3. Door system
Door type Remarks
2S: 2-panel side opening
Horizontal
3S: 3-panel side opening These door types have comparatively fast operation.
sliding doors
2CO: 4-panel center opening
Vertical 2U: 2-panel upward opening These door types make it easy to align same-size entrance width and car width.
sliding doors 3U: 3-panel upward opening Note: Not applicable with 2BC operation.
1 2
Car and Entrance Designs Operation System
Signal fixtures such as Car operating panel and Hall position indicator, etc., are shown according to operation system.
The applications vary based on the model, so please confirm when ordering.
E-102 FC-101-2S Finishes and Designs 2-panel side opening Single automatic for freight (1BF) : Standard
Selective collective (2BC) : Optional
Door frame Narrow Jamb with Painted steel sheet Signal fixtures Functions Remarks
Entrance Doors Painted steel sheet
Direction arrow Shows direction during operation.
Extruded hard aluminum (Capacity of
2000kg or less) Position indicator Shows position of elevator.
Entrance Sill
Steel plate with black paint (Over IN-USE indicator Shows elevator is in use. Only 1BF
2000kg capacity)
Push to register call. Invalid while IN-USE
Indicator is incorporated in Hall button Hall position indicator Call button Only 1BF
Hall buttons
unit. indicator is illuminated.
CBM-J31 CBM-C111
3 4
Specifications
Ventilation Diffuser fan automatically shut off to conserve energy.
Entrance Columns (Only Horizontal Sliding Doors) Stainless steel hairline For maintenance or energy-saving measures, a car can be taken out
Hall Out of Service Switch (HOS)
Car Wall Protectors Stainless steel hairline of service temporarily with a key switch mounted in a specified hall.
Appearance
Flooring Checkered steel plate with black paint Necessary wires are provided in the traveling cable.
Capacity of 2000kg or less Extruded hard aluminum
Wiring for BGM Speaker
(Speaker: by owner)
Sill Over 2000kg Capacity Steel plate with black paint Mitsubishi Emergency Landing Device (MELD) Upon power failure, a car equipped with this function
Operational Features
Vertical Sliding Doors Same unit as car flooring automatically moves and stops at the nearest floor using a
Narrow Jamb
Painted steel sheet rechargeable battery, and the doors open to ensure passenger
Door Frame
Stainless steel hairline
safety. (Max. allowable floor-to-floor distance is 10 meters.)
Stainless steel hairline sensors, all cars stop at the nearest floor, and park there with
Entrance
Painted steel sheet the doors open to facilitate safe evacuation of passengers.
Doors
Stainless steel hairline Fire Emergency Return (FER) Upon activation of a key switch or a buildings fire sensors, all
Capacity of 2000kg or less Extruded hard aluminum calls are canceled, all cars immediately return to a specified
Sill Over 2000kg Capacity Steel plate with black paint evacuation floor and the doors open to ensure safe passenger
Vertical Sliding Doors Checkered steel plate with black paint evacuation.
Car Operating Operation by Emergency Power Source Upon power failure, the car uses the buildings emergency
Faceplate Stainless steel hairline
Signals
Panel Auto/Manual (OEPS) power supply to move to a specified floor, where the doors
Hall Position
Indicator
Faceplate Stainless steel hairline
then open to facilitate the safe evacuation of passengers.
After the car has arrived at the floor, normal operation will
The sensitive mechanical door edge detects the operator or be available.
Safety Door Edge (SDE)
goods upon contact during door closing. Supervisory Panel (WP) A panel installed in a buildings supervisory room, etc., which
Ultrasonic Door Sensor (USDS) Sound waves are used to scan a 3D area near the open doors monitors and controls each elevators status and operations
(Only Horizontal Sliding Doors) to detect the operator or goods. by remote, using indicators and switches which are provided
Operational Features
Horizontal Sliding Doors Car side The infrared-light beam (one or two) covers the full width of on request.
5 6
Layout Drawings and Dimensions for One Gate (1D1G)
For JIS Code
Y
Y
BB
60 22 1550 5050 206 154
45 18.5 1250 4850 192.2 144.2
F-2500-2U*4 2500 4000 4400 2U 3600 3700 4500 155.9 80.4
60 22 1550 5050 206 154
45 18.5 1250 4850 192.2 144.2
JJ JJ JJ F-2500-3U*4 4000 4400 3U 3600 3700 3950 155.9 80.4
60 22 1550 5050 206 154
X X X
45 18.5 1250 4850 208 154
F-3000-3S 4100 4800 3S 3750 4100 3300 166.7 92.2
60 26 1800 5050 223 165
45 18.5 1250 4850 208 154
F-3000-2U*4 3000 4100 4800 2U 3750 4100 4500 174.5 92.2
60 26 1800 5050 223 165
45 18.5 1250 4850 208 154
F-3000-3U*4 4100 4800 3U 3750 X 4100 3950 174.5 92.2
Machine Room Plan Hoistway Section 60 26 1800 5050 223 165
*1: Since required motor power varies according to the specifications, such as elevator cage weight, etc., please consult our sales agency for details.
Min. clear
*2: Since reaction load varies according to the specifications, please consult our sales agency for details.
machine
height
room
*3: In cases where capacity exceeds 3000kg, please consult our sales agency for details.
Cinder concrete
finish (by owner) *4: 2U, 3U door type can not be applied for EN-81-1 or GB code.
Ventilating fan (by owner)
100
Overhead OH
R1
R2
Y
BM
Control
panel
Access door
Min. floor height
Entrance height HH
W1200XH2000
Ventilation
hole (by owner)
X
AM
Pit depth
PD
7 8
Layout Drawings and Dimensions for Two Gates (1D2G & 2D2G)
For JIS Code
Y
Y
BB
60 22 1550 5050 219 168
BB
*1: Since required motor power varies according to the specifications, such as elevator cage weight, etc., please consult our sales agency for details.
*2: Since reaction load varies according to the specifications, please consult our sales agency for details.
*3: In cases where capacity exceeds 3000kg, please consult our sales agency for details.
Min. clear
machine
height
room
Cinder concrete *4: 2U, 3U door type can not be applied for EN-81-1 or GB code.
Ventilating fan (by owner) finish (by owner)
100
Overhead
OH
R1
Y
BM
R2
Max. Travel 30m
Min. floor height
Control
panel
Entrance height HH
Access door
W1200H2000
Ventilation
hole (by owner)
X
Pit depth
AM
PD
9 10
Entrance Layouts
70
30
132
Entrance height HH
137
135
thickness 28
Jamb depth JD
Wall
(100)
70
100
Finish
Entrance width JJ
150
100
Entrance height HH
30
200
60
132
137
135 200
28
thickness
Jamb depth JD
135 30
(50 or 100)
Wall
100 150
Finish
Entrance width JJ
60
100 200 2-panel upward opening door
200
(2U)
It can not be applied for EN-81-1 or GB code.
135 30
Sill width
140 *1
30 *1
Entrance height HH
140 *1
Jamb depth JD
(100)
Entrance width JJ 100
3-panel side opening door 100 200
(3S)
60
140 *1 30 *1
70
30
Entrance height HH
175
Sill width
200 *1
Jamb depth JD
60
(100)
Wall
Entrance height HH
100
Finish
Entrance width JJ
200 *1
150
100 200
60
Jamb depth JD
240
(100)
Entrance width JJ 100
100 200
175 30
60
*1: Since dimensions for vertical sliding doors vary according to the entrance width, entrance height 60
and floor height, please consult our sales agency for details.
200 *1
11 12
Electrical Installation Important Information on Elevator Planning
13 14
Eco Changes is the Mitsubishi Electric Groups environmental statement,
and expresses the Groups stance on environmental management.
Through a wide range of businesses, we are helping contribute to the
realization of a sustainable society.