1. The daily report summarizes work progress on the Early Loading System project for PT. BAMA contractor on August 19, 2014.
2. Work during the week included continuing walkway construction, electrical packing, and mounting motor plates. Equipment used included excavators, cutting tools, cranes, webbing, welding equipment, and vehicles.
3. The report lists project personnel, weather conditions, potential work obstacles, and plans for the following day's work.
1. The daily report summarizes work progress on the Early Loading System project for PT. BAMA contractor on August 19, 2014.
2. Work during the week included continuing walkway construction, electrical packing, and mounting motor plates. Equipment used included excavators, cutting tools, cranes, webbing, welding equipment, and vehicles.
3. The report lists project personnel, weather conditions, potential work obstacles, and plans for the following day's work.
1. The daily report summarizes work progress on the Early Loading System project for PT. BAMA contractor on August 19, 2014.
2. Work during the week included continuing walkway construction, electrical packing, and mounting motor plates. Equipment used included excavators, cutting tools, cranes, webbing, welding equipment, and vehicles.
3. The report lists project personnel, weather conditions, potential work obstacles, and plans for the following day's work.
JENIS PEKERJAAN No PERALATAN KERJA Keterangan an VolumeHarian VolumeKomulatif lah Uan ak 1 Setting tower & bracing - 1 Excavator 1 Unit Komatsu 200 2 AlatPotongApi 2 Unit 3 Crane 1 Unit Sumitomo 108 RH 2 Kelanjutan Cat Walkway - 4 Webbing 2 Unit 5 Travo Las 1 Unit 6 Pick Up LV 12 1 Unit 7 Bus 03 1 Unit 3 Packing Walkway 8 Genset 1 Unit 9 Unit 10 Unit 4 Packing Electrikal 11 Unit 12 Unit 13 Unit 5 Pasang plat dudukan motor - - 14 Unit 15 Pcs 16 Unit 6 Cat Tower & bracing - - 17 Pcs 7
No MASALAH ( HSE ) Cuaca (v)
No PERSONIL ( SDM ) Jumlah Waktu Cerah Hujan 1 Site Manager 1 orang 07 V 2 Administrasi 1 orang 08 V 3 Foreman 1 orang 09 V 4 Fitter 1 orang 10 V 5 Semi Fitter 3 orang 11 V 6 Welder 1 orang 12 v 7 Fitter 2 orang 13 V 8 Operator Excavator & Crane 1 orang 14 V No KENDALA KERJA 9 Driver 1 orang 15 V 1 10 Team Sipil 3 orang 16 V 2 11 17 V 3 12 18 V 4 13 19 V 14 20 V 15 21 V No RENCANA KERJA BESOK 16 17 1 2 3 4 5 6 DAILY REPORT Project Tanggal: Minggu : II
Early Loading System - 19 Agustus 2014
Tabang KONTRAKTOR PT.BAMA DAILY REPORT Project Tanggal: Minggu : II
Early Loading System - 19 Agustus 2014
Tabang KONTRAKTOR PT.BAMA DAILY REPORT Project Tanggal: Minggu : II
Early Loading System - 19 Agustus 2014
Tabang KONTRAKTOR PT.BAMA
Diketahui oleh : Disusun oleh : Disetujui oleh:
Perusahaan PT. BAMA PT. BAMA PT. Guruh Putra Bersama
Nama Totok Budi Setyono Karmawan Jabatan Admin Site Manager Port Manager