This document provides details of a test package for the Kuantan Resin Plant project in Malaysia. It lists Jacobs Engineering as the EPCM and Eastman Chemical as the client. The test package covers drawings, quality plans, inspection reports for civil and steel works, testing reports, snag lists, and as-built drawings for the Kuantan Resin Plant project in Malaysia.
This document provides details of a test package for the Kuantan Resin Plant project in Malaysia. It lists Jacobs Engineering as the EPCM and Eastman Chemical as the client. The test package covers drawings, quality plans, inspection reports for civil and steel works, testing reports, snag lists, and as-built drawings for the Kuantan Resin Plant project in Malaysia.
This document provides details of a test package for the Kuantan Resin Plant project in Malaysia. It lists Jacobs Engineering as the EPCM and Eastman Chemical as the client. The test package covers drawings, quality plans, inspection reports for civil and steel works, testing reports, snag lists, and as-built drawings for the Kuantan Resin Plant project in Malaysia.
2.0 Drawing 2.1 Plot Plan 2.2 Panji Alam Drawing 2.3 FCSB Shop Drawing
3.0 Quality Plan
3.1 Inspection and Test Plan
4.0 Civil Works
4.1 Material Approval 4.2 Material Receiving Inspection Report 4.3 Inspection Reports
5.0 Steel Works
5.1 Material Approval 5.2 Material Receiving Inspection Report 5.3 Inspection Reports
6.0 Testing Report
6.1 Testing Contractor Approval 6.2 Cube Test Report 6.3 California Bearing Ratio (CBR) Test Report 6.4 Field Density Test (FDT) Test Report 6.5 Tensile Test Report