Shut Down Tasks for February 2017 CCM

Activity Description ( CCM ) Department Remarks

Scale removing from all CCM trenches chamber and cooling


bed IF & CCM Team

Ladle and casting floor cleaning CCM Team


Tundish car nozzle centering block service (Both) CCM Team

Oscilation cam tie with pin changing at ST-2 CCM Team

Checking all air belows CCM Team

Allignment of foot rollers ( both strands ) CCM Team


Alignment of secondary cooling pipes, nozzle cleaning and CCM Team
changing
Checking rollers and bearings of apron CCM Team

withdrawal cooling jackets change at St-1 (Inside) Service CCM Team

withdrawal cooling jackets change at St-2 (Inside) Service CCM Team

Checking and changing bearings, conveyor chains and rollers


at PCRT and DRT CCM Team

Repairing spray pipe at pusher,rollers and cooling bed. CCM Team

Greasing of Complete Machine CCM Team

Scale pit filter cleaning CCM Team

Coloring of CCM at withdrawal and auto cutter CCM Team

House Keeping of all Plant and adjacent area of CCM CCM Team

Secondary Flow meters display at HMI Electrical Dept