SAUDI ARAMCO RAS TANURA REFINERY

CLEAN FUELS PROJECT


(PACKAGE-2-MECH WORKS)

METHOD OF STATEMENT
FOR
TIE-IN NO. 054-077

(EGE-TR-MS-077)
Revision Number 1 Reference EGE-TR-MS-077
Number
Amendment 0 Date 23-Oct-2018
Document Title METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT
054 FOR RASTANURA REFINERY CLEAN FUELS PROJECT

REVIEW & APPROVAL SIGNATURE RECORD BY EGE

ROLE TITLE SIGNATURE DATE

Prepared by Engineering Dept.

Reviewer 1 QA/QC Manager

Reviewer 2 Safety Manager

Approved by Construction Manager

REVIEW & APPROVED BY TR

ROLE TITLE SIGNATURE DATE

Reviewed by Project Engineer

Approved by Construction Manager

RECOD OF REVISION
REVISION DESCRIPTION DATE
0 ISSUED FOR REVIEW & APPROVAL 13-Sep-18
1 ISSUED FOR REVIEW & APPROVAL 23-Oct-18
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

Table of Contents

1.0 SCOPE ..................................................................................................................... 2

2.0 PURPOSE ................................................................................................................. 2

3.0 DEFINITION & ABBREVIATIONS ............................................................................... 2

4.0 RESPONSIBILITIES .................................................................................................... 2

5.0 MANPOWER............................................................................................................ 4

6.0 TOOLS AND EQUIPMENT ......................................................................................... 4

7.0 WORK METHODOLOGY ........................................................................................... 5


7.1 Engineering Preparation........................................................................................................................ 5

7.2 WORK to be executed before Shutdown Time for TIE-IN 054-077 ........................................................... 6

7.3 Work to be executed during the shutdown time for Tie-In Work for 054-077.................................. 10

7.4 Post tie-in Activity ............................................................................................................................. 11

8.0 RFI for Layup & Reinstatement ............................................................................ 11

9.0 SAFETY ACTION PLAN .......................................................................................... 11

10.0 SAFETY INSPECTION ............................................................................................ 12

11.0 APPLICABLE REFERENCES..................................................................................... 12

12.0 APPENDICES ........................................................................................................ 13

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 1 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

1.0 SCOPE

This Method Statement covers the methodology of Tie-In No. 054-077 pipe spool at unit 054 for
Rastanura Refinery Clean Fuel project. The work consists of furnishing of all supervision, labor,
materials, tools and equipment necessary for all Tie-in works.

2.0 PURPOSE

The purpose of this Method Statement is to show the methodology and describe the sequential steps
for execution of Tie-In No. 054-077. It is the intention of this document to ensure that safe practices
are being imposed on the tie-in works considering the protection and safety of personnel & utilities
from hazards that might occur during execution of works.

3.0 DEFINITION & ABBREVIATIONS

TERM DESCRIPTION
A written document that explains the planned execution method
Method Statement to control the work at various stages and to assure quality, and
delivery on time of the work.
Company Saudi Aramco
Contractor TR (Tecnicas Reunidas)
Sub-Contractor EVERGREEN CONTRACTING CO. (EGE)
WPS Welding Procedure Specification
PQR Procedure Qualification Record
ITP Inspection & Test Plan
Work to be performed with piping or equipment out of service,
Cold Tap
depressurized and vented.

4.0 RESPONSIBILITIES

POSITION TITLE ROLE DESCRIPTION OF TASK


Project Manager Coordination & Control Responsible for the over-all direction,
coordination and control of all Tie-In
activities.
Construction Direct management of Implementation and control of construction
Manager activities as planned and scheduled. Over
site construction.
all responsible for on-time completion of
work.
DOCUMENT NO. REVISION PRINT DATE PAGE
EGE-TR-MS-077 1 23-Oct-2018 2 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

Project Project planning, Responsible for the overall planning and


direction of craftsmen activities related to
Engineer implementation
Tie-In works including determining method
and Monitoring of works, manpower levels, and equipment
requirement & work schedule. Monitoring of
all Tie-In work related activities.

Piping Engineer Technical Support, Review and interpretation of Codes,


Standards & Specifications, Technical
Monitoring manuals and drawings. Prepare, develop
and/or update work procedure as required.
Provide technical direction to supervisors
assigned to area of work and craftsmen to
ensure work is completed in proper
sequence.
Piping Supervisor Supervision and Involve in the planning, organizing and
execution of all Tie-In activities. Prepare
Execution
safety and quality action plan that must be
implemented and observed during the Tie-
In installation activities.
Piping Foremen Direct execution of the Responsible for the direct execution at site
work. Instruct working and ensure that the work is performed in
accordance with latest approved Tie-In IFC
personnel. drawing and proper usage of tools and
equipment, wearing of PPE and daily
housekeeping of the work area.
Welding Supervisor Site Supervision Directly in-charge and supervise all welding
work activities. Responsible for the daily
work progress, work quality and safety.

Welding Foremen Take the lead on Directly execute, lead and give instruction to
welders about the assigned work, work
assigned work.
procedure, proper usage of tools and
equipment, wearing of PPE and daily
housekeeping of the work area.
Rigging Supervisor Supervision and Responsible for direct execution of the
execution of all rigging rigging works, unloading of materials.
Ensure that lifting plan and procedures are
activities. strictly followed and executed.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 3 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

QC Manager Site management, Preparation of QC program & guidelines.


Ensure the work has performed in
program & guidelines.
compliance with approved Project Quality
Plan, TRS Quality documents, Saudi
Aramco Standards & Procedures. Monitor
QC personnel mobilization at site as per
Schedule Q. Over all responsible in project
quality issues.

QC Supervisor Implement QC program and policies.


Supervise the daily QC site activities.
Site Supervision
Responsible for all site QC matters and
issues.

QC Inspector Inspections, record and Responsible for the necessary inspection


and test to be carried out during Tie-In
document reports
activities. Record and document reports of
all inspection & testing in accordance to the
approved QC-ITP and QC Program.

Safety Inspector Ensure safety for the Responsible in inspection and monitoring
safety aspects and ensure that the work is
proper execution of done in accordance with TR/Saudi Aramco
fabrication activities Safety Standards and EGE Safety
guidelines.

5.0 MANPOWER

The Piping Supervisor will control the activities at the site and he will be directly reporting to the
Project Engineer. The basic manpower under him will consist of the following:

5.1 Piping Foreman


5.2 Pipefitters
5.3 Permit Receiver
5.4 Welding Foreman
5.5 Welders
5.6 Rigger 1
5.7 Riggers
5.8 Heavy equipment operators
5.9 Flag men
5.10 Fire watch
5.11 Helpers & Labors

6.0 TOOLS AND EQUIPMENT

Tools and equipment needed should be in good condition and must be checked by
Supervisor prior to use in the Tie-In area. These includes but not limited to:
DOCUMENT NO. REVISION PRINT DATE PAGE
EGE-TR-MS-077 1 23-Oct-2018 4 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

6.1 Welding Machines


6.2 Cold cutting machine (pneumatic cutting machine)
6.3 Grinders
6.4 Hilti Drilling machine
6.5 Nylon Slings
6.6 Chain Blocks
6.7 Pencil Grinder
6.8 Forklifts
6.9 Crane
6.10 Trailer Truck
6.11 Common Hand Tools
6.12 Air Compressor
6.13 Radiography (Weld Joints)
6.14 Hydro test pump
6.15 Flange Tester
6.16 Impact/Torque Wrenches
6.17 Hydro test manifold
6.18 Portable electrode oven

7.0 WORK METHODOLOGY

7.1 Engineering Preparation

7.1.1 Review all references such as approved Tie-in Procedure and Packages (construction
drawings, project specifications, work permit requirements, and work procedures Saudi
Aramco standards GI-0002.100)

7.1.2 Ensure WPS, PQR, Tie-In packages are TR /Saudi Aramco approves
documentation prior to any tie-in activities.

7.1.3 Ensure drawings are IFC latest revision approved by TR/Saudi Aramco
prior to start tie-in works.

7.1.4 Conduct site verification to determine actual tie-in location and site condition in
reference to Isometric drawing nos. CD-363084 SHT.001 rev.01D, P&ID no. NA-
M23669 SHT.001 rev.15A1, and Piping layout NA-815071 SHT.003 rev.02

7.1.5 Prepare tie-in package with the latest revision of IFC drawings in reference TR
/ Saudi Aramco requirements.

7.1.6 Prepare Job Safety Analysis. (shall be submitted separately)

7.1.7 Prepare lifting plan / rigging plan and shall be approved prior to the Tie- In works.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 5 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

7.1.8 Ensure that Manifold testing are approved including the verification of the calculation of
the test pressure against existing T min results by Engineering.

7.1.9 Ensure that Relief pressure valves are set as per pressure calibration, based on the
calculated test pressure.

7.1.10 Prepare Hydrotest Procedure for TRS / Saudi Aramco PMT approved prior to start
of Hydro Testing.

7.2 WORK to be executed before Shutdown Time for TIE-IN 054-077

7.2.1 Inspection of Material

Subcontractor / Contractor will perform during the Receiving form TR facilities


warehouse. The inspection shall be based on SAIS-L-2-29 but not limited to:

7.2.1.1 Tie-ins pipe and fitting shall have the material specification and grade stamped.

7.2.1.2 Pipe shall be free of handling and fabrication damages and manufacturing defects.

7.2.1.3 Support material will have inspected and approved.

7.2.1.4 Inspect the existing pipe in order to perform the tie-ins

7.2.2 Pre-Fabrication Activities:

Subcontractor/ Contractor will execute the below activities before shutdown


date

7.2.2.1 Tie-in spool no’s SPL-001 and SPL 002 (for CD-363084 Sht.001 rev. 01D) will be pre-
fabricated at Fabrication shop.
7.2.2.2 Pre-fabricated spools to be internal cleaned, dried and will be covers on both sides before
transfer to painting yard.
7.2.2.3 Blasting a n d painting of p i p e spools as per SAES-H-002. Painting system APCS-
1D shall be used at Painting shop (ARAMCO certified painting shop). Pipe ends shall be
covered with wooden cover or plastic cap for preservation & mobilization to paint shop
7.2.2.3 Hydrotest of Tie-In spool 1 will be conduct in EGE lay down area (Test Pressure is 423.6
bar). Hydro test of spool 2 will be conduct after erection of continue Isometric spools.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 6 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

7.2.2.4 Each material and fabricated tie-in spool shall be identified and delivered to the tie-in
location as bagged and tagged with the assigned tie-in number.
7.2.2.5 One Support POS-001-TP-077 (as shown in figure below) wil be prefabricated and will
be welded before Hydrotest.

Dimension shall be checked at site

Z03B

7.2.2.6 The activities to perform hydro test will be:

No# Action Action by Remark


1 Obtain work permit prior to start of SUB-
hydrotest activities CONTRACTOR

2 Installation of approved temporary blinds SUB-


and temporary gaskets as per attached CONTRACTOR
P&ID dwg no. NA-M23669 Sht.001 rev. 15A1
& Isometric dwg no.CD-363084 Sht.001 rev.
01D. Install pressure gauges on high point.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 7 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

3 RFI will be raised for bolt torque and gaskets SUB-


verification. Torque the flanges as per approved CONTRACTOR
flange bolting procedure. TR bolt torque
procedure no.

4 Follow Hydro test schematic diagram SUB-


(attachment-2) & test procedure. CONTRACTOR

5 Hydro test tie-in of all spool is needed. SUB-


Refer to attached isometric drawing & P&ID for CONTRACTOR

the test limit.


6 The filling point of water will be lowest SUB-
elevation as shown in attached P&ID dwg no. CONTRACTOR

NA-M23669 Sht.001 Rev. 15A1& Isometric dwg


no.CD-363084 Sht.001 rev. 01D.
The hydro test pressure will be 423.6 psig
(29.41 bar)
7 Each hydro-test manifold is equipped with SUB-
RV the set point of that relief valve is 1.05 times CONTRACTOR

the test pressure- 30.88 bar. Relief valve


calibration certificate valid only for one week.

8 Ensure that all hoses, PG & RV are tested SUB-


& calibrated prior to use. Pressure gauge CONTRACTOR

calibration certificate valid only for one month.


9 Raise RFI for witness and acceptance of SUB-
hydrotest by TRS / Saudi Aramco PMT CONTRACTOR

After Hydro test, internal cleaning and dry SUB-


will be done. Hydro test water will be drained to CONTRACTOR
10 / COMPANY
the nearest ditch inside EGE laydown area.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 8 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

Tie-In Information

NOTE; REFER TO ATTACHED P&ID MARKED-UP HYDRO TEST LIMIT FOR REFERENCE P&ID dwg.
no. NA-M23669 Sht.001 Rev. 15A1& Isometric dwg no.CD-363084 Sht.001 rev. 01D
7.2.3 Pre-Tie-in/Site Activities:
7.2.3.1 Ensure that tie-in site verification has been carried out and tag the tie-in
location.
7.2.3.2 Cleaning and Purging
After final cleaning and purging line will be handover to Contractor/Sub-
Contractor for Execution

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 9 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

Submit and get the approval for Cold WP From company and follow.
Operations Safety’s Instructions.
Mark exact tie-in using approved marking method.
Two Pipe Supports POS-001-TP-077 will be installed on foundation. EGE QC will
raise request for inspection of bolt torqueing.
7.2.3.3 Storage and handling of Tie-ins spools and material
Subcontractor / contractor will perform inspection to ensure all tools and
equipment’s has valid calibration certificate / third party certification. Tools box
shall be placed in designed area in plant included manifold, hoses.
Ensure equipment operators has valid license/certificate. Crane will be used to
unload the spools at site. After unloading the spools and material will be
inspected by Subcontractor/Contractor and SA Operations in order to make sure
the proper man power for the material during the transportation from Workshop.
Pipe shall be placed on mounds or sleepers.
Valves, Gaskets, nuts and bolts will be inspected in EGE workshop. They will be
store in shipping crates or on racks. ALL material will be handled with care during
shifting to site. All documentation MTC, etc. shall be carried with the material,
isolation valves will be tested at shop.
Below find List of material
Valve
Bolts and nuts Gaskets
Flanges
7.3 Work to be executed during the shutdown time for Tie-In Work for 054-077
(Cold tap Tie-In)

7.3.1 Before any works is done, Work permit must be secured from Saudi
Aramco Operation Department.
7.3.2 Prior to Execution, check that tie-in location is gas free by following Cold WORK
PERMIT pr ocedur e and Operations instructions.
Precaution shall be taken care to prevent ignition of flammable or combustible
materials. Existing pipe will be cut with Cold cutting machine and mobilized using
crane as per approved lifting plan.
7.3.3 Lift spool no. SPL-001 of CD-363084 Sht.001 in proper position using crane as per

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 10 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

approved lifting plan and connect with existing flange by flange joint 01. RFI will be
raised for bolt torque and gaskets verification. Torque the flanges as per approved
flange bolting procedure.
7.3.4 Lift spool no. SPL-002 of CD-363084 Sht.001 in proper position using crane as per
approved lifting plan and Connect with spool no. SPL-001 of CD-363084 Sht.001 by
flange joint 06.
7.3.5 Bolt torque shall be prepared by referring to Saudi Aramco Standard for
Bolt Torque Procedure.

7.4 Post tie-in Activity

7.4.1 Clean the area of construction debris, waste materials, tools and equipment.
7.4. 2 EGE shall close all related work permits.

8.0 RFI for Layup & Reinstatement

8.1 EGE assigned site QC/QA Inspector will perform quality inspection of tie-in activities as
per approved ITP.
8.2 QC acceptance criteria shall be in accordance to the approved ITP as described in the project
specifications, Saudi Aramco QC Standard.
8.3 EGE assigned QC Inspector shall carry out all the inspection works related to
Tie-In activities and coordinate with TRS-QC representative on daily basis.

9.0 SAFETY ACTION PLAN

9.1 Prior to Start the Job, Supervisor /Foreman have to share the work scope, identification of
work location, associated hazards and mitigation with crew.
9.2 Equipment and Tools should be inspected prior to use and replace if found defective.
9.3 Supervisor / Foreman / Safety Officer have to ensure the working crew are wearing the
right PPE as per the associated hazards with activities
9.4 Supervisor / Foreman have to ensure continues supply of drinking water at site and Working
crew are drinking the water and taking the rest frequently.
9.5 Supervisor / Foreman / Safety Officer / Permit receive should be available at site to ensure
work is going on safely as per the work permit requirement / JSA requirement.
9.6 Review the attached JSA

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 11 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

10.0 SAFETY INSPECTION

EGE assigned Site Safety Officer will implement safety program and policies at site in accordance to
Saudi Aramco Safety Standards. A Job Safety Analysis will be prepared by EGE site safety
representative for submission to TRS and for review and approval by Saudi Aramco Ras Tanura
Refinery Safety Department before start of tie-in works.

11.0 APPLICABLE REFERENCES

REFERENCE AUTHOR TITLE


SAES-A-004 Saudi Aramco General Requirements for Pressure Testing
Applicable Codes and Standards for Pressure
SAES-L-100 Saudi Aramco
Piping
SAES-L-105 Saudi Aramco Piping Line Class
SAES-L-109 Saudi Aramco Selection of Flanges, Stud Bolts and Gaskets
SAES-L-110 Saudi Aramco Limitations on Pipe Joints and Components
SAES-L-150 Saudi Aramco Pressure Testing of Plant Piping and Pipelines
SAES-L-310 Saudi Aramco Design of Plant Piping
SAES-L-350 Saudi Aramco Construction of Plant Piping.
API 598 API Valve Inspection and Testing
ASME B31.3 ASME Process Piping
ASME Section IX ASME Welding and Brazing Qualifications
SAES-W-011 Saudi Aramco Welding requirements for On-Plot Piping.
01-SAMSS-010 Saudi Aramco Fabricated Steel Piping.
01-SAMSS-048 Saudi Aramco Valve Inspection and Testing Requirements.
Disposal of Waste water from Cleaning,
SAEP-327 Saudi Aramco Flushing, and Dewatering Pipelines and
Vessels
SAEP-351 Saudi Aramco Bolted Flange Joints Assembly
SATIP-L-350-02 Saudi Aramco Saudi Aramco Typical Inspection Plan
GI-0002.100 Saudi Aramco Work Permit System
GI-0002.102 Saudi Aramco Pressure Testing Safely
GI-0002.711 Saudi Aramco Fire and Safety Watch

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 12 of 13
METHOD STATEMENT OF PIPING TIE-IN NO. 054-077 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT

12.0 APPENDICES

CD-363084 Sht.001 rev. 01D -TIE IN ISOMETRIC DRAWING


NA-M23669 Sht.001 Rev. 15A1 - P&ID
ATTACHMENT 2 - Schematic hydro test diagram
ATTACHMENT 3 - Welder JCC
SATR-L-2001 - Flange Joint Tightening Inspection Report
SATR-W-2006 - Fit-Up Report
SATR-W-2007 - Welding Report
SATR-W-2008 - Welding Summary
JSA - Job Safety Analysis
SIS - Safety Instruction Sheet.

DOCUMENT NO. REVISION PRINT DATE PAGE


EGE-TR-MS-077 1 23-Oct-2018 13 of 13
NOTES:

1.FOR DETAILS OF INSTRUMENTS ASSOCIATED WITH LCC-618


SEE DA-054143.
PLANT 55 2.LOW LOW LEVEL ALARM STOPS PUMP IN AN ACTIVE PML OR MML.
PLANT 54
HIGH HIGH LEVEL ALARM STOPS PUMP IN AN ACTIVE MML FOR A
TANK TO TANK TRANSFER USING A PUMP.
3.HIGH POINT VENTS & LOW POINT DRAINS PROVIDED BY PIPING.
THE LOW POINT DRAIN SHOULD BE 4" DIA. EXTRA DRAINS & VENTS
TO BE PROVIDED IN DETAIL DESIGN AS PER NEED.
4.DURING UNLOADING OF GASOLINE FROM NP-7 INTO T-1445,
T-1544 & T-1545 HV-084, HV-085 & MOV-101 MUST BE LOCKED
OPEN AND DURING UNLOADING INTO REST OF GASOLINE TANKS
MOV-193 ALSO MUST BE LOCKED OPEN INCLUDE ALL THOSE VALVES.
PI MOTHBALLED 5.FOR TYPICAL INSTRUMENTATION DETAILS SEE DWG.CA-359405.SH.001.
942 AS-PER TTSD/TSU-135/94
GENERAL NOTES:
- REFER TO GENERAL NOTES ON P&ID J99-A-PID-CA-350456-002.
I
- FOR LEGEND AND SYMBOLOGY SEE J99-A-PID-CA-350456-001 TO 018.

0-300 PSIG
0-400 PSI
PI PT
942 942

3/4"
1"
CLOUDED ITEMS ARE PART OF BI-10-00742
CONTRACTOR'S SCOPE.
1" V
1" 1" 1" V
HV0088
DASH-DOT CLOUD SHOWS CHANGES FROM
20" 22" SP-15 PREVIOUS REVISION INCLUDING SITE SURVEY.
16" CL150 18"CL150
LEGEND
4" CL150
PIPING MATERIAL INSTRUMENT DEFINITION & SYMBOLS SAES-J-003
D SPECIFICATION SAES-L-105
AC/AFO -AIR TO CLOSE/ VE -VIBRATION ELEMENT
AIR FAILURE OPEN VS -VIBRATION SWITCH
AC/AFS -AIR TO CLOSE/AIR VT -VIBRATION TRANSMITTER
PROCESS LINE
FAILURE STEADY XL -PILOT LIGHT
INSTRUMENT AO/AFC -AIR TO OPEN/ (NOT FOR MOTOR)
AIR LINE AIR FAILURE CLOSE XS -LIMIT SWITCH
AO/AFS -AIR TO OPEN/AIR ZV -SAFETY SHUTDOWN VALVE
INSTRUMENT
FAILURE STEADY
ELECTRICAL LINE DATA LOGGER POINT
AOV -AIR OPERATED VALVE
F-FLOW P-PRESS.

INPUTS
AT -ANALYZER TRANSMITTER
L-LEVEL T-TEMP.
DT -DENSITY TRANSMITTER

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL, OR IN PART, SHALL BE OBTAINED FROM THIS DRAWING WITHOUT THE WRITTEN CONSENT OF SAUDI ARAMCO.
X-MISC. A-ALARM
REDUCER ESD -EMER. SHUTDOWN SYSTEM
LOCAL PANEL
FC - FLOW CONTROLLER
SPECTACLE MOUNTED INSTR.
B1-10-00742 PLATE-OPEN
FV -FLOW CONTROL VALVE
FCV -FLOW CONTROL VALVE
BOARD MOUNTED
TO T-1544 054 147 SPECTACLE
(SELF-ACTUATED) INSTRUMENT
20"-P-09019-1CS1P13 FE -FLOW ELEMENT
PLATE-CLOSED R/G
CA-359435.001 FG -FLOW SIGHT GLASS
STATUS LIGHTS
GATE VALVE FHV -FLOW MANUAL CONT. VALVE XL R=RED, G=GREEN
NP-7 FHTD -FLOW MANUAL TRANSDUCER PILOT LIGHT (DO NOT
GLOBE VALVE FIC -FLOW INDICATOR CONTROLLER USE FOR MOTOR STATUS)
1" V 1" V CHECK VALVE FM -FLOW METER
TO T-1445, T-1545 20"-P-09017-1CS1P13 FO -RESTRICTION ORIFICE MOTOR STATUS
PILOT LIGHT
NA-641518.011 15A1 PLUG VALVE FQI -FLOW TOTALIZER INDICATOR
FR -FLOW RECORDER
15A1 BALL VALVE ML LOCAL MOUNTED
NP-7 FT -FLOW TRANSMITTER INSTRUMENT
15A1 DOUBLE DISC FY -FLOW RELAY
SET @ 150 PSI GATE VALVE HIC -HAND INDICATOR CONTROLLER
MOUNTED BEHIND
15A1 ANGLE VALVE HS -HAND SWITCH LOCAL PANEL
20" CSO PZV 3/4" V LA -LEVEL ALARM
B1-10-00742 B1-10-00742 16"
+

2930 -LEVEL CONTROL VALVE


PRESS.RELIEF VALVE LV RACK MOUNTED
20" CSO -LEVEL CONTROL VALVE
24"x20" 054 077 054 075 TO CRUDE OIL LINE LCV (OR BACK OF PANEL)
1" (SELF-ACTUATED)
15A1 LG -LEVEL GAUGE GLASS ELECTRICAL
V
-LEVEL INDICATOR CONTROLLER SUPPLY REQUIRED
NOTE 4 LIC
24"x20"

1CS1P13 VACUUMRELIEF VALVE


MOV 3/4" LI -LEVEL INDICATOR
1A1 3" 3/4"
TO T-1447, T-1448 +
MOV LR -LEVEL RECORDER INSTRUMENT
24"-P-3416-1A1 M 193 M -LEVEL SWITCH AIR SUPPLY REQUIRED
T-1346, T-1347, T-1446, +
12" 1" V 15A1 M MOTOR OPERATED LS
3/4" V 101 1" V LT -LEVEL TRANSMITTER
T-1546 & T-1747 1" V 1" V 1" V VALVE H
24"x16" 24"x16" 1A1 HV0085 24" HV0084 NP-7 LTD -LEVEL TRANSDUCER HIGH LOW
22" NP-7 22" ML -MOTOR STATUS LIGHT L
NA-M23668.001 DA-698470.001 -MOTOR OPERATED VALVE
MOV
16"CL150 16" 16"CL150 22" P

NP-7 16" CL150 FROM NORTH PIER PISTON OPERATED NA -ANNUNCIATOR TWO PEN RECORDER
1-1/2" D D 1-1/2" HV 1-1/2" VALVE PB -PUSHBUTTON
NOTE 4 NOTE 4 12" 4" V NOTE 4 4" CL150
16" +
15A1 PC -PRESSURE CONTROLLER FF
12" 8497 CONTROL VALVE PV -PRESS. CONTROL VALVE FOUNDATION
PCV -PRESS. CONTROL VALVE FIELDBUS INSTRUMENT
2" V 3/4" (SELF ACTUATED)
P
BALL TYPE PDC -PRESS. DIFF. CONTROLLER DISTRIBUTED CONTROL/SHARED
V CONTROL VALVE PDI -PRESS. DIFF. INDICATOR DISPLAY SYMBOLS
WITH POSITIONER PDIC -PRESSURE DIFFERENTIAL
(DCS) DISTRIBUTED CONTROL
S INDICATOR CONTROLLER SYSTEM, OPERATOR ACCESSIBLE
SOLENOID VALVE PDIS -PRESSURE DIFFERENTIAL IN CONTROL ROOM
INDICATOR SWITCH (DCS) DISTRIBUTED CONTROL
PDT -PRESS. DIFF. TRANSMITTER
20" VALVE NORMALLY SYSTEM, OPERATOR INACCESSIBLE
15A1 J/O NP-10 FUEL CARGO PDTD -PRESS. DIFF. TRANSDUCER IN CONTROL ROOM
20" CLOSED
PG -PRESSURE GAGE
NA-M23692.001 PI -PRESSURE INDICATOR (DCS) DISTRIBUTED CONTROL
SYSTEM, OPERATOR INACCESSIBLE
PIC -PRESS. INDICATOR CONTROLLER
IN FIELD
PR -PRESSURE RECORDER
PS -PRESSURE SWITCH
PT -PRESSURE TRANSMITTER DISTRIBUTED CONTROL
PX -PRESSURE POINT INTERCONNECTING LOGIC
PY -PRESS. COMPUTATION MOD. CONTROLLER WITH BINARY
PZV -PRESSURE RELIEF VALVE OR SEQUENTIAL FUNCTIONS
RTD -RESIST. TEMP. DETECTOR
(PLC) PROGRAMMABLE LOGIC
SI -SPEED INDICATOR
CONTROLLER, NORMALLY
SS -SPEED SWITCH INACCESSIBLE OR BEHIND THE
TC -TEMP. CONTROLLER PANEL DEVICE OR FUNCTIONS
TV -TEMP. CONTROL VALVE (PLC) PROGRAMMABLE LOGIC
TCV -TEMP. CONTROL VALVE CONTROLLER FUNCTION,
MOV (SELF-ACTUATED) CAN BE NORMALLY
+
M
4" V 4" V 107 16"x12" TE -TEMP. ELEMENT DISPLAYED ON CRT

15A1 TSO -TIGHT SHUT OFF TG -THERMOMETER LOCAL DCS OR AUXILIARY


TO T-17 NAPTHA 16"x10" 4" S.C. - SAMPLE CONN. THS -TEMP. HAND SWITCH DCS LOCATION NORMALLY
TI -TEMP. INDICATOR ACCESSIBLE TO OPERATOR
S -DRAIN TO
NA-641518-007 16" PRESSURE SEWER TR -TEMP. RECORDER
(PLC) PROGRAMMABLE LOGIC
TS -TEMP. SWITCH
-OILY WATER SEWER CONTROLLER I/O POINT
OWS TT -TEMP. TRANSMITTER NORMALLY INACCESSIBLE
D -DRAIN TTD -TEMP. TRANSDUCER BY OPERATOR
V -VENT TW -THERMOWELL
I PI
941
FI REFERENCE DRAWINGS
LETTER IDENTIFICATION OF LINES AE-036204
0-300 PSIG 0-400 PSI 2 09
PIPING SYMBOLS AB-036227
TO FTD-09
PI PT FC EQUIPMENT SYMBOLS AB-036305
NA-M23668 SHT. 001
941 941 09 INSTRUMENT SYMBOLS AC-036950

0-10 PIPING LAYOUT INDEX


FT 0-100" PLANT 54 PLANT 55
PLOT PLAN
09 IN WC F PROCESS FLOW DIAGRAM
1" V 1" V 1" V 09 HYDROSTATIC TEST DIAGRAM
FROM G-197/G-198 DISCHARGE
GASOLINE DISCHARGE NO. 1 DRAWING CONTROL FOR J.O. EWO NO # 06N942A RD-302050
18"-P-3418-1A1
NA-M23668.001 INSTRUMENT INSTALLATION SCHEDULES

1" D 1" D 1" D

FE
+

09 ALL PRODUCTS LINE TO SOUTH


D-13.147
PIER ARE MOTHAOLLED
15 A1 14-Jun-2018 ISSUED FOR CONSTRUCTION MMG JYM JLT
15 16-Nov-2017 ISSUED FOR CONSTRUCTION ARV FFM JLT
Rev. Date Description By Chk Appr
REVISION VALIDATION
THIS REVISION NO. 15A1 IS COVERED, FOR ALL APPROVAL AND CERTIFICATION
REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO:

10-00742-0006-001

DESIGN CERTIFICATION REVIEW FOR KEY DRAWINGS OTHER


(DESIGN AGENCY) REQUIRED (SAUDI ARAMCO)
ENGG./DATE CERTIFIED BY/DATE CONST. AGENCY/DATE OPERATIONS/DATE BY/DATE

REV.NO. DATE REVISION DESCRIPTION


15A1 14-JUN-2018 ISSUED FOR CONSTRUCTION

JOB ORDER/EWO NO.


THIS REVISION IS NOT TO BE USED FOR
10-00742-0006 CONSTRUCTION UNTIL CERTIFIED AND DATED

SAUDI ARABIAN OIL COMPANY


DRAWING TYPE
PIPING & INSTRUMENTATION DIAGRAM PID
GASOLINE SYS.NP/SP PR.H.FAC.
TERM.SOUTH SHIPPING PUMPHOUSE -1, 2
RAS TANURA SAUDI ARABIA
PLANT NO. INDEX DRAWING NUMBER SHT. NO. REV. NO.

054 A NA-M23669 001 15A1


Saudi Aramco 5994 ENG. (09/03)

SMART CADD-05