THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
1.0 INTRODUCTION
This procedure applies to project site, which requires ABS Cold Water
Pipe installation work, which is carried out by the HJCSB.
3.0 REFERENCES
4.0 PURPOSE
5.0 RESPONSIBILITY
6.0 RESOURCES
Page 2 of 6
THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
Item Description
6.2.1 Measurement
6.2.2 Drill & Drill Bit
6.2.3 Hammer
6.2.4 Hand Saw
6.2.5 Extension Wire
6.2.6 Grinder
6.2.7 Measurement Tape
Item Description
6.3.1 Safety Shoes
6.3.2 Safety Vest
6.3.3 Safety Harness
6.3.4 Safety Helmet
6.3.5 Gloves
6.3.6 Basic First Aid Kit
When materials arrive to site, it will be stored in a clean and dry area. The
bulk of the pipes & fittings will be stored at the Main Plumbing store. For ease
of working smaller amounts will be stored at the place of installation.
8.1.2 Then plumb a line from highest floor till the lowest floor
where the pipe is to be installed. Install the wall bracket to
support pipe
Page 3 of 6
THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
8.2.2 Use drill machine drill the start and end points marked.
Insert 10mm drop-in anchor into drilled points.
8.2.4 Install type ‘A’ hanger with the threaded stud with nut and
washers. When the hangers are ready then slot the pipe
through the hangers.
8.2.5 After slot in the pipes, apply ABS Solvent cement to join the
both pipes and fittings together. Complete the jointing check
the pipe joint is in correct position.
8.2.6 If the piping is require enclosed in the brick wall, that piping
must have pressure test before it plaster back with cement
mortar. After it complete pressure test the final connection
to all the sanitary wares fixtures will carry out the functional
test during commissioning.
8.3.1 Cut the pipe clean and square. Remove internal external burr
and clean out swart.
8.3.2 Abrade the end of the pipe over the length equal to the
socket depth. Clean the abraded surfaces with a clean rag.
Page 4 of 6
THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
i) Submission Checklist
ii) ABS Cold Water Pipe installation work checklist
During work progress and final work done shall carried out inspection and
testing to ensure conformance of installation work.
The project work shall follow the work methodology. Our site representative
will carried out the procedure, a report for inspection request form will be
forwarded 24 hours before an inspection to be carried out by consultant’s
representative. The inspection request form shall be enclosed with the
checklist, drawing and submission checklist.
10.2 Testing inspection will be carried out to ensure no leaking and all
Connection is well joint.
10.3 Plug all the water outlet point and fill up water.
10.4 Using hand pump to increase the pressure in the test pipe at least 1.5
times the working pressure or 7.0 bars, whichever is higher.
10.6 If pressure cannot be sustained, check the pipe for leakage and rectify.
Page 5 of 6
THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
ii) P.P.E shall be worn at all time to avoid any unwanted incidence.
iv) All workers shall adhere to safety HIRADC Form at all time.
12.1 General
Page 6 of 6
THE PROPOSED CONSTRUCTION AMD COMPLETION OF THE COMMERCIAL OFFICE
BUILDINGS AND EXTERNAL WORKS AT LOT 2C5 PRECINCT 2, PUTRAJAYA
Installation Inspection
−−
Pressure Test
Test Fails
Repeat Test
Test Pass
Page 7 of 6