You are on page 1of 15

Volume 3 Issue 1 September 2015 ISSN: 2347-1697

International Journal of Informative & Futuristic Research


Design And Detailing Of Counter-Fort
Retaining Walls For Construction Site
Paper ID IJIFR/ V3/ E1/ 011 Page No. 61-75 Civil
Subject Area
Engineering
Key Words Retaining Wall, Counter-Fort, Base Pressure, Active Earth Pressure, Passive
Earth Pressure

M.E. (Structure) Student,


Department Of Civil Engineering
Rupa B. Patil 1
Rajarshi Shahu College of Engineering
Tathawade, Pune-Maharashtra, India
Assistant Professor
Department Of Civil Engineering
G. R. Patil 2
Rajarshi Shahu College of Engineering
Tathawade, Pune-Maharashtra, India

Abstract
A retaining wall is a structure designed and constructed to resist the lateral pressure
of soil when there is a desired change in ground elevation that exceeds the angle of
repose of the soil. The most important consideration in proper design and installation
of retaining walls is to recognize and counteract the tendency of the retained
material to move down slope due to gravity. This creates lateral earth pressure
behind the wall which depends on the angle of internal friction () and the cohesive
strength (c) of the retained material, as well as the direction and magnitude of
movement the retaining structure undergoes. In many cases we have to come across
the retaining wall of 7m, 8m, 9m height. So we will consider these heights for non-
cohesive soil conditions for different spacing of counter-forts. We studied, by
changing the spacing of counter-forts what will be the change in thickness of stem as
well as heel slab, what is the optimum spacing of the counter-forts, what is the effect
of changing spacing of counter-forts on bending moments, and plotted a graph of
optimum spacing of counter-forts vs height of wall. The data presented here in
following sections clearly indicates that changing spacing of counter-forts for
retaining wall results in, reduction of spacing of counter forts will result in reduction
in bending moments in heel slab and stem wall, reduction of spacing of counter forts
will result in reduction in thickness of heel slab and stem wall. It is also observed that
for 1m, 1.5m, 2m, 3m, 3.5m, 4m spacing of counter-forts the concrete and steel
quantities per meter length of retaining wall is more than at 2.5m spacing. So
optimum spacing of counter-forts for 7m, 8m, 9m height retaining wall is observed to
be 2.5m.

www.ijifr.com
Published Online On: 11/09/2015 61
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

1. Introduction
1.1 General
A soil mass is stable when the slope of the surface of the soil mass is flatter than the safe slope. At
some locations where the space is limited, it is not possible to provide flat slope and the soil is to be
retained at a slope steeper than the surface one. In such cases, a retaining structure is required to
provide lateral support to the soil mass. Retaining walls are relatively rigid walls used for
supporting the soil mass laterally so that the soil can be retained at different levels on the two sides.
Generally, the soil masses are vertical or nearly vertical behind the retaining structure. Thus, a
retaining wall maintains the soil at different elevations on its either side. In the absence of a
retaining wall, the soil on the higher side would have a tendency to slide and may not remain stable.
As the supply of level building sites diminishes, the need to create level building plat forms for
industrial construction sites will increase. Also, on many developed sites there is often a need to
level the front and/or back yards to fully utilize the space for carports, gardens, and other industrial
requirements. Thus, our paper is been cleared with the design of a counter fort retaining wall to
such industrial boundaries. In many cases we have to come across the retaining wall of height 7m,
8m, 9m height. So we will consider these heights for different soil conditions for different spacing
of counter forts.
1.2 Counter-Fort Retaining Wall:
Counter fort walls are cantilever walls strengthened with counter forts monolithic with the back of
the wall slab and base slab. The counter-forts act as tension stiffeners and connect the wall slab and
the base to reduce the bending and shearing stresses. To reduce the bending moments in vertical
walls of great height, counter forts are used, spaced at distances from each other equal to or slightly
larger than one-half of the height Counter forts are used for high walls with heights greater than 8 to
12 m.
1.3 Objectives of the study:
After having literature review and having on field experience it found necessary to study by
changing the spacing of counter-forts what will be the change in thickness of stem as well as heel
slab, what is the optimum spacing of the counter-forts, what is the effect of changing spacing of
counter-forts on bending moments, and plotted a graph of optimum spacing of counter-forts vs
height of wall for 7m, 8m ,9m height retaining walls. In the proposed investigation we are going to
design counter fort retaining walls of height 7m, 8m ,9m for the spacing of counter forts from 1m to
4m for non-cohesive soil condition and soil bearing capacity 25T/Sq.m. And we are going to study
the variation of bending moment in stem wall and heel slab for the different spacing of counter
forts. This study will provide the ready reference to consultants as well as students for basic size
and bending moments for the specified heights and soil conditions.

2. Modelling And Analysis Of Retaining Wall


2.1 Problem Description:
In many cases we have to come across the retaining wall of 7m, 8m, 9m height. So we will consider
these heights for non-cohesive soil conditions for different spacing of counter forts.
By changing the spacing of counter-forts what will be the change in thickness of stem as
well as heel slab.
To study the optimum spacing of the counter-forts.
To prepare a graph of spacing of counter-forts vs bending moments
To prepare a graph of optimum spacing of counter-forts vs height of wall

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 62
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

2.2 Analysis of counter-fort retaining wall by using excel programme:

Counter fort retaining wall 7 m height


Height of retaining wall, H = 7m
Grade of concrete, = 25 N/
Grade of steel, = 500 N/
R = 3.32 From design constant sheet
K= 0.46 From design constant sheet
SBC of soil, P = 25 T/
SBC of soil, P = 250 KN/
SBC of soil, P = 0.25 N/
Density of soil, = 0.000018 N/
Density of soil, = 18 KN/
Angle of internal friction, =
= 0.50, 1- = 0.50, 1+ = 1.50
= = 0.334, = 0.111
= 13.89
Minimum depth of foundation required, = = 1.545 m
Depth of foundation provided = 1.5 m
So, over all height of wall = 8.5 m
Unit weight of concrete = 24000 N/
A) Preliminary dimensions of wall component
i) Base width
B=0.6*H = 4.2 m (a)
B=0.7*H = 4.9 m (b)
So, B = 4.9 m (maximum of a and b)
Assume, B = 5.5 m
ii) Toe projection
Toe projection = C*B
C = 1 -( )
W1
C = 0.0981
COUNTER
So, toe projection = C*B = 0.5 m FORT H
Assume, toe projection = 0.75 m W3

iii) Clear spacing of counter-forts (l),


1.5m
l=3.5( )
W2
= 0.389, so ( ) = 0.79 D A
l = 2.7634 m
So, assume clear spacing of counter-forts (l) = 2.5 m
iv) Thickness of base slab
Assumed thickness of base slab = 0.3 m

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 63
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

B) Design of stem wall


h = Height of stem wall = 8.2m
Pressure intensity at base = h( ) = 49.23KN/
Maximum working moment, M = 25.64 KN-m
Factored moment, = 38.46 KN-m, x = 38461068.09 N-mm
Consider 1000 mm (b) width of stem slab.
Effective depth required for balanced section is (d) =

d= = 105.585 mm
Clear cover assumed 35 mm
Diameter of bar used is 16 mm
Assuming an under reinforced section and to provide a suitable thickness to resist shear at base of
stem, adopt an overall thickness of stem wall required = 148.5847322 mm ~ 150 mm constant up to
the top.
Over all depth of section is (D) = 0.15 m
So, effective depth of section is (d) = 99 mm ~ 100 mm
IS:456-2000, clause G-1.1,
The reinforcements in the stem are computed using the relation,
= 0.87 d* +
By solving we get the quadratic equation,
( ) bd + =0
500 - 2500000 + 2210406212 = 0

=
a = 500, 2a = 1000
b = -2500000, so -(b) = 2500000
c = 2210406212, 4ac = 4.42081E+12
-4ac = 1.82919E+12
= 1352474.612
First root = 1147.525388
Second root = 3852.474612
Or second way to calculate area of steel is,

= ( ( ))1000d

= 1148.342806
( > .hence safe. )
.= bD
In % Grade Of Steel
0.12 FE 415 & FE500
0.15 FE 250
= 180
Using 16 mm dia. Bars,

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 64
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

Spacing ( S ) of bars = 175.16 mm


So, provide 16 mm bars at 175 mm C/C
= 1149.388 ( > . hence safe. )
( > . hence safe. )
Distribution bars
Using 10mm dia. Bars,
Spacing ( S ) of bars = 436.508 mm
So, provide 10 mm bars at 300 mm C/C
= 261.905 ( > . Hence safe. )
C) Check for stability of wall
1) Check against over turning
Consider 1m length of retaining wall
Height of stem wall = 8.2 m
Base width (B) = 5.5 m
Heel Projection (b') = 4.6 m
Depth of soil on toe projection (h) = 1.2 m
Toe projection = C*B = 0.75m
Sr. No. Description Of Load Magnitude Of Distance Of C.G. Moment @ A
Load In (KN) From `A' In (M) In (KN-M)
1 Weight of stem wall (W1) 29.52 4.675 138.01
2 Weight of base slab (W2) 39.60 2.750 108.90
3 Weight of earth fill over heel 943.00 2.300 2198.90
slab (W3)
Total 1012.12 2415.81
Horizontal earth pressure on the full height of the retaining wall tending to overturn the wall.
= w
= = 0.334
= 216.883 N acting at H/3 from A where, = 2.8333 m
Over turning moment = = 614.502 N-m
Stabilizing moment = = 2415.806 N-m
Factor of safety against overturning = = 3.931
Which is greater than 2, hence ok.
2) Check for sliding
Horizontal earth pressure on the full height of the retaining wall tending to slide the wall.
= w
= 216.883 N
Total force opposing sliding = x W= 0.58 W = 587.03 N
Factor of safety against sliding= = 2.71
Which is greater than 1.5, hence ok?
D) Maximum and Minimum pressure at the base
The distance of point of application of the resultant from point A is,

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 65
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

z= , z = 2.994 m
Eccentricity (e) = z- b/2 = 0.244 m
But, b/6 = 0.917 m
So, e < b/6
Maximum and minimum pressure at the base are given by,
=184.022
H*e =1.708, = 0.311
= ( ) = 241.174 KN/
Maximum intensity of soil pressure at base is less than SBC hence ,safe.
= ( ) = 126.87 KN/
Pressure diagram at the base
c b A
D

241.174 126.87 KN/


225.5867858
KN/ 2
KN/m H'
j
i
E f g

Pressure at line cf at toe projection is = 225.59 KN/

E) Design of toe slab


Moment in toe slab
Sr. No. Description Of Load Magnitude Of Distance Of C.G. Moment @ C
Load In (KN) From `C' In (M) In (Knm)
1 Upward pressure 'cdif ' 169.190 0.375 63.45
2 Upward pressure 'efi ' 5.845 0.45 2.63
Total 66.08
3 Deduct self weight of toe 5.400 0.375 2.03
slab
4 Deduct weight of soil 16.200 0.375 6.08
above toe slab
Total 8.10
Maximum working moment in toe slab = M = 57.98 KN-m
Factored moment = = 86.96 KN-m, x = 86964849.90 N-m
Consider 1000 mm (b) width of toe slab.
Effective depth required for balanced section is (d) =
d= = 158.77 mm
Clear cover assumed 35 mm
Diameter of bar used is 12 mm

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 66
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

Over all depth required =199.77 mm ~ 200 mm


Over all depth of the section assumed is (D) = 0.3 m
Assumed thickness is greater than required hence ,safe
Effective depth of the section is (d) = 253 mm ~ 255 mm
IS:456-2000, clause G-1.1
The reinforcements in the stem are computed using the relation,
= 0.87( ) d[ ]
By solving we get the quadratic equation,
( ) bd + =0

500 - 6375000 + 4997979880 = 0



=
a = 500, 2a = 1000
b = - 6375000, so -(b) = 6375000
c = + 4997979880, 4ac = 9.99596E+12
-4ac = 3.06447E+13
= 5535762.39
First root = 839.238
Second root = 11910.76
Or second way to calculate area of steel is,

= ( ( ))1000d

= 839.689
( > .hence safe. )
.= bD
in % Grade of steel
0.12 FE 415 & FE500
0.15 FE 250
= 360
Using 12 mm dia. Bars,
Spacing ( S ) of bars = 134.744 mm
So, provide 12 mm bars at 130 mm C/C
= 870.33 ( > . hence safe. )
( > . hence safe. )
Distribution bars
Using 10mm dia. Bars,
Spacing ( S ) of bars = 218.254 mm
So, provide 10 mm bars at 200 mm C/C
= 392.857 ( > . hence safe. )
E) Design of heel slab
Consider 1000 mm wide strip of heel slab.
Near end 'A' upward soil pressure = 126.87 KN/

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 67
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

Weight of soil on strip = 147.6 KN/


Self weight of strip = 7.2 KN/
Total downward load on heel slab = 154.8 KN/
Net downward pressure = 27.930 KN/
Spacing of counter fort (l) = 2.5 m
Maximum working moment in heel slab = M =14.54688138 KN-m
Factored moment, = 21.82 KN-m, x = 21820322.07 N-mm
Consider 1000 mm (b) width of stem slab.
Effective depth required for balanced section is (d) =
d= = 79.528 mm
Clear cover assumed 35 mm
Diameter of bar used is 10 mm
Over all depth required = 119.53 mm ~120
Over all depth of the section assumed is (D) = 0.3 m
Assumed thickness is greater than required, hence ,Safe
Effective depth of the section is (d) = 253 mm ~ 255 mm
IS:456-2000, clause G-1.1
The reinforcements in the stem are computed using the relation,
= 0.87( ) d[ ]
By solving we get the quadratic equation,
( ) bd + =0

500 - 6375000 + 1254041498 = 0



=
a = 500, 2a = 1000
b = - 6375000, so -(b) = 6375000
c = 1254041498, 4ac = 2.50808E+12
-4ac = 3.81325E+13
-4ac = 6175155.221
First root, = 199.845
Second root, = 12550.155
Or second way to calculate area of steel is,

= ( ( ))1000d

= 199.95
.= bD
in % Grade of steel
0.12 FE 415 & FE500
0.15 FE 250
= 360
Using 12 mm dia. Bars,
Spacing (S) of bars = 392.96 mm

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 68
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

So, provide 10 mm bars at 200 mm C/C


= 392.857 ( > . hence safe. )
( > . hence safe. )
Distribution bars
Using 10mm dia. Bars,
Spacing ( S ) of bars = 218.254 mm
So, provide 10 mm bars at 200 mm C/C
= 392.857 ( > . hence safe. )
E) Design of counter fort
Thickness provided at the top = 300 mm
Thickness of counter-fort= 300 mm
Centre to centre spacing of counter-fort (l) = 2.5 m
Maximum working moment in counter-fort is,
M=
= = 0.334,
Maximum working moment in counter-fort is, M = 1379.265 KN-m
Factored moment = = 2068.897775 KN-m, x = 2068897775 N-mm
Consider 300 mm (b) width of counter-fort.
Effective depth required for balanced section is (d) =
d= = 1413.837 mm
Clear cover assumed 35 mm
Diameter of bar used is 12 mm
Over all depth required = 1454.837 mm ~1455 mm
Over all depth of the section assumed is (D) = 1.46 m
Assumed thickness is greater than required, hence ,Safe
Effective depth of the section is (d) = 1413 mm ~ 1410 mm
IS:456-2000, clause G-1.1
The reinforcements in the stem are computed using the relation,
= 0.87( ) d* +
By solving we get the quadratic equation,
( ) bd + =0
500 - 10575000 + 35670651289 = 0

=
a = 500, 2a = 1000
b = - 10575000, so -(b) = 10575000
c = 35670651289, 4ac = 7.13413E+13
-4ac = 4.04893E+13
-4ac = 6363122.066
First root = 4211.88
Second root = 16938.12
As per IS:456-2000, clause 26.5.1.1

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 69
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

.=
= 719.1
= 4211.88
( > .hence safe. )
Dia. of bar in mm No. of bars Total area
25 6 2943.75
25 3 1471.875
= 4415.625 ( > . Hence safe. ) .

3 Extract Sheets
Table 3.1 Thickness of stem wall in (m)
Clear spacing of the Thickness of stem wall in
counter-fort (l) in (m) (m)
7m 8m 9m
1.0 0.150 0.150 0.150
1.5 0.150 0.150 0.150
2.0 0.150 0.150 0.150
2.5 0.150 0.175 0.175
3.0 0.175 0.200 0.200
3.5 0.200 0.200 0.225
4.0 0.225 0.225 0.300

Table 3.2 Thickness of base slab in (m)


Clear spacing of the
counter-fort (l) in (m) Thickness of base slab in (m)
7m 8m 9m
1.0 0.15 0.15 0.15
1.5 0.15 0.15 0.15
2.0 0.15 0.15 0.15
2.5 0.20 0.30 0.35
3.0 0.25 0.35 0.45
3.5 0.30 0.40 0.45
4.0 0.30 0.40 0.50

Table 3.3 Thickness of counter-fort in (m)


Clear spacing of the Thickness of the counter forts
counter forts (l) in (m) in (m)
7M 8M 9M
1.0 0.3 0.3 0.3
1.5 0.3 0.3 0.3
2.0 0.3 0.3 0.3
2.5 0.3 0.4 0.4
3.0 0.4 0.4 0.4
3.5 0.4 0.4 0.5
4.0 0.5 0.5 0.5

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 70
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

Table 3.4: Concrete quantity in Cu.m per meter length


Spacing of counter Concrete qty. in Cu.m per meter
forts in meter length
7m 8m 9m
1.0 9.4 10.41 12.50
1.5 7.5 8.50 10.25
2.0 6.6 7.60 9.00
2.5 5.7 7.30 8.80
3.0 5.8 7.40 8.90
3.5 6.4 7.40 9.70
4.0 6.4 7.30 9.50

Table 3.5 Steel quantity in Cu.m per meter length


Spacing of Counter forts in Steel qty. In Kg per meter
meter length
7m 8m 9m
1.0 795 801 806
1.5 736 746 756
2.0 707 732 757
2.5 750 730 755
3.0 773 780 790
3.5 801 800 818
4.0 817 825 830

4 Results And Discussion

4.1 Thickness of stem wall in m vs clear spacing of counter-fort in m


0.35

0.3
Thickness of stem wall in (m)

0.25

0.2
7M

0.15 8M
9M
0.1

0.05

0
1 1.5 2 2.5 3 3.5 4
Clear spacing of the counter-fort(l) in (m)
Figure 1- Thickness of stem wall in m vs clear spacing of counter-fort in m

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 71
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

4.2 Thickness of base slab in m vs clear spacing of counter-fort in m

0.6

0.5 THICKNESS OF
Thickness of base slab in (m)

BASE SLAB IN
(m) 7M
0.4

THICKNESS OF
0.3 BASE SLAB IN
(m) 8M

0.2
THICKNESS OF
BASE SLAB IN
0.1 (m) 9M

0
1 1.5 2 2.5 3 3.5 4
Spacing of counter-forts in (m)
Figure 2- Thickness of base slab in m vs clear spacing of counter-fort in m

4.3 Thickness of counter-fort in (m) vs clear spacing of counter-fort in m

0.6

0.5
Thickness of the counter forts in (m)

Thickness of the
counter forts in
0.4 (m) for 7M

0.3
Thickness of the
counter forts in
0.2 (m) for 8M

0.1
Thickness of the
counter forts in
0.0 (m) for 9M
1.0 1.5 2.0 2.5 3.0 3.5 4.0
Clear spacing of the counter forts (l) in (m)

` Figure 3- Thickness of counter-fort in m vs clear spacing of counter-fort in m

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 72
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

4.4 Concrete quantity in Cu.m per meter length vs clear spacing of counter-fort in m -

35
Concrete quantity in Cu.m per meter length

30 CONCRETE QTY. IN
CU.m PER METER
25 LENGTH 9M

20
CONCRETE QTY. IN
CU.m PER METER
15
LENGTH 8M

10
CONCRETE QTY. IN
5 CU.m PER METER
LENGTH 7M
0
1 1.5 2 2.5 3 3.5 4
Spacing of Counter forts in meter

Figure 4: Concrete quantity in Cu.m per meter length vs clear spacing of counter-fort in m

4.5 Steel quantity in Cu.m per meter length vs clear spacing of counter-fort in m
840
Steel qty. in Kg per meter length

820
800
780
760
740 7m
8m
720
9m
700
680
660
640
1 1.5 2 2.5 3 3.5 4
Spacing of counter forts in meter
Figure 5- Steel quantity in Cu.m per meter length vs clear spacing of counter-fort in m

5 Conclusion
I. Thus the data presented here in above sections clearly indicates that changing spacing of
counter-forts for retaining wall results in,
II. From extract sheet it is observed that for 7m height retaining wall bending moment in stem
wall increases from 4.1 KN-m for 1m c/c spacing of counter-forts to 65.64 KN-m for 4m

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 73
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

c/c spacing of counter-forts. Also bending moment in heel slab increases from 2.3 KN-m
for 1m c/c spacing of counter-forts to 37 KN-m for 4m c/c spacing of counter-forts.
III. For 8m height retaining wall bending moment in stem wall increases from 4.60 KN-m for
1m c/c spacing of counter-forts to 80.05 KN-m for 4m c/c spacing of counter-forts. Also
bending moment in heel slab increases from 3.50 KN-m for 1m c/c spacing of counter-forts
to 55.00 KN-m for 4m c/c spacing of counter-forts.
IV. For 9m height retaining wall bending moment in stem wall increases from 5.00 KN-m for
1m c/c spacing of counter-forts to 80.05 KN-m for 4m c/c spacing of counter-forts. Also
bending moment in heel slab increases from 3.60 KN-m for 1m c/c spacing of counter-forts
to 56.80 KN-m for 4m c/c spacing of counter-forts.
V. From graph 4.1 it is observed that for 7m, 8m, and 9m height of retaining walls for 1m,
1.5m and 2.0m spacing of counter-forts the thickness of stem wall required is minimum
thickness 150mm. As the spacing of counter-forts increases the thickness of stem wall
increases to 175mm to 300 mm for 3.0m 3.5m and 4.0m spacing of counter-forts.
VI. From graph 4.2 it is observed that for 7m, 8m, and 9m height of retaining walls for 1m,
1.5m and 2.0m spacing of counter-forts the thickness of stem wall required is minimum
thickness 150mm. As the spacing of counter-forts increases the thickness of stem wall
increases to 175mm for 3.0m spacing 200mm for 3.5m spacing and 300mm for 4.0m
spacing of counter-forts.
VII. It is also observed that for 1m,1.5m, 2m, spacing of counter-forts the no. of counter-forts
are more for the same length of retaining wall due to which concrete and steel quantities are
more than it is for 2.5m spacing of counter-forts. For 3m, 3.5m, 4m spacing of counter-forts
the basic dimensions and steel requirements are more due to which concrete and steel
quantities per meter length of retaining wall is more than at 2.5m spacing. So 2.5m. clear
spacing is the optimum spacing of counter-fort for 7m, 8m, and 9m height of retaining wall
VIII. (5) From graph 4.3 it is observed that for 7m, 8m, and 9m height of retaining walls for 1m,
1.5m and 2.0m spacing of counter-forts the thickness of counter-fort required is 300mm. As
the spacing of counter-forts increases the thickness of counter-fort increases to 500mm.
IX. From table 4.6 it is observed that for 7m height of retaining wall if tapered section of stem
wall is provided then we can save concrete quantity up to 1.5 to 2.5 Cu.m per meter length
of retaining wall. Similarly this is true for 8m and 9m height of retaining walls.

6 References
[1] Kenny Luu1, Ken ONeil2, Weimin Deng3, Design of the Counterfort Retaining Wall on the
Barangaroo Headland Park Project, Sydney.
[2] M. Ghazavi and V. Salvati, Sensitivity analysis and design of reinforced concrete cantilever
retaining walls using bacterial foraging optimization algorithm.
[3] Patil S. M. Wagh and Prof. K. S. Wagh, Reduction in construction material:effect of the provision
of the loft behind the cantilever retaining wall
[4] J. Khana and M. Sikderb,Design basis and economic aspects of different types of retaining walls.
[5] S.N. Moghaddas Tafreshi and T. Nouri, Seismic stability of reinforced retaining wall.
[6] .Lohith Reddy, Y.Naga Harish and K.N.S Pavan Kumar Varma Analysis and design of retaining
wall of Ganges valley school
[7] Siripuram Anusha, R.Sabitharaj and M. Balakoteshwari Design of retaining wall for a minor
bridge.
[8] Dr. B.C. Punmia, Ashok Kumar Jain and Arun Kumar Jain (2007.) Limit State design of
reinforced concrete Laxmi Publications (P) LTD, New Delhi.
[9] Gopal Ranjan, and Rao, A.S.R. (2000). Basic and Applied Soil Mechanics, 2 nd Edition, New Age
International (P) Ltd. Publishers, New Delhi

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 74
ISSN: 2347-1697
International Journal of Informative & Futuristic Research (IJIFR)
Volume - 3, Issue - 1, September 2015
25th Edition, Page No.:61-75

[10] IS 456:2000 COP Plain And Reinforced Concrete.


[11] K.R. Aror (2003). Soil Mechanics and Foundation Engineering, 6th Edition, Standard Publishers
Distributors, Delhi.
[12] Basudhar, P.K., and Madhav, M.R. (1980), Simplified Passive Earth Pressure Analysis Journal of
Geotechnical Engineering Division, ASCE, April, GT4, 470-474.
[13] Choudhury, D. and Singh, S. (2006)a; "New approach for estimation of static and seismic active
earth pressure", Geotechnical and Geological Engineering, Springer, Netherlands, 24(1), 117-127
[14] Das, B.M. (2002). Principles of Geotechnical Engineering, 5th Edition, Thomson Brooks/Cole.
[15]Murthy, V.N.S. (2002). Principles of Soil Mechanics and Foundation Engineering, 5th Edition, UBS
Publishers Distributors Ltd., New Delhi

Rupa B. Patil, G. R. Patil:: Design And Detailing Of Counter-Fort Retaining


Walls For Construction Site 75

You might also like