ABSTRACT
G.O.Ms.No.22 . Dated:23-02-2015.
2. In the reference 2nd read above, the orders so issued in the reference
1 cited were kept in abeyance. The orders issued in the reference 2nd read
st
ii. Distributory work shall be deleted from the scope of the contractor
and executed separately, whenever a new agreement is signed in
pursuance of these orders, if the tender premium is not agreed on
the distributory network rates as per Memo.No.34843/Reforms/A1/
2006, dated:04.01.2010.
iii. As and when extra structures needed as well for extra quantities,
beyond the original scope of work, the EPC Code shall be followed.
P.T.O.,
:: 2 ::
vii. Any other issues arising shall be examined by State Level Standing
Committee and High Power Committee for resolution.
viii. The State Level Standing Committee and Internal Bench Mark
Committee shall make recommendations for all the works based on
the above guidelines. The High Power Committee headed by Chief
Secretary and Committees of Secretaries in accordance with
G.O.Ms.No.121, I&CAD(PW:COD) Department, dated:15.10.2004
shall examine the proposals for resumption of works along with
financial implications and make suitable recommendations to
Government in Irrigation Department for taking decision and issue
orders on the same.
//FORWARDED :: BY ORDER//
SECTION OFFICER.