3 days Fri 16/06/17 Tue 20/06/17
25 Site restoration 2 days Fri 16/06/17 Mon 19/06/17
26 Project close-out 1 day Tue 20/06/17 Tue 20/06/17

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Water Storage Tank Reha
Milestone Inactive Task Manual Summary Rollup Progress
work for Shell R.A
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 1
19 Jun 10 Jul 31 Jul 21 Aug 11 Sep 02 Oct 23 Oct 13 Nov 04 Dec 25 Dec 15 Jan 05 Feb 26 Feb 19 Mar 09 Apr 30 Apr 21 May 11 Jun 02 Jul 23 Jul
Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun Tue Thu Sat Mon Wed Fri Sun

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Water Storage Tank Reha
Milestone Inactive Task Manual Summary Rollup Progress
work for Shell R.A
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 2