1. MATERIAL LIST.
2. BILL OF MATERIAL.
BOM for CAST IRON Alternate BOM-1
CLUTCH MC ASSEMBLY
CMC Machining - Cast iron Plunger Assembly Pushrod Clevis Lock nut
4. ROUTING
Created two production version 001 is for the CAST IRON, Production version 002 is for the
ALUMINIUM.
This 5 steps completes the Master data.
Creating the planned order for Finish Material Clutch, Alternate BOM-2, production version-0002.
Enter the T-code MD11 in command box and press entre.
Entere the order qty, start date and Production plant. Then click on save.
Enter the planned order number and order type (PP01) and press enter, entry option group will be
appear select Group – 50000376, Group counter – 2.
Release the production order and check the availability of the materials. Click on the save.
Enter the Qty to be confirm and select the confirmation type as final confirmation. Then click on
save.
The message will appears as the production order as been confirm and saved.
Give the movement type 101, order – 300554 and loaction SMLF press entre.
click on the save.
Entre the order number 300554 and select the selection for collective orders. Press entre.
In the production order select the Function> Restrict processing> Complete Technically.
So TECO process completes.
This all steps completes the Manual Production Order.
Production Order Print Sample
-----END-----