NO. 14, JALAN BALAKONG JAYA 4, TAMAN INDUSTRI BALAKONG JAYA, 43300 BALAKONG,
SELANGOR, M'SIA.
TEL : +6016 - 211 4762 FAX : +6016 - 329 0508
CONTRACTOR APPROVAL
REV. NO. PREPARED DATE CHECKED DATE APPROVED STATUS DATE
DOCUMENT NO. :
R&Y/BJM/LPG/2023/006
R&Y ENGINEERING AND CONSTRUCTION SDN. BHD.
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
TABLE OF CONTENTS
- Table Of Contents 2
Method Statement Amendment
- 3
Record
1.0 Introduction 4
3.0 References 4
4.0 Purpose 4
5.0 Responsibility 5
2
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
3
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
1.0 INTRODUCTION
1.1 To outline work method for the complete installation of Carbon Steel Sch
40 pipes and accessories.
2.1 The work shall be applied to complete the installation of the Carbon Steel
Sch 40 pipes and accessories installation with reference to the Energy
Commission requirement and regulation.
2.3 Ensure that the welding works of the pipe are executed in according with
the contractual requirement, applicable engineering codes and standard,
statutory laws, regulation and the approved shop drawings.
3.0 REFERENCES
i. QA/QC preliminary submission of sample / material
4.0 PURPOSE
To ensure that the Carbon Steel Sch 40 pipes and fittings installation is comply to
project specifications and standard.
4
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
5.0 RESPONSIBILITY
All the responsibilities are under R&Y Engineering & Construction Sdn. Bhd.
(Contractor) person in charge
i) Project Manager
Responsible to lead the planning of Piping installation work and
value engineering the best possible Pipe routine.
ii) Project Engineer
Responsible to lead the operation at site and controlling the site
progress.
iii) QA /QC Engineer
To document up the form and procedure
iv) Site Supervisor
To carry out the work and monitor the worker on site
6.0 RESOURCES
5
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
ITEM DESCRIPTION
6.3.1 Safety Shoes
6.3.2 Safety Vest
6.3.3 Safety Harness
6.3.4 Safety Helmet / Welding Mask
6.3.5 Glove
6.3.6 Fire Extinguisher
6.3.7 Basic First Aid Kit
7.1 When materials arrived to site. It will be stored in a clean and dry area for
daily usage. Please view the location of storage at the list of attachment.
The temporarily store will be erected at the location given. Propose location
for storage material at level P5.
7.2 Alternatively, the bulk of materials shall stored at a designated place nearby
to the project site. This is to ascertain that the materials to be easily
available for delivery to site.
8.1 Pipeworks
8.1.1 Mark the pipeline location in the building according to the approved
shop drawings.
8.1.3 When pipeline passes through the building wall, a PVC pipe sleeve
shall be provided. The pipe sleeve provided shall always 1 " NPS
bigger than the pipeline size and shall be of minimum equal length
to the wall thickness. Example for 4” gas pipe to use 6” size for
pipe sleeve. Gap between sleeve and pipe must be filled with fire
proof material.
6
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
8.1.4 For concealed piping inside wall or slab, the pipe shall be wrapped
tape with 50 % overlapping.
8.1.5 For exposed piping, the pipe shall be painted. Only approved paint
shall be used. Pipe inside riser shaft also to be painted.
8.1.6 All pipes shall be cut to length requirement and shall prepare for
welding.
8.2.1 Purpose
8.2.1.1The painting procedure underlines the method statement for
painting of steel pipes that is conducted either at the workshop or
dedicated work area at the site.
8.2.2.3 Surface to be painted must be clean & dry. Clean the pipe
surface by using pressurized water or wipe with wet cotton rag.
Grease, oil rust, scale and dirt must be removed and the pipe
must be dry be paint coatings are applied.
7
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
8.2.3.3 Apply one coat of high gloss paint as finishing coat, yellow in
color, by using a paint brush and allowed to dry.
8.2.3.4 Painted pipe shall be allowed to use only after the paint has
been thoroughly dried.
8.2.4 Labeling
8.2.4.1 After painting has been completed, identify pipeworks with clear
labels as per Client’s Specifications. Labeling should be spray
painted and not sticker.
8.2.4.2 Carry out labeling work with arrows to indicate flow directions.
8.3.2 For partial testing, compressed air will be used for pressure test.
Once all pipe connected, Nitrogen will be used for pressure test.
8.3.3 All outlets shall be plugged off except the pressure inlet point of
pipeline.
8
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
8.3.3.3 Hold the test pressure for 1 hour. If pressure remains, the
line is deemed as gas tight.
8.4 Cleaning
9
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
I. Submission Checklist
II. Carbon Steel Sch 40 pipe installation checklist
9.2 During work progress and final work done shall carried out inspection and
testing to ensure conformance of installation work.
9.3 The project work shall follow the work methodology. The site
representative will carried out the procedures, Inspection Request (IR) will
be forwarded before an inspection to be carried out by consultant’s
representative. The inspection request (IR) shall be enclosed with the
checklist, drawing and submission checklist.
10
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
10.1 All work shall be carried out in accordance to the safety standard required
by the relevant authorities.
10.2 P.P.E shall be worn at all time to avoid any unwanted incidence.
10.4 Any work above ground 1.5m, worker must wear safety harness. Working
platform will be used. Scaffolding will be erected for such purposes.
10.6 All workers shall adhere to safety manual at all the time.
10.7 When work is completed, housekeeping will be required to keep the work
area clean and tidy. Thus to ensure the place is safe.
11.1 General
The purpose of the quality control is to provide a proper guideline for the
Carbon Steel Sch 40 pipe installation such that the following targets will be
attained:-
11
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
ATTACHMENT 1
12
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
ATTACHMENT 2
Undercoat Painting
Pressure Testing
13
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
Appendix A
Inspection Form
14
WORK METHOD STATEMENT
PROJECT: EXTENSION OF LPG PIPING SYSTEM AT MEETSUN , PAVILION BUKIT
JALIL MALL
Work Method Statement For Aboveground Carbon Steel Pipe For Liquefied Petroleum
Gas Reticulation System.
15