Professional Documents
Culture Documents
Development of Pavement Management System For Indian National Highway Network PDF
Development of Pavement Management System For Indian National Highway Network PDF
502
DEVELOPMENT OF PAVEMENT MANAGEMENT
SYSTEM FOR INDIAN NATIONAL HIGHWAY
NETWORK
By
CONTENTS
Page
1. Introduction ... ... 272
2. Research Survey ... ... 273
3. Identification of National Highway Network ... ... 274
4. Data Acquisition and Database ... ... 276
5. Calibration and Validation of HDM-4 Pavement ... ... 289
Performance Prediction Models
6. Pavement Management at Project Level ... ... 290
7. Pavement Management at Network Level ... ... 305
8. Applications of the Study ... ... 323
9. Conclusions ... ... 324
SYNOPSIS
1. INTRODUCTION
1.1. Background
2. RESEARCH SURVEY
3.1. General
4.1. General
The road network data collection was carried out based upon the data
requirements of HDM-4, and it consisted of obtaining secondary data from the
past records and relevant government publications, and collecting current data
from the selected pavement sections by carrying out field studies. The road
network data includes the locational data that describes the position and geometry
of the pavement section, and the attribute data, which describes the road
characteristics or inventory associated with it.
DEVELOPMENT OFPAVEMENT MANAGEMENT SYSTEM FOR INDIAN 277
NATIONAL HIGHWAY NETWORK
The road network data collection in the field was divided under the
following heads:
Where
UI = Unevenness Index in mm/km
B = Bump Integrator reading
W = No. of wheel revolutions
The relationship given in Equation 2 has been used to convert the UI into
the universally acceptable International Roughness Index (IRI - measured in m/
km) [Odoki and Kerali, 200016].
Field evaluation - Test pits of size approx. 0.5 m x 0.5 m were dug
up at suitable locations with in all pavement sections. The following
tests were conducted and observations taken in the pits: Thickness of
the most recent surfacing course and old surfacing courses, Thickness
of granular base and sub-base courses, Qualitative assessment of
the level of compaction of all layers, Field dry density and field
moisture content of sub grade. For characterization of materials in the
laboratory, representative subgrade soil samples were collected from
the test pits.
Laboratory evaluation - The detailed evaluation in the laboratory
was done on the soil samples in accordance with the Indian Standard
specifications. The following tests were carried out for each soil sample:
Atterbergs limits (Liquid limit and Plastic limit), Proctor density and
optimum moisture content, CBR (unsoaked and soaked at field
conditions)
All road network data items, which are required to be specified for each
pavement section, are given in the Tables 3(a) to 3(d). All these data items
reside in the road network database created in HDM-4. This road network
database has been named as National Highway Network, for all future
references and uses.
TABLE 3(a). H IGHWAY N ETWORK - BASIC D ATA 282
Section Section Link Name Speed Flow Traffic Flow Climate Zone Section Carriage- Motorized AADT
ID Name Type Pattern Length way AADT Year
(km) Width
(m)
NH-5801 NH-58 [km 130-141] Muzzafarnagar - Roorkee Two Lane Standard Inter-city North India - Plains 11 7.0 11,450 2002
NH-5802 NH-58 [km 141-153] Muzzafarnagar - Roorkee Two Lane Standard Inter-city North India - Plains 12 7.0 11,370 2002
NH-5803 NH-58 [km 153-173] Muzzafarnagar - Roorkee Two Lane Standard Inter-city North India - Plains 20 7.0 12,290 2002
NH-5804 NH-58 [km 173-192] Roorkee - Rishikesh Two Lane Standard Inter-city North India - Plains 19 7.0 13,980 2002
NH-5805 NH-58 [km 192-204] Roorkee - Rishikesh Two Lane Standard Inter-city North India - Plains 12 7.0 13,860 2002
NH-5806 NH-58 [km 204-218] Roorkee - Rishikesh Two Lane Standard Inter-city North India - Plains 14 7.0 11,260 2002
NH-5807 NH-58 [km 218-228] Roorkee - Rishikesh Two Lane Standard Inter-city North India - Plains 10 7.0 8,540 2002
NH-7201 NH-72 [km 105-118] Paonta Sahib - Dehradun Single Lane Standard Inter-city North India - Plains 13 3.7 3,650 2002
NH-7202 NH-72 [km 118-132] Paonta Sahib - Dehradun Two Lane Standard Inter-city North India - Plains 14 7.0 5,720 2002
NH-7203 NH-72 [km 132-148] Paonta Sahib - Dehradun Two Lane Standard Inter-city North India - Plains 16 7.0 5,870 2002
NH-7204 NH-72 [km 162-180] Dehradun - Haridwar Two Lane Standard Inter-city North India - Plains 18 7.0 7,280 2002
NH-7205 NH-72 [km 180-197] Dehradun - Haridwar Two Lane Standard Inter-city North India - Plains 17 7.0 6,840 2002
NH-72A1 NH-72A [km 0-11] Chutmalpur - Dehradun Two Lane Standard Inter-city North India - Plains 11 7.0 6,550 2002
NH-72A2 NH-72A [km 11-22] Chutmalpur - Dehradun Two Lane Narrow Inter-city North India - Plains 11 6.1 6,310 2002
NH-72A3 NH-72A [km 22-33] Chutmalpur - Dehradun Two Lane Narrow Inter-city North India - Hills 11 6.5 6,250 2002
NH-72A4 NH-72A [km 33-43] Chutmalpur - Dehradun Two Lane Standard Inter-city North India - Hills 10 7.0 6,040 2002
AGGARWAL, PROF. JAIN & DR. PARIDA ON
NH-7301 NH-73 [km 0-11] Roorkee - Saharanpur Two Lane Standard Inter-city North India - Plains 11 7.0 7,840 2002
NH-7302 NH-73 [km 11-25] Roorkee - Saharanpur Two Lane Standard Inter-city North India - Plains 14 7.0 7,750 2002
NH-7303 NH-73 [km 25-35] Roorkee - Saharanpur Two Lane Narrow Inter-city North India - Plains 10 6.5 7,670 2002
NH-7304 NH-73 [km 35-47] Roorkee - Saharanpur Two Lane Standard Inter-city North India - Plains 12 7.0 7,650 2002
NH-7401 NH-74 [km 0-13] Haridwar - Najibabad Two Lane Narrow Inter-city North India - Plains 13 6.1 5,480 2002
NH-7402 NH-74 [km 13-30] Haridwar - Najibabad Two Lane Narrow Inter-city North India - Plains 17 6.1 5,520 2002
TABLE 3(b). H IGHWAY NETWORK - C ONDITION DATA
Section Condition Rough- Cracking Ravelled Potholes Edge Rut Texture Skid Benkel- Adjusted
Name Year ness Area Area (no./km) Break Depth Depth Resistance man structural
IRI (%) (%) (m 2/km) (mm) (mm) (SCRIM) Beam Number of
(m/km) deflec- pavements
tion mm (SNP)
NH-58 [km 130-141] Asphaltic Concrete (AC) 40 100 1994 2000 2000 2000
NH-58 [km 141-153] Asphaltic Concrete (AC) 40 100 1992 1998 1998 1998
NH-58 [km 153-173] Asphaltic Concrete (AC) 40 100 1992 1998 1998 1998
NH-58 [km 173-192] Double Bituminous Surface Dressing (DBSD) 25 100 1992 1997 2000 2000
NH-58 [km 192-204] Double Bituminous Surface Dressing (DBSD) 25 100 1992 1997 2000 2000
NH-58 [km 204-218] Double Bituminous Surface Dressing (DBSD) 25 100 1990 1996 1999 1999
NH-58 [km 218-228] Double Bituminous Surface Dressing (DBSD) 25 100 1990 1996 1998 1998
NH-72 [km 105-118] Single Bituminous Surface Dressing (SBSD) 15 50 1990 1996 1999 1999
NH-72 [km 118-132] Asphaltic Concrete (AC) 25 50 1992 1997 1997 1997
NH-72 [km 132-148] Asphaltic Concrete (AC) 25 50 1992 1997 1997 1997
NH-72 [km 162-180] Double Bituminous Surface Dressing (DBSD) 25 50 1990 1995 1999 1999
NH-72 [km 180-197] Double Bituminous Surface Dressing (DBSD) 25 50 1990 1995 1998 1998
NH-72A [km 0-11] Single Bituminous Surface Dressing (SBSD) 15 50 1992 1992 1997 1997
NH-72A [km 11-22] Single Bituminous Surface Dressing (SBSD) 15 50 1993 1993 1998 1998
AGGARWAL, PROF. JAIN & DR. PARIDA ON
NH-72A [km 22-33] Single Bituminous Surface Dressing (SBSD) 15 50 1992 1992 1997 1997
NH-72A [km 33-43] Double Bituminous Surface Dressing (DBSD) 25 50 1996 1996 2001 2001
NH-73 [km 0-11] Asphaltic Concrete (AC) 25 50 1992 2000 2000 2000
NH-73 [km 11-25] Asphaltic Concrete (AC) 25 50 1994 2001 2001 2001
NH-73 [km 25-35] Double Bituminous Surface Dressing (DBSD) 25 50 1992 1992 1997 1997
NH-73 [km 35-47] Double Bituminous Surface Dressing (DBSD) 25 50 1992 1992 1997 1997
NH-74 [km 0-13] Double Bituminous Surface Dressing (DBSD) 25 50 1992 1992 1999 1999
NH-74 [km 13-30] Double Bituminous Surface Dressing (DBSD) 25 50 1992 1992 1999 1999
DEVELOPMENT OFPAVEMENT MANAGEMENT SYSTEM FOR INDIAN 285
NATIONAL HIGHWAY NETWORK
TABLE 3(d). LABORATORY T EST RESULTS OF SUBGRADE SOIL SAMPLES
differences between different type of vehicles, the objectives of the study, and
the availability and quality of data. A typical vehicle fleet in India may be
considered to be comprised of the following vehicles for the purpose of economic
analysis to be conducted in PMS. The same set of vehicles has also been
identified as representative vehicle fleet for Indian conditions, in the latest Road
User Cost Study [MORT&H 2001c19]:
The basic vehicle fleet data items, which are required to be specified for
each vehicle type. All these data items reside in the vehicle fleet database created
in HDM-4. This vehicle fleet database has been named as National Vehicle
Fleet, for all future references and uses.
Amongst the above components of the road user costs, Vehicle Operating
Cost (VOC) is the largest component and also susceptible for quantification
with relative ease. VOC is defined as the price the user has to spend to move
the vehicle per unit distance. Time cost involves monetary value of the time of
passengers spent on traveling and the time taken by cargo in transit. The accident
costs involves costs of human life and property, which is very difficult to quantify
in monetary terms. Hence this cost is not included in the analysis. The road user
cost data, in respect of all representative vehicles have been taken as per the
recommendations made in the Updated Road User Cost Study [MORT&H
2001c 19].
The project level pavement management analysis may be done using the
Project Analysis application of the HDM-4. Project analysis is concerned
with the evaluation of one or more road projects or investment options. In the
present study, the following four types of case studies have been undertaken for
the project level pavement management.
TABLE 7. CALIBRATION OF HDM-4 PAVEMENT DETERIORATION MODELS
Calibration Factors Average
Sl.
Model Description HDM-4 Pavement Deterioration Models Calibration
No. Set1 Set2 Set3 Set4 Set5 Factor
2 2
ICA = Kcia [CDS * 4.21 EXP{0.14 SNP 17.1(YE4/SNP )} +
1. Cracking Initiation 0.37 0.44 0.39 0.48 0.45 Kcia = 0.43
CRT]
Cracking 0.45 1/0.45
2. dACA = Kcpa (CRP/CDS) [(1.84 * 0.45 * dtA+ SCA ) - SCA] 0.77 1.11 1.25 1.51 1.64 Kcpa = 1.25
Progression
2
3. Ravelling Initiation IRV = Kvi CDS * 10 * RRF * EXP[-0.156 * YAX] 0.34 0.34 0.36 0.39 0.41 Kvi = 0.37
2
dARV = Kvp(1/RRF) (1/CDS ) [(0.6 + 3.0 * YAX) * 0.352 * dtv+
4. Ravelling Progression 0.35 1/0.35 0.79 0.61 0.46 0.39 0.35 Kvp = 0.52
DEVELOPMENT
SRV ) SRV]
OF
(1 + 0.05 * HS)
5. Potholing Initiation IPT =Kpi 2.0 * (1 + 1* CDB)(1 + 0.5 * YAX)(1 + 0.01* MMP) 0.48 0.53 0.42 0.42 0.41 Kpi = 0.45
T ABLE 8. D ETAILS OF O BSERVED AND P REDICTED C RACKING RAVELLING AND R OUGHNESS V ALUES
NATIONAL HIGHWAY NETWORK
NH-58 [km 130-141] 1.6 1.85 15.1 3.8 2.30 39.4 2.3 2.05 10.8
NH-58 [km 141-153] 5.7 5.08 10.8 5.8 4.63 20.1 4.2 3.90 7.1
NH-58 [km 153-173] 10.2 11.78 15.5 6.5 8.61 32.4 5.6 4.75 15.1
NH-58 [km 218-228] 13.8 17.08 23.7 10.4 7.88 24.2 5.7 5.29 7.2
NH-72 [km 118-132] 15.3 17.11 11.8 13.5 15.58 15.4 6.1 5.26 13.8
FOR INDIAN
NH-73 [km 11-25] 2.1 1.70 19.0 4.5 6.04 34.2 2.6 2.49 4.2
NH-73 [km 35-47] 16.2 20.77 28.2 10.3 13.00 27.0 7.3 6.58 9.8
NH-74 [km 13-30] 11.8 14.17 20.0 10.2 14.26 39.8 4.8 4.91 2.1
Correlation y = 1.2731x 1.0131 y = 1.2403x 1.0396 y = 0.8651x +0.2294
2
R value 0.98 0.79 0.97
291
292 AGGARWAL, PROF. JAIN & DR. PARIDA ON
6.2.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. The analysis period is defined by a start year (i.e. current year 2003)
and the duration of 10 years (i.e. 2003-2012). All these project details are
specified in the opening screen of the Project Analysis application of HDM-4.
6.2.4. Pavement history: For the pavement section under study, the last
reconstruction was in 1992, setting the pavement type to AMGB (Asphaltic
Mix on Granular Base). After the application of overlay in 1997, the pavement
type resets to AMAP (Asphaltic Mix on Asphaltic Pavement), and after the
application of surface dressing in 2000, the pavement type has got reset to STAP
(Surface Treatment on Asphaltic Pavement).
Alternative 3 Alternative 4
2003 15134 1.64 5.22 3.47 7.40 1.84 0 1.84 5.22 3.47 14.80 3.67 0 3.20
2004 16383 1.78 5.93 2.05 0.00 0.00 0 0.65 5.15 3.66 37.04 7.85 0 3.40
2005 17736 1.93 5.93 2.10 1.11 0.00 0 0.82 4.90 4.06 71.82 9.91 18 3.64
2006 19200 2.09 5.92 2.17 1.88 0.00 0 0.99 4.66 5.57 40.49 0.00 35 1.97
AGGARWAL, PROF. JAIN & DR. PARIDA ON
2007 20787 2.26 5.92 2.24 4.48 0.00 0 1.17 4.53 2.05 0.50 0.00 0 0.24
2008 22505 2.45 5.91 2.32 9.53 0.00 0 1.35 4.53 2.15 0.00 0.00 0 0.47
2009 24365 2.66 5.89 2.43 17.81 0.00 0 1.53 4.53 2.26 1.27 0.00 0 0.72
2010 26380 2.88 5.86 2.56 30.41 0.00 0 1.72 4.52 2.38 3.51 0.00 0 0.96
2011 28562 3.12 5.70 2.72 24.25 1.87 0 1.11 4.51 2.52 7.82 0.00 0 1.21
2012 30925 3.38 6.46 1.75 0.60 0.00 0 0.45 4.48 2.69 15.08 0.65 0 1.46
DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEM FOR INDIAN 295
NATIONAL HIGHWAY NETWORK
6.2.9. Description of works: The timing of works report indicates the
works that would be implemented in each analysis year for each project
alternative along with the costs involved in the same. The various works items
resulting from all the M&R alternatives specified, as triggered by the respective
intervention parameters and timings of their application are shown in Table 11.
The total cost to be incurred by the highway agency on maintenance management
of the pavement section under each M&R alternatives, over the whole analysis
period of 10 years is also shown in Table 11.
5.0
4.5
Base Alternative
(m/km IRI)
4.0 Alternative1
3.5 Alternative2
3.0 Alternative3
Alternative4
2.5
2.0
1.5
1.0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
2012 DBSD 25 mm DBSD 25 mm ***** ***** 0.219 13.499 13.499 ***** *****
Crack Seal
Total Capital Cost in Million Indian Rupees 1.978 53.998 71.314 61.632 59.850
DEVELOPMENT OFPAVEMENT MANAGEMENT SYSTEM FOR INDIAN 297
NATIONAL HIGHWAY NETWORK
TABLE 12. E CONOMIC ANALYSIS SUMMARY
6.3.2. Pavement history: For the pavement section under study, the last
reconstruction was done in 1990, setting the pavement type to AMGB (Asphaltic
Mix on Granular Base). After the application of overlay in 1995, the pavement
type resets to AMAP (Asphaltic Mix on Asphaltic Pavement), and after the
application of surface dressing in 1999, the pavement type has got reset to STAP
(Surface Treatment on Asphaltic Pavement).
6.3.5. Description of works and costs: The various works items resulting
from the improvement alternatives specified, as applicable in the pre-defined
application years are shown in Table 15. The total cost to be incurred by the
highway agency on improvement of the pavement section under each
improvement alternatives, over the whole analysis period of 10 years is also
shown in Table 15.
Lane Addition +
OF
Total Capital Cost in Million Indian Rupees 1.120 39.783 39.783 39.783
299
300 AGGARWAL, PROF. JAIN & DR. PARIDA ON
6.4.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. An optimum analysis period of 10 years is chosen considering the fact
that almost all pavement sections will become candidates for reconstruction in
the next ten years in the absence of any other maintenance or rehabilitation
DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEM FOR INDIAN 301
NATIONAL HIGHWAY NETWORK
work. Analysis by Project method is chosen for this case study. All these
project details are specified in the opening screen of the Project Analysis
application of HDM-4.
6.4.4. Analyse project: The application is run for simulating the pavement
condition of the five pavement sections under the defined M&R alternative. No
economic analysis is required to be conducted in this case as there is no other
alternative defined for comparison purposes.
8.0
Average Roughness Value
7.0
6.0 NH-5807
(m/km IRI)
NH-7205
5.0 NH-72A2
NH-7303
4.0 NH-7402
3.0
2.0
1.0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
Fig. 3. Roughness progression for all pavement sections
302 AGGARWAL, PROF. JAIN & DR. PARIDA ON
1. NH-5807 2007 4
2. NH-7205 2005 2
3. NH-72A2 2005 2
4. NH-7303 2004 1
5. NH-7402 2006 3
It can be concluded from the RSL values shown in the above table that in
the absence of any other maintenance activity, all the pavement sections included
in this case study will become candidate sections for reconstruction with in 1 to
4 years, which is a very costly affair. Hence it may be suggested that these
pavement sections should be provided with suitable maintenance and
rehabilitation works as they become due.
6.5.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases as
defined earlier. An optimum analysis period of 20 years is chosen to trigger a
number of M&R cycles. Analysis by Project method is chosen for this case
study.
6.5.4. Analyse project: The application is run for simulating the pavement
condition of the pavement sections under the three defined M&R alternatives
over the analysis period of 20 years. An economic analysis is also conducted
with a discount rate of 10 per cent.
304 AGGARWAL, PROF. JAIN & DR. PARIDA ON
5.00
Average Roughness Value
4.50
4.00
(m/km IRI)
3.50 Scheduled
Overlay
3.00
2.50 Condition
2.00 Responsive
Overlay
1.50
1.00
2003
2005
2007
2009
2011
2013
2015
2017
2019
2021
Year
Fig. 4. Progression of roughness under three alternatives
6.5.6. Description of works: The various work items resulting from the
two M&R alternatives specified, as triggered by the respective intervention
parameters and timings of their application are shown in Table 20. The total
cost to be incurred by the highway agency on maintenance management of the
pavement section under two M&R alternatives, over the whole analysis period
of 20 years is also shown in Table 20.
TABLE 20. DESCRIPTION OF M&R WORKS AND ASSOCIATED COSTS
The network level pavement management analysis has been done using
the Programme Analysis application of the HDM-4. This application deals
primarily with the prioritisation of a defined long list of candidate pavement
306 AGGARWAL, PROF. JAIN & DR. PARIDA ON
In the present study, the following four types of case studies have been
undertaken for the network level pavement management, using the Programme
Analysis application of HDM-4.
7.2.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. All 22 pavement sections included in the National Highway Network
have been selected for this study. All six types of vehicles included in the
National Vehicle Fleet have been selected for this study. The composition of
traffic and the annual growth rates as applicable to all pavement sections have
been selected appropriately.
High > 10,000 Overlay 40 mm Bituminous Concrete Roughness > 2.8 m/km IRI
Wet Mix Macadam 200 mm + Base Course 50 Roughness > 6 m/km IRI
mm Bituminous Macadam + Surface Course 40 and
mm Bituminous Concrete Total Damage Area >10%
Double Bituminous Surface Dressing Total Damage Area > 10%
M&R Resealing +
Alternative Overlay + Overlay 25 mm Bituminous Concrete Roughness > 4 m/km IRI
Medium 5,000 to 10,000
Reconstruction Wet Mix Macadam 200 mm + Base Course 50 Roughness > 8 m/km IRI
mm Bituminous Macadam + Surface Course 25 and
mm Bituminous Concrete Total Damage Area > 20%
Single Bituminous Surface Dressing Total Damage Area > 15%
Overlay 25 mm Semi Dense Bituminous Roughness > 5.2 m/km IRI
Concrete
Low < 5,000
Wet Mix Macadam 200 mm + Base Course 50 Roughness > 10 m/km IRI
mm Bituminous Macadam + Surface Course 25 and
mm Semi Dense Bituminous Concrete Total Damage Area > 30%
AGGARWAL, PROF. JAIN & DR. PARIDA ON
DEVELOPMENT OFPAVEMENT MANAGEMENT SYSTEM FOR INDIAN 309
NATIONAL HIGHWAY NETWORK
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
km
400
Budget Requirements (Million
350
300
250
Rupees)
200
150
100
50
0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
10.0
9.0
Average Roughness Value
8.0
7.0 Base
(m/km IRI)
Alternative
6.0
M&R
5.0 Alternative
4.0
3.0
2.0
1.0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
(i) Revise maintenance and improvement standards and run the life-
cycle analysis again. This will essentially include lowering the
intervention criteria for each M&R works to be applicable.
(ii) Execute budget optimisation since the maintenance/improvement
standards have already been fixed, keeping in view the minimum
requirements of the candidate pavement sections, very little scope
exists for their revision. Hence, under most of the circumstances,
the second option of budget optimisation would usually be selected.
The budget optimisation provides a facility to select road sections
that can be included within a specified budget in order to maximize
the economic benefits. After performing the budget optimisation, a
revised work programme is produced. This works programme has
a total cost that is within the specified budget.
(Contd.)
DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEM FOR INDIAN 315
NATIONAL HIGHWAY NETWORK
TABLE 27. PRIORITIZED LIST OF M&R W ORKS FOR THE YEARS 2003-2012
All the M&R works scheduled on this pavement section, as per the
unconstrained works programme, throughout the analysis period of 10 years,
now appear in the revised optimized works programme list. A portion of this
list is shown highlighted in Table 28. Since the limiting budget remains the
same, this section has to be accommodated in the optimized works programme
only by excluding some other sections having marginally higher NPV/Cost ratio.
how the funds requirements vary with changing the serviceability level from
High to Medium, and to Low. How these fund requirements compare with the
requirements, when the highway network is maintained as per an optimum level
of serviceability, is also shown in this case study.
7.3.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases. All
22 pavement sections included in the national highway network have been
selected for this study.
four alternative M&R strategies have been defined for each road section on the
basis of desired level of serviceability to which the road network is to be
maintained. All these M&R strategies are effective from the start year of the
analysis period i.e. 2003. The selected alternative strategies, maintenance and
rehabilitation works involved and the corresponding intervention criteria are
shown in Table 29.
M&R High Resealing with DBSD Total Damage Area > 5 per cent
Serviceability Overlay with 40 mm BC Roughness > 2.8 m/km IRI
Reconstruction with Roughness > 6 m/km IRI and
200 mm WMM + 50 mm Total Damage Area >10 per cent
BM + 40 mm BC
M&R Medium Resealing with DBSD Total Damage Area > 10 per cent
Serviceability Overlay with 25 mm BC Roughness > 4 m/km IRI
Reconstruction with Roughness > 8 m/km IRI and
200 mm WMM + 50 mm Total Damage Area > 20 per cent
BM + 25 mm BC
M&R Low Resealing with SBSD Total Damage Area > 15 per cent
Serviceability Overlay with 25 mm SDBC Roughness > 5.2 m/km IRI
Reconstruction with Roughness > 10 m/km IRI and
200 mm WMM + 50 mm Total Damage Area > 30 per cent
BM + 25 mm SDBC
2000
Budget Requirements (Million Rupees)
1800
Optimum Fund Requirements
1600
1400
1200
1000
800
600
400
200
0
Optimum High Medium Low
Serviceability Serviceability Serviceability Serviceability
Level of Serviceability
74 per cent of funds required for obtaining optimum serviceability. The funds
requirement for maintaining the whole highway network at the lowest level of
serviceability would only be of the order of about 46 per cent. But as per the
prevalent practice of allocation of funds in India, only 50-60 per cent funds are
available for maintenance management of National Highways [MORT&H,
2001a]. With such kind of fund allocation, it would not be possible to maintain
whole of the highway network either at high or even at medium level of
serviceability. However, the available funds would be sufficient enough to
maintain the highway network at the lowest level of serviceability.
7.0
Average Roughness Value
6.0 High
Serviceability
5.0 Medium
Serviceability
(m/km IRI)
Low
4.0 Serviceability
Optimum
3.0 Serviceability
2.0
1.0
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
1. 100% 1475.9
2. 90% 1328.3
3. 80% 1180.7
4. 70% 1033.1
5. 60% 885.5
6. 50% 738.9
It is quite clear from the above figure that the average roughness value of
the highway network keep on increasing with gradual reduction in budget levels,
which in turn may lead to very high road user cost values. Thus reduced budget
levels have a very detrimental impact on the condition of the highway network.
This case study demonstrates the effect of not taking up the maintenance
when it is due, may be because of unavailability of funds altogether and thereby
deferring the maintenance to subsequent years. The main objective of this
322 AGGARWAL, PROF. JAIN & DR. PARIDA ON
5.5
Roughness (m/km IRI)
5
100% Budget
4.5 90% Budget
80% Budget
4
70% Budget
3.5 60% Budget
50% Budget
3
2.5
2
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
Fig. 10. Average Roughness Value Under Varying Levels of Budget Allocations
analysis is to show how the condition of the highway network will get affected
because of this postponement in taking up the requisite maintenance and
rehabilitation activities.
7.5.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases. All
22 pavement sections included in the national highway network have been
selected for this study.
It is quite evident from the above figure that the average roughness value
of the highway network will not change much if the maintenance is delayed by
one year, but this value will rise very sharply, in case the application of
maintenance activities is deferred by two years or more, resulting in very high
road user costs. Thus, it may be concluded that the M&R activities should not
be delayed much from the time they have been triggered by the respective
intervention levels.
DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEM FOR INDIAN 323
NATIONAL HIGHWAY NETWORK
9.00
8.00
Average Roughness Value
7.00
6.00 M&R-2003
(m/km IRI)
M&R-2004
5.00
M&R-2005
4.00 M&R-2006
3.00
2.00
1.00
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
Year
The work carried out under this study may find numerous applications
for the purpose of maintenance management of various highway networks. Some
of the potential applications are outlined below:
9. CONCLUSIONS
The following conclusions have been drawn on the basis of this study:
The practice of pavement management is absolutely essential on the
part of highway agencies, especially in developing country like India,
because of paucity of available maintenance funds. But the process of
development of PMS need to made simpler so that the field engineers
may be able to understand and utilize it effectively.
Internationally recognised HDM-4 system has been used for the
development of pavement management programmes for the National
Highway network in the country.
The pavement deterioration models incorporated into HDM-4 have
been calibrated using the pavement condition data collected on the
pavement sections and calibration factors for various deterioration
models such as cracking, ravelling, potholing and roughness models
have been obtained.
The validity of these models has been checked to test the efficacy of
these models, by comparing the distress predictions made by the
calibrated deterioration models with those actually observed on the
selected pavement sections.
The R 2 values obtained for cracking progression (0.98), ravelling
progression (0.79), and roughness progression (0.97) model show very
good agreement between observed and predicted values. Therefore,
these models have been used for prediction of distresses and the
development maintenance management strategies for the highway
network
Under project level PMS analysis, the optimum M&R strategy for a
pavement section has been determined on the basis of highest NPV/
Cost ratio, amongst a number of pre-defined M&R strategies. Similarly,
an optimum improvement strategy for another pavement section has
been determined.
The remaining service life for a number of pavement sections has been
determined which varies from 1 to 3 years, indicating that
reconstruction on most of the pavement sections would be inevitable
in the near future, in the absence of any sound maintenance management
policy.
DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEM FOR INDIAN 325
NATIONAL HIGHWAY NETWORK
The adoption of condition responsive maintenance strategies in
comparison with the scheduled type of maintenance strategies indicate
a saving of more than 33 per cent in highway agency costs over an
analysis period of 20 years.
Under network level PMS analysis, an unconstrained works programme
has been prepared for a period of 10 years and the total budget
requirements for maintenance management of the whole highway
network at a pre-defined optimum serviceability level have been
determined, which comes out to be 1475.87 million Indian Rupees.
The budget requirements for maintaining the highway network at an
optimum serviceability level are almost 40 times more than those
required for maintaining it with only routine maintenance type of
activities.
Since the usual level of fund allocations for the maintenance
management of National Highways in India is of the order of 60 per
cent of the requirements only, therefore an optimized and prioritized
works programme has been prepared for 60 per cent budget availability.
The funds requirements for maintaining whole of the highway network
at the highest level of serviceability (Rs. 1871.8 million) is about 27
per cent more than those required for maintaining it at the optimum
level of serviceability. However, it would be possible to maintain the
same highway network at a medium level of serviceability at about 74
per cent of funds (Rs. 1089.1 million). But since the budget availability
is normally 60 per cent, it would just be possible to maintain this
highway network at the lowest level of serviceability.
The average roughness value of the highway network keep on
increasing with gradual reduction in budget levels, which in turn may
lead to very high road user cost values. The same is also true when the
maintenance activities are increasingly deferred beyond the year in
which they become due. Both these scenarios have a very detrimental
impact on the overall health of the highway network.
REFERENCES
1. Aggarwal, S., Jain S.S., and M. Parida (2002) A Critical Appraisal of Pavement
Management Systems Vol. 63 No.2, IRC Journal, Indian Roads Congress, New Delhi,
pp 327-403.
2. Bennet, C.R., and W.D.O. Paterson (2000) A Guide to Calibration and Adaptation,
HDM-4 Documentation Series, Volume-5, The World Road Association (PIARC), Paris,
France.
3. Chakrabarti, S., Rawat, M.S., and B. Mondal (1995) Highway Design and
Maintenance Standards Model (HDM): Calibration and Adaptation to Indian
Conditions IRC Journal, Vol. 56, No. 1, pp 75-101.
326 AGGARWAL, JAIN & PARIDA ON DEVELOPMENT OF PAVEMENT MANAGEMENT
SYSTEM FOR INDIAN NATIONAL HIGHWAY NETWORK
4. CRRI (1994) Pavement Performance Study on Existing Pavement Sections, Final
Report, Central Road Research Institute, New Delhi.
5. Dattatreya, J.K., Veeraragavan A., Murthy, K., and C.E.G. Justo, (1992) A Suggested
Simplified System for Pavement Maintenance Management of Road Network, IRC
Journal, Vol. 53, No. 2, pp 217-273.
6. Fwa, T.F., and K.C. Sinha (1986) Routine Maintenance and Pavement Performance,
ASCE Journal of Transportation Engineering, Vol. 112, No. 4, pp 329-344.
7. George K.P., and A. Rajashekhran (1995) Future Directions in Pavement
Management, Proceedings, ICORT-95, University of Roorkee, Roorkee, pp 437-447.
8. Haas, R.C.G., and W.R. Hudson (1978) Pavement Management System, McGraw-
Hill Book Company, New York, 1978
9. IRC: 81 (1997) Guidelines for Strengthening of Flexible Road Pavement using
Benkelman Beam Deflection Technique, Indian Roads Congress, New Delhi.
10. Jain S.S., and A.K. Gupta (1994) Development of Pavement Management System for
Indian Highway Network, Final Report of the R&D Project, Submitted to AICTE,
New Delhi by COTE, Department of Civil Engineering, UOR, Roorkee.
11. Jain, S.S., Gupta, A.K., Khanna, S.K., and E. Safa (1994) Development and
Application of Deterioration Models for Maintenance Management of Flexible
Pavements, An Invited Paper Published in the Proceedings of the Conference on Traffic
Safety of Two Continents and Strategic Highway Research Program (SHRP), Hague,
Netherlands.
12. Jain, S.S., Gupta, A.K., and S.K. Khanna (1996) Development of Maintenance and
Rehabilitation Investment Strategy for Flexible Pavements, IRC Journal, Vol. 57, No.
2, pp 367-418.
13. Jain, S.S., Parida, M., and M.M.S. Rawat (1999) A Rational Approach for Pavement
Management System for Urban Roads Highway Research Bulletin, IRC, No. 61, pp
69-99.
14. Kadyali, L.R. (1992) Study for Updating Road User Cost Data, L.R. Kadyali and
Associates, New Delhi.
15. Kennedy, C.K., Young, A.E., and I.C. Butler (1990) Measurement of Skidding
Resistance and Surface Texture and the Use of Results in the United Kingdom, Surface
Characteristics of Roadways: International Research and Technologies, ASTM STP
1031, American Society for Testing and Materials, Philadelphia, pp 87-102.
16. Kerali, H.R., McMullen, D., and J.B. Odoki (2000) HDM-4 Applications Guide,
HDM-4 Documentation Series, Volume-2, The World Road Association (PIARC), Paris,
France.
17. MORT&H (2001a) Report of the Committee on Norms for Maintenance of Roads in
India, Ministry of Road Transport & Highways, Government of India, New Delhi.
18. MORT&H (2001b) Road Development Plan Vision: 2021, Ministry of Road Transport
& Highways, Government of India, New Delhi.
19. MORT&H (2001c) Updation of Road User Cost Data, Final Report prepared by
Central Road Research Institute for Ministry of Road Transport & Highways,
Government of India, New Delhi.
20. Sharma, S.C. (1995) Recent PMS Studies in India, Indian Highways, May, 1995,
Indian Roads Congress, pp 21-29.
21. Snaith, M.S. (2002) Pavement Management, Presentation made at 62nd Annual
Session of the Indian Roads Congress, Kochi, India.