Professional Documents
Culture Documents
K-00 13/03/2017 Bharath Patel Gopakumar Yashwanth Initial Issue for Company Review
OOCEP
Rev Date Prepared by Reviewed by Approved By Description
Approval
1.0 PURPOSE
To specify minimum requirements for Earth Works as specified in the COMPANY Specification.
To describe work sequence and the controls necessary to meet general safety and environmental
standards as minimum requirements.
It shall also act as a guide to construction personnel on how to carry out the works safely and in
accordance with Company Project HSSE & Quality requirement.
Further, the Method Statement also describes the Quality Management and HSSE Management specific
to the activity.
2.0 SCOPE
The scope covers Earth Work and Construction of concrete sleepers & foundations for pipe supports and ,
equipment (Pumps). Modification of existing foundation of stair case / slab to serve the purpose of
construction for Off Loading Facility in GPP. Provision of temporary access to Diesel Tank during extension of
existing stair case.
3.0 REFERECNES
This Method Statement is prepared and issued in accordance with the following Documents.
4.0 ABBREVIATIONS
5.0 EQUIPMENT
Only manual excavation will be permitted
Shovel
Compactor
Water Tanker
Pipe/cable detector
Theodolite Instrument
Leveling Instrument
6.0 SAFETY
Apply Operational PTW for any work associated with the Earth Work at construction work site in GPP.
Restrict unauthorized entry to the worksite.
Installation of proper signboards at site locations
Ensure use of proper PPE as required.
Conduct daily Tool Box Talks before commencing the work.
Work shall be carried out in accordance with the requirements as described in HSSE Plan to ensure: The
site is left clean and tidy at all times.
Combustion emissions are minimized.
All vehicle engines are switched off when not in use and in case of emergency alarm.
Damage to land from the operation of equipment / vehicles is avoided..
Spills & leaks of hydrocarbons are reported immediately to the HSSE Advisor and cleaned up in accordance
with the relevant procedure.
Detailed Level 2 TRA to be conducted
Personnel and equipment shall not come in contact with any live facility.
Ensures that all the persons have required safety training and PPE.
Ensures that approved working methodology is followed at all levels.
Ensures awareness of work force with regards to HSE.
Monitors Progress at site.
Ensures Construction Execution Plan, detailed Method Statement & RA’s are followed as per the
procedure / QCP/ OOCEP Specification.
Allocates adequate labor & plant resources.
Determines plant and equipment to be used for Earth Works, and that such plant/ equipment is in safe
working order and certificated or calibrated as necessary.
Ensures that Method Statements are identified and control measures taken before starting the work.
Ensures that all construction operations are carried out to schedule and in accordance with quality and
safety requirements.
Ensures the filling of all vehicle entry certificates.
Identifies hazards, which have not been identified and ensure that the controls are in place and
forwards to the HSSE Manager for inclusion in the hazard register.
Assesses field activities by conducting onsite audits and site visits to ensure HSE compliance.
Ensures that the personal protective equipment is appropriate for use by the employees with respect to
the specific job hazards.
Interacts with the Construction Manager, Engineers, Supervisors, workers and OOCEP Operations
Team.
Advises the GPS Plant Supervisor regarding noted defects in vehicles, plant/equipment and monitors
the close out of remedial measures.
Advises Site Supervisors/Construction Manager on Occupational health and hygiene issues.
Provides guidance and support during the performance of the Daily Risk Assessment (TBT) Procedure
as and when required.
Continuous availability of safety persons at site to ensure all HSSE procedures/specifications are being
implemented.
Ensures that Company approved PTW system is implemented and being monitored for full compliance.
Functionally responsible to the Project Manager and Project Quality Manager, field day to day activities
reporting to Construction Manager for:
Implementing the Quality systems on site in accordance with Project Quality Plan and Quality Control
Plans and procedures.
Verification of lab test samples and witness tests.
Verification of all calibrated instruments and gauges.
Preparing all pre-construction documentation with respect to Control of all Earth Works.
Liaising with COMPANY QA/QC representative to resolve all QA/QC related problems.
Reviewing site generated daily documentation with QC Inspectors.
Co-ordination of inspection personnel with site inspectors.
7.5 SURVEYOR
8.0 METHODOLOGY
Ensure that the Instruments used for Earth Work operation have been checked, calibrated and certified for
accuracy and a system established for periodic checking of the instruments during site use. The instruments
shall be calibrated once in a year, and calibration certificate for the instruments shall be available at site,
verified by Company HSE.
Before commencement of works, GPS will obtain the required PTW and prepare records including
photographs (taken by only OOCEP authorized person) of the existing state of the site with reference to any
features that may require special care and/or reinstatement and agree with COMPANY site representatives.
Construction Manager shall obtain all necessary data with approval, as “Approved for Construction” required
for the job in hand. Quality Inspector shall ensure the latest drawings, Method Statement and QCPs are
available at work site.
Underground services shall be marked as per the drawing, detected with the help of cable detector,
pipe detector or trial pits and protected prior to taking up earthwork in the area. Position of service shall
be shown on Construction drawing and marked on ground with line paint beyond edge of the
excavation. This shall be covered under OOCEP ground disturbance certificate, approved by authorized
Company person.
During the manual excavation work if an unknown service is detected, stop work and the Civil
Foreman/Engineer shall inform to the client for further instruction.
The Civil Foreman/ supervisor will ensure that all top-soil which contain humus or any organic matter is
stripped away properly from area to be excavated. The top soil shall be manually removed to a minimum
depth of 200 mm or as directed by the company.
8.4 EXCAVATION
8.4.1 GENERAL
PTW shall be raised prior to work commencement . The Civil Superintendent /Engineer shall check the
Project Specification and TRA 2, GDC and drawing to be attached to PTW.
The Civil Foreman/ Engineer shall make sure that over excavation is not carried out and if loose, soft or
unsound ground is encountered, this matter is reported to the Client's representative. Construction of concrete
sleepers, foundations for pipe supports and equipment (Pumps)
Loose soil, bad ground or cavities encountered within any part of the excavations for foundations of
equipment / structures shall be excavated to a solid formation and filled to foundation with mass
concrete (C10) or compacted material in layers as directed by the company.
The civil Foreman /supervisor shall be responsible for the safety of people, equipment, existing
services, nearby buildings, structures etc.
Civil Inspector in conjunction with the Civil Foreman/ Engineer shall arrange to carry out necessary testing as
per the Contract Specification after compaction of each layer. Frequency of testing and degree of
compaction shall be as mentioned in the Contract Specification. Results shall be forwarded to the Client's
representative for approval.
Civil Inspector will inform the Client's representative when the excavations are ready to receive blinding
concrete. The Civil Superintendent shall make sure that formations are checked and approved by Client's
representative prior to the start of concrete work Through RFI submission.
Earth work activities shall be executed in accordance with the requirements of the Quality Control plan ABB-
GEN-QAC-PLN-GPS-16015-00003, and in accordance with this Method Statement. Surveyor/Civil inspector
will maintain quality records of Survey and Set out activity. These records will be in possession of QA/QC
Engineer.
Non-conformance to this Method Statement, Project Specification and Deviation from COMPANY approved
HSE Plans shall be considered as non-conformities. All non-conformities raised by QA/QC personnel
(internal/external authorities) shall be addressed within seven working days. All non-conformities except the
HSE related ones, will be recorded and log shall be maintained in the QA/QC Site Office.
11.0 ATTACHMENTS