NDCT # 1
1 Job Pile 750 728
2 For Tower Crane 750 5
Sub-Total 733
NDCT # 2
3 Job Pile 750 728
4 For Tower Crane 750 5
Sub-Total 733
Chimney
5 Job Pile 750 496
Sub-Total 496
Power Block Area
6 MPHB # 1 & 2 641
7 TDBFP # 1 24
8 MDBFP # 1 12
9 STG # 1 102
10 Boiler # 1 279
11 PA Fan # 1 20
12 FD Fan # 1 20
13 ID Fan # 1 34
14 Coal Mill # 1 244
15 ESP Foundation # 1 380
16 MDBFP # 2 12
17 TDBFP # 2 24
18 STG # 2 102
19 Boiler # 2 272
20 PA Fan # 2 20
21 FD Fan # 2 20
22 ID Fan # 2 34
23 Coal Mill # 2 244
24 ESP Foundation # 2 380
25 Control Building 153
Sub-Total 3017
Service Building
26 Service Building 81
Sub-Total 81
Fly Ash silo
27 Silo - 1, 2 & 3 156
Sub-Total 156
Bottom Ash hopper
28 Unit # 1 36
29 Unit # 2 36
Sub-Total 72
Test Piles
30 19
Sub-Total 19
TOTAL 5307
L&T POWER - TPPC
MW Super Critical Thermal Power Project, Rajpura
ils piling works (M-25 Concreting)
Theorotical Conc.
Depth of Boring Depth of Conc. Total consumption Qty up to
up to OGL (RM) (RM) of Concrete (Cum) COL+1.0m
(Cum)
12919.50 12282.35
295.50 286.28
147.00 143.14
3076.00 2415.89
5968.50 5723.50
144.00 130.06
140.00 130.06
240.00 221.11
5245.00 4997.99
1906.00 1826.53
144.00 143.01
325.50 286.28
2124.50 2095.45
5160.00 5034.57
221.10 23.00 145.00 130.62
140.00 130.06
238.00 221.11
4851.50 4604.51
1906.50 1826.53
3261.50 3090.58
48378.00 45719.62
1379.00 1288.20
1379.00 1288.20
75714.23 72119.16
Total Wastage 3595.07
Debited to S/C 1314.4
Wastage 2280.67
Piling Conc works 73433.56
Excess (above
COL) Concrete
Qty (Cum)
279.35
5.31
284.66
309.56
7.08
316.64
42.71
42.71
637.15
9.22
3.86
660.11
245.00
13.94
9.94
18.89
247.01
79.47
0.99
39.22
29.05
125.43
14.38
9.94
16.89
246.99
79.97
170.92
2658.38
90.80
90.80
143.83
143.83
18.89
20.39
39.28
18.78
18.78
3595.07
Details of PCC & RCC Qty in GCW for Oct'2014
Qty
S.no Description Power Block BOP
(A) (B)
1 PCC M-10 7638.459 3917.609
Qty
Total
(C = A + B)
11556.068
131.187
1158.771
21188.355 120
123.782
48842.897
9191.165
23901.580 500
6597.660
23.440
122714.9050
er final bill
PB
11425
15
1528
12130
43222
588
296
24434
93638
Qty FTM of Oct'2014
Description
Power Block BOP
PCC M-15
M-20 ( AGL )
M-30 ( AGL)
M-40 BGL
S. no Description
CHIMNEY
2 CHIMNEY RAFT ( M 25 )
NDCT-01
1 NDCT-01 PCC ( M- 10 )
19 Pre-cast
23 Corbel (M30)
NDCT-02
1 NDCT-02 PCC ( M- 10 )
18 Pre-cast
19 Stair case ( M30 )
Summary
S.No Description
1 M-10
2 M-25
3 M-30
4 M-35
5 M-40
M10 244
M25 12257
M40 3344.000
M35 6125.000
Completed
M35 1597.283
M35 1899.789
M35 1138.809
M35 1141.000
27746.881
M10 828.000
M30 4137.617
M10 1132.000
M30 7878.000
M40 1459.870
M40 512.370
M40 3044.913
M40 4173.000
M40 1828.830
M40 2011.980
M40 1332.100
M40 1151.382
M40 573.893
M40 1122.415
M40 564.228
M30 548.780
M30 1838.000
M30 2033.000
M30 77.000
M30 814.000
M30 45.000
M30 190.000
M30 77.300
38835.918
M10 828
M30 4137.617
M30 7878.000
M40 2102.649
M40 2734.595
M40 2492.318
M40 2603.000
M40 1889.000
M40 1706.045
M40 1127.600
M40 162.800
M40 1394.800
M40 1258.673
M40 100.364
M30 898.483
M30 115.060
M30 114.090
M30 109.000
M30 2512.581
M30 459.340
M30 814.000
M30 47.000
38081.967
Total Qty
M-10 4164.00
M-25 12257.00
M-30 35525.51
M-35 11901.88
M-40 40816.38
104664.766
CONCRETING QTY FOR TEMPORARY STRUCTURES INCLUDING WEIGH BRIDGE & BOILER LAYD
AREA (Status as on Oct'14)
1 M10
2 M20
Chimney - Concreting for Temporary works
3 M25
4 M30
5 M10
6 M15
NDCT # 1 - Concreting for Temporary works
7 M20
8 M25
9 M10
10 M-15
NDCT # 2 - Concreting for Temporary works
11 M20
12 M25
13 M10
Temporary Structure - Store, P&M workshop, Time office,
14 Safety, Labour Colony, LPG Storage Godown, Main office, M15
15 Slipper work, Steel yard, Gantry, Haripur Road repair, Pit Bldg M20
& Fabrication Yard
16 M25
17 M10
18 Batching Plant M20
19 M25
20 M10
21 M15
Laydown Area
Laydown Area
22 M20
23 M25
24 Counter block for crane M25
25 Counter block for crane M30
26 Chemical foundation for Boiler M20
27 Chemical foundation for Boiler M25
28 Pressure Part Assembly M10
29 M10
Switch Yard
30 M25
31 M10
L&T Power - EPC
32 M25
33 M10
34 M20
35 BMH - CHP Area for Wagon Trippler M25
36 M30
37 M35
SUMMARY : -
S NO ITEM QTY (Cum)
1 M10 1595
2 M15 880
3 M20 789
4 M25 872
5 M30 996
6 M35 111
Total RCC Qty 5242
RIDGE & BOILER LAYDOWN
UOM QTY
Cum 130.5
Cum 16.0 50.5
Cum 5.5 16.0
Cum 4.0
Cum 110.0 0.0
Cum 46.0
Cum 12.0
Cum 63.0
Cum 7.0 0.0
Cum 34.0
Cum 10.0
Cum 103.0
Cum 1044.5
Cum 772.8
Cum 75.3
Cum 215.3
Cum 51.0
Cum 139.0
Cum 134.0
Cum 294.0
Cum 107.5
Cum 493.3
Cum 238.5
Cum 33.0
Cum 93.0
Cum 27.0
Cum 9.0
Cum 8.0
Cum 75.0
Cum 212.0
Cum 1.0
Cum 12.5
Cum 4.0
Cum 38.0
Cum 12.0
Cum 903.0
Cum 110.5
Details of concrete consumption in piling works as per certified
1) RCC ( M-25) of GCW Piling-Pile dia wise RM qty - Actual consumption Upto Aug'12
Concreting of Pile in RM
S.No Description
600
1 Cum. Upto RAB-24 5998.000
TOTAL (Rm) 5998.000
Summary
Grand Total for M-25 piling upto Aug'12 75492.500
Built up quantity ( M-40 ) upto Aug'12 183.734
s per certified RA Bill for Aug'12
on Upto Aug'12
750 1000
30011.500 39483.000
30011.500 39483.000
75492.500