PROJECT SCHEDULE OF ACTIVITIES

(in weeks)

This appended document presents the system project schedule of activities divided into f
will be completed in 40 weeks. This chart is based on the RAD methodolog

Planning Phase
Activities 1 2 3 4 5 6 7 8 9###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

A Conduct Interview
B Summarize Interview Results
C Prepare Data Flow Diagram
Analysis Phase
D Prepare ER-D
E Prepare Data Dictionary
F Work on Database Design
Design Phase
G Prepare System Proposal Functionalities
H Design System Prototype
I Proposal Presentation
J Revisions
Implementation Phase
K Coding
L Unit Testing
M System Testing
N System Presentation

Legend: Completed Activities


Uncompleted Activities
S

vities divided into four (4) phases and


e RAD methodology.

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
PERT TABLE
Forward Passing Backward Passing
ACTIVITIES PRED a m b ET ES EF LS LF
A NONE 2 3 4 3 0 3 0 3
B A 2 3 4 3 3 6 3 6
C B 2 3 4 3 6 9 6 9
D B 2 3 4 3 6 9 6 9
E C,D 2 2 2 2 9 11 9 11
F E 1 2 3 2 11 13 12 14
G E 1 3 5 3 11 14 11 14
H F,G 2 4 6 4 14 18 14 18
I H 1 1 1 1 18 19 18 19
J I 1 1 1 1 19 20 19 20
K J 10 16 22 16 20 36 20 36
L J 10 16 22 16 20 36 20 36
M K,L 2 3 4 3 36 39 36 39
N M 1 1 1 1 39 40 39 40

Formula: 6ET=a+4m+b
SLACK
0 0 =LS-ES
0 0 =LF-EF
0 0
0 0
0 0
1 1
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
Cod Predecess
e or
a m b ET ES LS EF
A NONE 3 6 15
B NONE 2 5 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E, F 1 4 7
I G 4 19 28
J H, I 4 4 4
LF SLACK