You are on page 1of 1

ANNEXURE-I

Project: Construction of PAIRA Bridge over the River of Paira, Bangladesh

Summary of Pile load Carrying Capacity in tons for different length at main bridge piers P-17,
P-18 and P-19, considering Zero End Bearing.

Allowable Allowable Depth of


Length of
Skin Vertical Fixity
Pile (m) RL of
Sr. Pier RL of Friction Capacity below RL of
from Lowest
No Nos Bore Hole in (T) (T) bed Fixity (m)
bottom Pile Bed Level
Level
Cap
(m)
100 2423 2423
110 2751 2751
120 3143 3143 44.09
1 P-17 (-)2.935 (-)47.025
125 3338 3338
130 3533 3533

100 2088 2088

110 2479 2479

2 P-18 120 (-)18.227 2869 2869 33.29 (-)51.517

125 (-)38.917 3065 3065

130 32604 32604

100 2248 2248

110 2567 2567

3 P-19 120 (-)0.327 2925 2925 47.0 (-)47.327

125 3105 3105

130 3284 3284

You might also like