Professional Documents
Culture Documents
Field Data-Based Probabilistic Assessment On Degradation of Deformational Performance For Shield Tunnel in Soft Clay
Field Data-Based Probabilistic Assessment On Degradation of Deformational Performance For Shield Tunnel in Soft Clay
A R T I C L E I N F O A B S T R A C T
Keywords: Performance assessment of operated metro shield tunnel is critical for safety, functionality and durability of
Performance assessment segmental lining structures. Furthermore, aleatory and epistemic uncertainties existed in the external
Probability density evolution environments and internal materials inevitably cause random structural performance over its designed service
Shield tunnel life. In view of the situation, this paper presents a probabilistic assessment on the degradation of deformational
Horizontal convergence
performance for shield tunnel in Shanghai soft clay by using well-documented field data. Horizontal convergence
Deformational performance
of inner diameter is selected as the basic performance indicator. The performance metric is reasonably assumed
to be a parabolic transformation from horizontal convergence. Then, stochastic analysis is carried out to
demonstrate the evolution of probability density function both over long-term period and short-term period. On
the basis of field data, a lognormal random process is proposed and fairly well validated to represent the
evolution of long-term performance. It is calculated that the probability of tunnel deformational performance
less than 95% (i.e., the serviceability limit of deformational performance) after 10-year operation is equal to
0.70, and the performance less than 75% (i.e., the ultimate limit state of deformational performance) after 50-
year operation is about 0.036. In addition, the autoregressive integrated moving average (ARIMA) model is
applied to gain insights relating to deformational performance evolution that produces relatively accurate short-
term forecasts. The monitoring frequency of twice a month is suggested for the accuracy of prediction based on
the field data in Shanghai. The proposed time-dependent deformational performance is helpful to determine the
necessity and urgency of preventive and control measures.
⁎
Corresponding author at: Geotechnical Building, Tongji University, Siping Road 1239, 200092 Shanghai, China.
E-mail addresses: huanghw@tongji.edu.cn (H.-w. Huang), 7zhangyj@tongji.edu.cn (Y.-j. Zhang), 09zhang@tongji.edu.cn (D.-m. Zhang), ba@umd.edu (B.M. Ayyub).
http://dx.doi.org/10.1016/j.tust.2017.05.005
Received 24 October 2016; Received in revised form 9 April 2017; Accepted 5 May 2017
0886-7798/ © 2017 Elsevier Ltd. All rights reserved.
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
108
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
1.20 Fig. 4. The material of segments is composed of the C55 concrete and
Deformational performance Q
the Q235 reinforced steel bars. More details about the material
1.00 parameters can be found in the regulation (STB/ZH-000001, 2010).
Fig. 5 depicts the longitudinal geology profile of a typical tunnel. The
0.80 groundwater table is about 0.7–0.9 m below the ground surface. The
initial cover depth of tunnel axis ranges between 17 m and 20 m. As
0.60 shown in Fig. 5, the tunnel was buried in the typical Shanghai soft clay.
It has been investigated that this type of soft clay shows strong time-
dependent behavior, e.g. consolidation and creep in a relatively long-
0.40
DF /Dout 0.0303 term period (Zhang et al., 2003; Yin et al., 2011). According to the site
investigation and laboratory test results, Fig. 6(a) illustrates the main
0.20 physical properties of the soils, including water content (w), void ratio
(e) and soil unit weight (γ). Fig. 6(b) presents the mechanical properties
0.00 of soils, such as N value (SPT), undrained shear strength (su), effective
0.000 0.005 0.010 0.015 0.020 0.025 0.030 0.035 cohesion (c'), effective friction angle (φ'), the compressive modulus (Es)
Horizontal convergence ratio ( D/Dout ) and the lateral earth pressure coefficient (K0). It is obvious that the soil
in this area has a high level of water content (e.g., 35% on average),
Fig. 2. Variation of performance with the increase of convergence.
resulting in a low level of strength (e.g., averaged su = 30 kPa) and
stiffness (e.g., averaged Es = 3 MPa).The time-dependent behavior of
Metro Line 2 are briefly introduced in this section. This tunnel is
surrounding soft clay might be the main reason causing the post-
representative for most of the existing metro tunnels in Shanghai in
construction deformation for tunnels even after a long period of
terms of excavation method, lining structural features, and construction
operation time. The post-construction deformation is the key concern
circumstances (Zhang and Huang, 2014; Liao et al., 2009; Wang, 2009).
for maintenance engineers in metro company and is thus mainly
The alignment of this tunnel is shown in Fig. 3. This tunnel was
discussed in this paper.
excavated by earth pressure balance (EPB) shield machine. Each lining
The time flow of this metro tunnel is shown in Fig. 7. The
ring of the metro tunnel was assembled by six segments. Each joint
construction for tunnel lining structure was completed in October
between two adjacent segments was connected by two 5.8-M30 steel
2008. Afterwards, the structural decoration and operation electronic
bolts. The designed outer diameter of each lining ring is 6.2 m with a
signal system were constructed before the trial operation was started in
wall thickness of 0.35 m and a longitudinal width of 1.2 m, as shown in
Investigated section
(S195~S280)
102m
Borehole
Tunnel Alignment
109
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
Concrete segment
Radial joint
Steel bolt
twall = 0.35m
Convergence
monitoring point
Fig. 4. Cross section of the instrumented segmental lining.
7
Elevation
Fill
Silty Clay
-1 Muddy sility clay
m m Sandy silt
Muddy sility clay
Tunnel crown
-9
Muddy clay
Investigated tunnel
Tunnel invert
-17
1-1 1-1 Clay
-25
3-1 3-1 Mixed silt and clay
June 2010. From May 2010 to April 2011, monitoring procedure of are strongly correlated. Therefore, horizontal convergence as a single
cross-section horizontal convergence was carried out by total station at indicator is capable to generally assess the tunnel deformational
45 different time moments. In the early 50 days of the monitoring performance in this case. In the present study, twelve lining rings
period, the monitoring frequency is once every three days. After then, numbered S199, S210, S215, S220, S230, S236, S241, S251, S256,
the frequency was reduced to once per week since the measurement S261, S272, and S278, were installed with the measurement points
indicates the relative stability of the deformation evolution. Fig. 4 among 85 lining rings ranging from ring No. S195 to ring No. S280. The
shows the layout of measurement points. They were installed at the nearby environmental condition is quite clean as shown in Fig. 3, and
inner surface of lining at about the springline (marked by solid triangle the ground condition shown in Fig. 5 has no significant variability along
dots in Fig. 4). the longitudinal alignment. Hence, the convergence for each ring is
Huang et al. (2017) have conducted a survey of the lining regarded to be comparable. The measured twelve convergence data
deformation for a number of lining rings in Shanghai Metro Line 2, could be seen as the random and independent structural response
and the results show that the joint open and the horizontal convergence samples. These data were used to develop a probabilistic model for
110
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
15
20.00
20
1
25.70 25
30
3-1
35 Max
Max
Min Min
40.45 40 Mean Mean
(a)
5
m
10
15
20
1
25
30
3-1
35 UU (Max)
CU Test Oedometer K0 Test
CU Test
UU (Min) Max Max Max Max
UU (Mean) Min Min Min Min
40 CPT Mean Mean Mean Mean
qu Test
(b)
Fig. 6. Soil properties from the site investigation: (a) physical properties; (b) mechanical properties.
assessment and prediction of tunnel deformational performance, which for tunnel lining is quantified by horizontal convergence ratio ΔD/Dout
is illustrated in the following section. (see Eq. (1)). Since Dout is constant at 6.2 m in this case, statistical
analysis of measured horizontal convergence ΔD was carried out before
the characterization of its deformational performance.
4. Long-term prediction for tunnel deformational performance
111
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
4.1. Long-term prediction of tunnel convergence ΔD tunnel (between S195 and S280) at a specific date j is assumed to be a
time-dependent random variable. Subsequently, a sequence of such
4.1.1. Data base collection time-dependent random variables constitutes a random process which
On the basis of measurement plan, observations of horizontal is denoted as {X(t): t ∈ T} = {X(t1), X(t2), … , X(t45)}, where X(ti) is a
convergence from twelve lining rings are available for collection within random variable within the time domain T (i.e., from May 2010 to April
the 250 days (i.e., from May 2010 to April 2011). Fig. 8 plots the 2011).
measured horizontal convergences along the time line. The original
point of time t (set to zero) stands for the date on May 30, 2010 since 4.1.2. Long-term prediction model
when the shield tunnel was put into operation. It is not surprising that For the established stochastic process {X(t): t ∈ T}, its forty-five
these field data sparsely distributed along the time line. The data dimensional cumulative distribution function (CDF) and the corre-
variation at a specific date in Fig. 8 reflects the difference for the sponding forty-five dimensional probability density function (PDF) are
convergence in the investigated twelve lining rings, which validates the expressed as follows, respectively:
objective of this paper that the tunnel convergence or deformational
F (x1,x2,…,xn;t1,t2,…,tn ) = P {X (t1) ⩽ x1,X (t2 ) ⩽ x2,…,X (tn ) ⩽ xn} (3a)
performance should be assessed in a probabilistic perspective. In
addition to the data being with significant scatter, Fig. 8 shows a small f (x1,x2,…,xn;t1,t2,…,tn ) (3b)
growth trend of convergence ΔD as a function of time t with an upper
bound and lower bound represented by red dash lines. where x1, x2, … , xn ∈ R and t1, t2, … , tn ∈ T. The CDF for random
For an explicit description of this data set, a 12 × 45 matrix is variables at different time points might be different in terms of
introduced to represent the dataset, which is expressed as: distribution type and parameters. It is necessary to infer the type of
probability distribution for each random variable X(t) based on the
⎡ ΔD1,1 ΔD1,2 ⋯ ΔD1,45 ⎤
⎢ ⎥ sample data, i.e., convergence values of twelve different lining rings.
X=⎢ ⋮ ⋮ ⋱ ⋮ ⎥ Due to the small amount of sampling, the Kolmogorov–Smirnov test
⎢⎣ ΔD12,1 ΔD12,2 ⋯ ΔD12,45⎥⎦ (2) (K–S test), as one of the most useful and general nonparametric
methods, was adapted to test whether the samples came from a
where ΔDi,j denotes the magnitude of convergence of lining ring i at
hypothesized distribution F(x) or not.
time j, e.g., ΔD8, 34 means the value of convergence ΔD at the 8th ring
In the present work, considering ΔD takes only positive real values,
on the 34th day dated from the original date. The convergence of the
K-S test was performed for lognormal distribution, which is often used
to model observations in measurement analysis. With the level of
S199 S210 S215 S220
significance α = 0.05, it was found that at each observation time point,
41 S230 S236 S241 S251
D
Ring No. the observed data are consistent with the hypothesized lognormal
39 S256 S261 S272 S278 distribution. Therefore, the sample of each X(t) reasonably follows
lognormal distribution and {X(t): t ∈ T} was subsequently modeled as a
Horizontal convergence
37
discrete-time lognormal random process.
35 12
1
(mm)
112
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
100 (|ε|) was modeled as a zero mean white noise source. Consequently, the
time-variant convergence ΔD(t) was treated as a continuous-time
90
lognormal random process, which was expressed as the sum of a trend
D (mm)
80 Observed mean value term and a random term, as follows (unit: mm):
1 ⎛ −[ln(1−x )−λ′]2 ⎞
f (x ) = exp ⎜ ⎟
15 S199 S210 S215 S220 2π (1−x ) ζ′ ⎝ 2ζ′ 2 ⎠ (10)
D (mm)
12 Ring No. S230 S236 S241 S251 Corresponding to the above PDF for performance index Q, the mean
9 S256 S261 S272 S278 and variance of Q at a given time moment t can be expressed as bellow:
6 1
μQ = 1− exp(2λ + 2ζ 2 )
3 (ΔDF )2 (11a)
Residual error of
0 1
σQ2 = exp(4λ + 4ζ 2 )[exp(4ζ 2 )−1]
-3 (ΔDF )4 (11b)
-6 Note that ΔDF is equal to 188 mm. Substituting ΔDF (188 mm), μ
-9 (i.e., Tr(t)) and σ (i.e., 1.73) from Eq. (6) into Eqs. (7)–(11), the time-
variant probability density function for performance Q(t) can be
-12
derived:
-15
1 ⎛ −[ln(1−x )−λ′(t )]2 ⎞
0 50 100 150 200 250 f (x,t ) = exp ⎜ ⎟
2π (1−x ) ζ′(t ) ⎝ 2[ζ′(t )]2 ⎠ (12)
(May 30, 2010)
Service time (day)
The mean function μQ(t) and standard deviation function σQ(t) of Q
Fig. 10. Residual error of ΔD at each time point. (t) can be expressed as follows:
113
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
0.99
0.98
0.98 0.97
0.96
0.97
0.95
0.96
.measured performance .measured performance
0.94 O predicted performance
O predicted performance
performance of the five lining rings over time, shown by the solid
μQ (t ) = −3.04 × 10−10t 2−5.75 × 10−6t + 0.973 (13a) black dots. The predicted deformational performance of the whole
tunnel (between lining S195 and S280) by using the above random
σQ (t ) = 3.21 × 10−7t + 0.003 (13b) process model (Eq. (12)) are also plotted in Fig. 12, represented by the
hollow grey dots. It is found that the measured performance data
Eq. (13) indicates that the mean value of performance decreases in a intensively locate around the main trend of predicted values, which are
parabolic form and the standard deviation increases in a linear form MCS results from the lognormal random process prediction model.
with time. It should be reasonable that the convergence of tunnel lining These results illustrate that the prediction of the mean of tunnel
will increase with time because of the time-dependent material deformational performance is reasonable and reliable for at least the
degradation effect. But the uncertainty of the performance prediction early five-year service life of the investigated shield tunnel. On the
in the context of the standard deviation will become more significant in other hand, the relative concentration of the measured performance
the future. data at each time t shows slightly smaller variance than that of the
Once the distribution associated with data characteristics was predicted deformational performance. The smaller variability results
obtained to represent the stochastic process of tunnel deformational from the fact that the available observations are only based on five
performance Q(t), the Monte Carlo simulation (MCS) was performed to lining rings, which is a relatively small sample size to produce an
generate a large amount of realizations. For each day in the time accurate standard deviation for validation.
domain (T = 0 ∼ 250 days), in which convergence observations are
available, 1000 realizations were generated to describe the evolution of
4.4. Prediction of long-term performance
tunnel deformational performance Q(t). Fig. 11 plots both the measured
and predicted performance Q during the 250 days, i.e., the hollow grey
Since the proposed probabilistic prediction model of tunnel perfor-
dots denote the data predicted by using MCS and the solid black dots
mance evolution has been fairly well validated in particular with the
represent the measured data. It is clearly seen from Fig. 11 that the
evolution of the mean of the performance, long-term performance
range of predicted data from the above random process model properly
prediction could be made for the tunnel with a similar condition, i.e., a
covers the original measured data. In other words, both the general
shield driven tunnel with a similar range of cover depth, similar ground
evolution trend and fluctuation of tunnel deformational performance
condition and operational condition. In this section, prediction analysis
with time generally agree well with field data. Hence, it proves that the
is demonstrated on deformational performance of metro shield tunnel
proposed random process model could reproduce the real performance
after a long period of service time (say 10 years for example). Under the
in an acceptable accuracy.
assumption that the long-term evolution of tunnel performance fol-
lowed the proposed random process derived previously, then perfor-
4.3. Validation of proposed random process of Q(t) mance degrading with time has a trend in a parabolic form with linearly
increasing variance (see Eq. (13)).
The prediction model to describe probabilistic evolution of tunnel Based on the constructed stochastic process, a MCS was performed
deformational performance Q(t) proposed here is assumed to follow the to simulate the evolving process of deformational performance until the
lognormal distribution at any moment t. This assumption is an outcome tunnel operates for 50 years, i.e., 18,250 days. Fig. 13 shows the
of the data collected at hand and should be validated by another simulation results and provides a comprehensive view of performance
independent data set for the same tunnel. To this end, the updated daily degradation. By applying Eq. (12), tunnel deformational performance
convergence data dated from Oct 30 of 2015 to Mar 30 of 2016, i.e., a could be predicted in the form of probability density function at
total of 130 days, were measured for five rings (i.e., S236, S251, S261, different time periods, say at the 1st year, 10th year, 20th year, 30th
S220, and S278) among the investigated twelve lining rings of the same year, 40th year, and 50th year of tunnel operation. Fig. 14 shows the
metro tunnel in Line 2 of Shanghai. By applying Eq. (1), corresponding change of these performance probability density functions (PDFs) when
deformational performance of each of the five lining rings was the time moment reaches the above six levels. It is not surprising to
calculated. observe from Fig. 14 that the PDF curve of performance evolution is
It should be noted that the initial time (t = 0) of the proposed model getting more and more “flat” in shape from the 1st year to the 50th
was set on May 30 of 2010. Hence, the starting date of validation data year. It should be attributed to the variance of performance degradation
set (i.e., Oct 30 of 2015) and the ending date of validation data set (i.e., increasing over time. Obviously the uncertainty becomes significant
Mar 30 of 2016) correspond to the time point at 1950 days and when performance deterioration progresses with increase of service
2080 days, respectively. Fig. 12 plots the measured deformational time. By integration probability density function at several points in
114
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
1.00E+00
Q<35%
1.00E-02 Q<45%
Probability
Q<55%
1.00E-04
Q<65%
1.00E-06 Q<75%
Q<85%
1.00E-08 Q<95%
1.00E-10
0 10 20 30 40 50 60 70 80 90 100 110
Time (year)
Fig. 15. Evolution of probabilities {P(Q < 35%), P(Q < 45%), … , P(Q < 95%)} over time.
115
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
of convergence evolution might be arguable for sound predictions. view and data are equally distributed along the zero line with certain
Therefore, more efficient approaches might be helpful to improve the randomness.
accuracy of prediction. In this section, autoregressive integrated mov- For the available 34 data points for Q∗(t), the first 30 points were
ing average (ARIMA) model, which has been widely used in modeling selected for establishing the ARIMA model, while the left four points for
temporal dependence structure of time series, is applied for a more model validation. Following the four-step procedure of building ARIMA
accurate prediction of evolution of the mean of tunnel deformational model, an explicit prediction model ARMA (3,2) for {dQ∗(t)} was
performance (denoted as Q∗ hereafter), especially in a relative short- developed by using the first 30 data points with the best-fitted model
term period. parameters and coefficients, which is expressed as follows:
dQt∗ = −0.361dQt∗−1−0.734dQt∗−2−0.346dQt∗−3 + εt + 0.228εt −1 + 0.938εt −2
5.1. Autoregressive integrated moving average model for predicting short-
(14)
term performance
where and dQ∗t, dQ∗t-1, dQ∗t-2 dQ∗t-3
are first order difference results of
An ARIMA model has three important model parameters (Box and the mean of deformational performance at time t, t-1, t-2 and t-3,
Jenkins, 1976), including p (i.e., order of auto-regressive process), d respectively. The parameters εt, εt-1 and εt-2 are the prediction errors at
(i.e., degree of difference), and q (i.e., order of moving average time t, t-1 and t-2, respectively.
process). It has been widely used and validated as an effective way Based on the above ARMA (3,2) model for {dQ∗(t)}, a corresponding
for data-learning and prediction (Liu et al., 2015; Ramos et al., 2015). ARIMA (3,1,2) model for {Q∗(t)} could be subsequently derived by an
In general, the procedure of building ARIMA model consists of four integral treatment since dQ∗ is the first order difference of Q∗. Hence,
main steps. First, it is necessary to test the stationarity of the time series the mean of deformational performance Q∗ could be predicted by the
by augmented Dickey-Fuller (ADF) unit root test (Elliott et al., 1996). following equation:
The non-stationary time series should be transformed by square root,
logarithmic algorithm or difference method to achieve stationarity. Qt∗ = 0.639Qt∗−1−0.373Qt∗−2 + 0.388Qt∗−3 + 0.346Qt∗−4 + εt + 0.228εt −1
Second, model parameters (p, q) are identified with autocorrelation + 0.938εt −2 (15)
function (ACF) and partial autocorrelation function (PACF) analyses
It is quite clear to see from Eqs. (14) and (15) that this prediction
(Box et al., 1994) and some other identification methods such as
model is dynamic and depends largely on the previous measured data.
Akaike's Information Criterion (AIC) (Shibata, 1976) and the Bayes
The previous three data points are necessary for predicting the fourth
information criterion (BIC) (Gideon, 1978). Third, based on the model
point of first order difference of the mean of performance dQ∗, while
identification the value of corresponding model coefficients can be
previous four data points are required for the fifth point of the mean of
estimated by comparing the goodness-of-fit of the models with different
performance Q∗. This essentially reflects the principle of dynamic short-
coefficient combinations. Finally, model test should be conducted to
term prediction. Fig. 17 plots the 4th-30th fitted data and the 31st-34th
assess model adaptability including significance test of coefficient,
predicted data by applying the proposed ARMA(3,2) model for
model stability test and residual diagnosis. Note that there are a
{dQ∗(t)}. It is found that there is a high agreement between the actual
number of possible models due to different combinations of model
and simulated values of {dQ∗(t)}. Therefore, this model could be
parameters and coefficients. Hence, these four steps should be repeated
applied for further analysis on {Q∗(t)}.
until the most appropriate model is obtained.
To apply ARIMA model for the short-term prediction of tunnel
lining deformational performance, a corresponding time series with a 5.2. Prediction of the mean of short-term performance
constant interval should firstly be generated. To this end, the weekly
convergence data of the twelve lining rings were extracted from the On the basis of the established model, the means of tunnel
original convergence observations. Then the weekly time series of the deformational performance from 5th week to 34th week were simu-
mean value of tunnel deformational performance could be derived lated. It should be noted that this model was established only based on
following the procedure developed in last section for long-term predic- the first 30 weekly measured data. In other words, the results before the
tion (see in Eq. (1)). Denoted as {Q∗(t)}, this time series includes a total 30th week calculated by using this model are the validation of the
of 34 data points and has been plotted against time tin Fig. 16 goodness of fit for this proposed model. The simulated results from the
(represented as the solid dot line). From Fig. 16, the time series 31st week to 34th week are the predictions of this model. Fig. 18 plots
{Q∗(t)} shows evidence of non-stationarity as there is a slight down- these 34 simulated data against time (see the hollow dot line). In
ward movement in the data. Therefore the first order difference was addition, the actual means of deformational performance of 34 weeks,
performed to remove the trend and a new series (denoted as {dQ∗(t)}) which were derived from field measured data, are also plotted in Fig. 18
was generated, plotted as the hollow dot line in Fig. 16. It can be for a comparison. It is observed from Fig. 18 that the simulated mean of
observed that the downward trend was removed in a graphical point of performance Q∗ agrees quite well with the actual data both for the
previous 30 weeks and the later 4 weeks. Additionally, Fig. 19 illus-
Q* dQ*
0.003 Actual Fitted Forecast
0.974 0.003
1st difference of Q* (dQ*)
0.002
Mean of deformational
0.973 0.002
performance Q*
0.001 0.001
0.972
0.000 0.000
0.971
-0.001 -0.001
0.970
-0.002
-0.002 Fitted Predicted
0.969 -0.003
-0.003
0.968 -0.004
0 35 70 105 140 175 210 -0.004
Service time (day) 0 35 70 105 140 175 210 245
Service time (day)
Fig. 16. Weekly time series of the mean of deformational performance and its first order
difference. Fig. 17. Comparison between actual dQ* and simulated values using ARMA (3,2).
116
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
0.974 (a)
Actual 0.974
Mean of deformational
0.973 Fitted
Mean of deformational
Forecast 0.973 Actual
performance Q*
0.972 Fitted
performance Q*
0.972 Forecast
0.971
0.971
0.970
0.970
0.969
Fitted Predicted 0.969
0.968
0 35 70 105 140 175 210 245
0.968
Service time (day) 0 35 70 105 140 175 210 245
Fig. 18. Comparison between actual Q* and simulated values using ARIMA (3,1,2). Service time (day)
0.003 (b)
0.002 0.975
Mean of deformational
+ 0.974 Actual
0.001 Fitted
performance Q*
0.973
Residual
Forecast
0.000 0.972
0 35 70 105 140 175 210 245
0.971
-0.001
- 0.970
-0.002
0.969
Service time (day)
-0.003 0.968
0 35 70 105 140 175 210 245
Fig. 19. Residuals of ARIMA (3,1,2).
Service time (day)
trates the residual error of the simulated results by subtracting the real Fig. 20. Fitness and prediction by ARIMA model using once two weeks measurement
measured results. It is clear seen from Fig. 19 that most of the errors frequency: (a) odd numbered subseries; and (b) even numbered subseries.
between the simulated and actual results of {Q∗(t)} are less than one
time of standard deviation (σ) of the model residual error. 17 data points, the previous 15 points for establishing model and the
Since ARIMA model is designed based on the correlations of the last two points as validation of predictability of the model. Similar
periodically collected data, it works best when the investigated data ARIMA modeling procedure to the previous model was then performed
exhibit a stable or consistent pattern over time (Akhtar and Rozi, 2009). for these two series. The best-fitted ARIMA (1,1,1) and ARIMA (2,1,1)
Since the tunnel deformational performance is naturally degraded as models were developed for the odd numbered series and even
time elapses, Fig. 19 has validated the relative stable and consistent numbered series, separately. Similar to Fig. 18, Fig. 20 plots the
form of variation. It thus results in a fairly well agreement between the simulated mean of performance Q∗ against time for the odd numbered
measured and predicted means of performance. The magnitude of the series (Fig. 20a) and even numbered series (Fig. 20b), respectively. In
predicted means of performance Q∗ and the associated bias from the addition, the actual measured data are also plotted in these figures. It is
actual data of the last 4 weeks are displayed in Table 1. The absolute also clear seen from Fig. 20 that the agreement between simulated and
percentage error (APE) was calculated to assess the bias of the proposed actual data are quite well both for the 15 fitted data points and the two
model. The APE value for each step ahead is rather small, i.e., APEmax is predicted data points.
equal to 0.11%, indicating that the constructed model ARIMA (3,1,2) Table 1 also exhibits the detailed comparison of prediction of the
for description of the evolution of the mean of tunnel deformational last two data points with the corresponding measured data. The
performance is reliable with high accuracy, and therefore can be used maximum of APE shows in Table 1 is around 0.12% which is close to
to forecast the expected numbers of cases. the APEmax equal to 0.11% for the previous ARIMA (3,1,2) model of
Note that the above prediction model was established based on one-week series. It is indicated that the ARIMA modeling based on these
weekly measurements (i.e., one data point is selected every other two subseries of the mean of tunnel deformational performance is able
week). In order to investigate the effect of monitoring frequency, in to achieve the comparable accuracy compared with the ARIMA (3,1,2)
other words, the choice of data interval, two time series were newly model of one-week series. In other words, when developing an ARIMA
built in this way that one data point was selected every two weeks, i.e., model for the time series of the mean of tunnel deformational
one series was for the data from odd-number weeks such as 1st, 3rd performance, its time interval can be rationally increased to two weeks.
week and etc., and the other was for the data from even-number weeks This would be helpful to facilitate appropriate practical inspection or
such as 2nd, 4th week and etc. Each group of these two series contained monitoring program on tunnel convergence. Similar analysis has been
Table 1
Predicted mean of performance Q* and associated bias APE.
117
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
conducted for four weeks a point time series. But the APE for the data set for long-term prediction, using the data of a total of
ARIMA model using four weeks a point frequency is relatively larger 30 weeks to predict the next four weeks could produce reasonably
than that of the one-week time series, as seen in Table 1. Hence, accurate performance. Through model comparison it is also in-
according to the present work, the monitoring frequency can be dicated that the optimal monitoring frequency can be reasonably
reasonably arranged as every two weeks for one point of data arranged as twice a month.
acquisition.
It can be concluded that the ARIMA model can be used to describe Overall, this approach allows for dynamic updating of the predic-
and predict the dynamic evolution of the mean of tunnel deformational tions both in the long term and short term based on continuously
performance with low computational complexity and reasonable accu- collected data in real time. The authors have to note that this data-
racy. However, it is known that ARIMA model is able to predict more driven dynamic analysis is purely based on the available measurement
accurately on the short term. With the extension of prediction period, data at hand. Hence, the conclusions and results are mostly suitable for
the prediction error will gradually increase. This is the natural tunnel linings with similar size and similar ground condition such as in
insufficiency of ARIMA model. In order to increase prediction accuracy, Shanghai metro. According to the probabilistic description and predic-
newly collected data should be added continually to the performance tion of deformational performance derived from field data, we are able
sequence over time. Consequently new parameter-coefficient combina- to get a fairly good understanding of the health status of tunnel lining
tions of the ARIMA model might be updated to the new series. Updating system and of the lifetime serviceability condition. The results are
the prediction model by using previous data is the essential sense of beneficial to guide the routine maintenance and deformation control to
data-driven probabilistic assessment of tunnel performance on the short prevent progressive failure of tunnel lining structure.
term.
The short-term performance prediction presented in the study case Acknowledgements
is illustrative for the shield tunnels operating in normal conditions, i.e.,
without the impact of extreme events or the implementation of This study is substantially supported by the financial support from
maintenance actions during the investigated time interval. As a result, the Natural Science Foundation Committee Programs (Grant nos.
the change of the Q value looks insignificant in a short term. However, 51608380 and 51538009). The support is gratefully acknowledged.
the significance of the short-term performance prediction is threefold. Besides, the field data are collected with the help of Dr. Rulu Wang and
First, through comparing the prediction accuracy of data collected at Mr. Hua Shao from Shanghai Metro Co., Ltd. The authors are also
different time intervals, appropriate short-term inspection and mon- grateful to them.
itoring interventions can be scheduled, i.e., whether it is 4 weeks,
2 weeks or even one week for the monitoring frequency. Second, short- References
term performance prediction is more precise and could be updated by
monitoring actual structural responses to ensure the satisfactory Ai, Q., Yuan, Y., Mahadevan, S., Jiang, X.M., 2016. Probabilistic degradation modeling of
operation until it reaches the limit state. The short-term prediction of circular tunnels assembled from segmental linings. Struct. Concr. 17 (2), 257–273.
Akhtar, S., Rozi, S., 2009. An autoregressive integrated moving average model for short-
mean value of performance could assist the long-term performance term prediction of hepatitis C virus seropositivity among male volunteer blood
prediction in this sense. Thirdly, timely short-term performance evalua- donors in Karachi, Pakistan. World J. Gastroenterol. 15, 1607–1612.
tion and prediction play an important role in the early warning of the Andrade, C., Martínez, I., 2009. Use of indices to assess the performance of existing and
repaired concrete structures. Constr. Build. Mater. 23, 3012–3019.
sudden drop of performance when extreme events occur. As the Asakura, T., Kojima, Y., 2003. Tunnel maintenance in Japan. Tunn. Undergr. Space
beneficial complementation for long-term prediction, therefore, it is Technol. 18 (2–3), 161–169.
necessary and significant to conduct more reliable short-term perfor- Ayyub, B.M., 2014a. Systems resilience for multihazard environments: definition, metrics,
and valuation for decision making. Risk Anal. 34, 340–355.
mance prediction. Ayyub, B.M., 2014b. Risk Analysis in Engineering and Economics, second ed. Chapman
Hall/CRC Press, FL.
6. Conclusion Bakhshi, M., Mobasher, B., Soranakom, C., 2012. Moisture loss characteristics of cement-
based materials under early-age drying and shrinkage conditions. Constr. Build.
Mater. 30, 413–425.
Monitoring and predicting shield tunnel performance are necessary Bennett, P.J., Kobayashi, Y., Soga, K., et al., 2010. Wireless sensor network for monitoring
to understand the structural responses and implement the effective transport tunnels. Proc. Inst. Civil Eng.-Geotech. Eng. 163, 147–156.
control measures once the performance reaches the limit state. In this Biondini, F., Frangopol, D.M., 2016. Life-cycle performance of deteriorating structural
systems under uncertainty: review. J. Struct. Eng. 142 (9), 1–17, F4016001.
paper, considering the structural features of metro shield tunnels, Box, G.E.P., Jenkins, G.M., 1976. Time Series Analysis: Forecasting and Control. Prentice
horizontal convergence of segmental lining ring is selected as the Hall, Englewood Cliffs.
performance indicator. A parabolic transformation function is built to Box, G.E.P., Jenkins, G.M., Reinsel, G.C., 1994. Time Series Analysis: Forecasting and
Control, third ed. Prentice Hall, Englewood Cliffs.
correlate the convergence ΔD with deformational performance Q. The Chang, C.T., Sun, C.W., Duann, S.W., Hwang, R.N., 2001. Response of a Taipei Rapid
long-term and short-term prediction of the degradation evolution Transit System (TRTS) tunnel to adjacent excavation. Tunn. Undergr. Space Technol.
process is proposed in this paper. Some of the main conclusions are 16 (3), 151–158.
Chen, Y.K., Durango-Cohen, P.L., 2015. Development and field application of a
drawn here: multivariate statistical process control framework for health-monitoring of
transportation infrastructure. Transport. Res. Part B-Methodol. 81, 78–102.
(1) On the basis of the measured convergence dataset (a matrix of DGJ08-11-99, 1999. Shanghai Foundation Design Code (DGJ08-11-99). Shanghai
Construction Committee, Shanghai.
45 × 12 sample points) of the shield tunnel for Shanghai Metro
Elliott, G., Rothenberg, T.J., Stock, J.H., 1996. Efficient tests for an autoregressive unit
Line 2, a lognormally distributed stochastic process is proposed and root. Econometrica. 64 (4), 813–836.
fairly well validated for the prediction of degradation evolution of Frangopol, D.M., 2011. Life-cycle performance, management, and optimisation of
structural systems under uncertainty: accomplishments and challenges. Struct.
deformational performance Q on the long term. From the prediction
Infrastruct. Eng. 7 (6), 389–413.
model, it is calculated that the probability of tunnel deformational Frangopol, D.M., Soliman, M., 2016. Life-cycle of structural systems: recent achievements
performance less than 95% (i.e., the serviceability limit of deforma- and future directions. Struct. Infrastruct. Eng. 12 (1), 1–20.
tional performance) after 10-year operation is equal to 0.7, and the Frangopol, D.M., Strauss, A., Kim, S., 2008. Bridgereliability assessment based on
monitoring. J. Bridge Eng. 13, 258–270.
performance less than 75% (i.e., the ultimate limit state of GB50157-2013, 2013. Code for Design of Metro. Ministry of Housing and Urban-rural
deformational performance) after 50-year operation is about 0.036. Development (MOHURD), PRC Beijing, China.
(2) In addition, an autoregressive integrated moving average (ARIMA) Ghosn, M., Dueñas-Osorio, L., Frangopol, D.M., McAllister, T.P., Bocchini, P., Manuel, L.,
Ellingwood, B.R., Arangio, S., Bontempi, F., Shah, M., Akiyama, M., Biondini, F.,
model is developed for more precise short-term prediction of the Hernandez, S., Tsiatas, G., 2016. Performance indicators for structural systems and
mean of deformational performance. Based on analysis of the same
118
H.-w. Huang et al. Tunnelling and Underground Space Technology 67 (2017) 107–119
infrastructure networks. J. Struct. Eng. 142, F4016003. operation of infrastructure systems under certainty: review. J. Struct. Eng. 142 (9),
Gideon, S., 1978. Estimating the dimension of a model. Ann. Stat. 6 (2), 461–464. 1–16, F4016004.
Gu, L.J., 2011. Study on deformation controlling standard of shield tunnel in soft clay Shen, S.L., Horpibulsuk, S., Liao, S.M., Peng, F.L., 2009. Analysis of the behavior of tunnel
considering the effects of Erection Errors. Master Thesis. Tongji University, Shanghai. lining caused by rolling correction operation. Tunn. Undergr. Space Technol. 24 (1),
Hamburger, R.O., Foutch, D.A., Cornell, C.A., 2003. Translating research to practice: 84–95.
FEMA/SAC performance-based design procedures. Earthquake Spectra 19 (2), Shibata, R., 1976. Selection of the order of an autoregressive model by Akaike’s
255–267. information criterion. Biometrika 63 (1), 117–126.
Hu, X.Y., Zhang, Z.X., Teng, L., 2009. An analytical method for internal forces in shield- STB/ZH-000001-2010, 2010. Technical Guidance for Shanghai Rail Transit Projects.
driven tunnel. Tunn. Undergr. Space Technol. 24, 675–688. Shanghai Shentong Metro Group Co., LTD.
Huang, H.W., Shao, H., Zhang, D.M., et al., 2017. Deformational responses of operated Stewart, M.G., 2004. Spatial variability of pitting corrosion and its influence on structural
shield tunnel to extreme surcharge: a case study. Struct. Infrastruct. Eng. 13 (3), fragility and reliability of RC beams in flexure. Struct. Saf. 26 (4), 453–470.
345–360. Strauss, A., Frangopol, D.M., Kim, S., 2008. Use of monitoring extreme data for the
Huang, H.W., Zhang, D.M., 2016. Resilience analysis of shield tunnel lining under performance prediction of structures: Bayesian updating. Eng. Struct. 30, 3654–3666.
extreme surcharge: characterization and field application. Tunn. Undergr. Space Tan, J., Cui, Z.D., Yuan, L., 2016. Study on the long-term settlement of subway tunnels
Technol. 51, 301–312. induced by multiline tunneling in Shanghai soft soil area. Comput. Geotech. 34 (5),
Huang, X.P., Yang, X.A., Lei, Z.Y., Zhu, Y., 2009. Research on convergent deformation of 486–492.
the existing metro tunnel. Urban Mass Transit. 3, 55–58. Wang, R.L., 2009. Analysis of influence factors and deformation behaviors for subway
Jin, W.L., Zhao, Y.X., 2002. Durability of concrete structures. Science Press, Beijing. tunnel deformation in shanghai soft ground. Undergr. Eng. Tunnels 1, 1–6 (in
Kobayashi, K., Kaito, K., Kazumi, K., 2015. Deterioration forecasting of joint members Chinese).
based on long-term monitoring data. EURO J. Transport. Logist. 4 (1), 5–30. Wang, R.L., Zhang, D.M., 2013. Mechanism of transverse deformation and assessment
Li, Y., Emeriault, F., Kastner, R., Zhang, Z.X., 2009. Stability analysis of large slurry index for shield tunnels in soft clay under surface surcharge. Chinese J. Geotech. Eng.
shield-driven tunnel in soft clay. Tunn. Undergr. Space Technol. 24, 472–481. 35 (6), 1092–1101 (in Chinese).
Liao, S.M., Liu, J.H., Wang, R.L., et al., 2009. Shield tunneling and environment White, Halbert, 1980. A heteroskedasticity-consistent covariance matrix estimator and a
protection in Shanghai soft ground. Tunn. Undergr. Space Technol. 24 (4), 454–465. direct test for heteroskedasticity. Econometrica. 48 (4), 817–838.
Liu, L., Luan, R.S., Yin, F., et al., 2015. Predicting the incidence of hand, foot and mouth Xu, B., Wang, H.L., Xia, C.C., 2010. Study on comprehensive evaluation of shield tunnel
disease in Sichuan province, China using the ARIMA model. Epidemiol. Infect. 144, structural defections. Chinese J. Undergr. Space Eng. 6 (1), 201–207.
144–151. Ye, Y.D., 2007. Research on deformation and method of health diagnose of operational
Liu, S.G., Yu, H.F., Jiang, D.H., et al., 2012. Service life prediction method of concrete subway structures in soft soil. Doctorial Thesis. Tongji University, Shanghai.
segments of shield tunnel. Concrete 7, 108–113. Yin, Z.Y., Karstunen, M., Chang, C.S., et al., 2011. Modeling time-dependent behaviour of
Liu, X., Bai, Y., Yuan, Y., Herbert, A.M., 2016. Experimental investigation of the ultimate soft sensitive clay. J. Geotech. Geoenviron. Eng. 137 (11), 1103–1113.
bearing capacity of continuously jointed segmental tunnel linings. Struct. Infrastruct. Yuan, Y., Bai, Y., Liu, J.H., 2012. Assessment service state of tunnel structure. Tunn.
Eng. 12 (10), 1364–1379. Undergr. Space Technol. 27, 72–85.
Ramos, P., Santos, N., Rebelo, R., 2015. Performance of state space and ARIMA models for Zhang, D.M., Pierre-Yves, H., Huang, H.W., 2003. Time-dependent stress-strain behaviour
consumer retail sales forecasting. Robotics Comput.-Integr. Manuf. 34, 151–163. of natural soft clay. International symposium on Deformation Characteristics of
Richards, J.A., 1998. Inspection, maintenance and repair of tunnels: international lessons Geomaterials. Lyon, France.
and practice. Tunn. Undergr. Space Technol. 13 (4), 369–375. Zhang, Z.G., Huang, M.S., 2014. Geotechnical influence on existing subway tunnels
Sánchez-Silva, M., Frangopol, D.M., Padgett, J., Soliman, M., 2016. Maintenance and induced by multiline tunneling in Shanghai soft soil. Comput. Geotech. 56, 121–132.
119