Tanggal Deskripsi Location

2-Feb-17 Contruction survey KP. 135+800 - 137+100


3-Feb-17 Contruction survey KP. 135+700 - 137+000

4-Feb-17 Contruction survey KP. 136+100-136+500

Contruction survey KP 135+500-138+500

5-Feb-17
ROW Clearing, Cut & Fill, and Grading KP.135+700-138+100

Access Road KP.135+700-138+100

Contruction survey KP. 138+100-141+000


6-Feb-17
ROW Clearing, Cut & Fill, and Grading KP. 137+700 - 138+100
Access Road KP. 137+700 - 138+100

Contruction survey KP. 138+100-139+500


7-Feb-17
ROW Clearing, Cut & Fill, and Grading KP.137+400-137+700
Access Road KP.137+400-137+700

1
Contruction survey KP. 138+100-141+000
8-Feb-17
ROW Clearing, Cut & Fill, and Grading KP.137+400-137+700
Access Road KP.137+400-137+700

KP. 141+000-141+500
Contruction survey
9-Feb-17 KP. 136+100 - 136+600
ROW Clearing, Cut & Fill, and Grading KP.135+800-135+900
Access Road KP.135+800-135+900
Contruction survey KP. 136+600 - 136+800

10-Feb-17 ROW Clearing, Cut & Fill, and Grading KP.135+500-135+600

Access Road KP.135+500-135+600


Contruction survey KP. 136+800 - 136+900
Loading Pipa KP. 135+500 - 135+700
11-Feb-17
ROW Clearing, Cut & Fill, and Grading KP. 135+600-135+700

Access Road KP. 135+600-135+700


Contruction survey KP. 136+900 - 137+000
Loading Pipa KP. 135+500 - 135+700
12-Feb-17
ROW Clearing, Cut & Fill, and Grading KP.135+700-135+800
12-Feb-17

Access Road KP.135+700-135+800


Contruction survey KP. 136+900 - 137+000

Loading Pipa KP. 135+500 - 135+700


13-Feb-17
ROW Clearing, Cut & Fill, and Grading KP. 135+800-135+900

Access Road KP. 135+800-135+900


Contruction survey KP. 136+900 - 137+000
Loading Pipa KP. 135+500 - 135+700
14-Feb-17
ROW Clearing, Cut & Fill, and Grading KP. 135+900-136+000

Access Road KP. 135+900-136+000


Contruction survey KP. 136+900 - 137+000
15-Feb-17 Loading Pipa KP. 135+500 - 135+700

ROW Clearing, Cut & Fill, and Grading KP. 136+000-136+100


Contruction survey KP. 136+900 - 137+000
16-Feb-17 Loading Pipa KP. 135+500 - 135+700

ROW Clearing, Cut & Fill, and Grading KP. 136+000-136+100

2
Contruction survey KP. 136+900 - 137+000
17-Feb-17 Loading Pipa KP. 135+500 - 135+700

ROW Clearing, Cut & Fill, and Grading KP. 136+000-136+100


Contruction survey KP. 136+900 - 137+000
18-Feb-17 Loading Pipa KP. 135+500 - 135+700

Stringing KP. 135+800 - 135+900


Loading Pipa KP. 135+500 - 135+700
19-Feb-17
Stringing KP. 135+900 - 136+050
Loading Pipa KP. 135+500 - 135+700
20-Feb-17
Stringing KP. 136+000 - 136+100
Loading Pipa KP. 135+500 - 135+700
21-Feb-17
Stringing KP. 136+000 - 136+100

Loading Pipa KP. 135+500 - 135+700


22-Feb-17

Stringing KP. 136+100 - 136+200

Loading Pipa KP. 135+500 - 135+700

23-Feb-17
Welding Preparation KP. 136+000
23-Feb-17
Welding Preparation KP. 136+000

Loading Pipa KP. 135+500 - 135+700

24-Feb-17
Welding Preparation KP. 136+000

Loading Pipa KP. 135+500 - 135+700

Stringing
25-Feb-17

Welding KP. 136+000

Loading Pipa KP. 135+500 - 135+700


26-Feb-17
Stringing
Welding KP. 136+000

Loading Pipa KP. 135+500 - 135+700

27-Feb-17
Stringing

Welding KP. 136+000

3
Kegiatan
Memberi patok dan memberi As Pipe
Memberi patok dan memberi As Pipe
Memberi patok dan memberi As Pipe
Test Pit
Memberi patok dan memberi As Pipe
Test Pit
Excavator Hitachi Masuk Site
Clearing ROW
Clearing ROW
Memberi patok dan memberi As Pipe
Test Pit
Clearing ROW
Clearing ROW
Memberi patok dan memberi As Pipe
Test Pit
Clearing ROW
Clearing ROW

4
Memberi patok dan memberi As Pipe
Test Pit
Clearing ROW
Clearing ROW
Memberi patok dan memberi As Pipe
Test Pit
Galian manual
Clearing ROW
Clearing ROW
Galian manual
Excavator Caterpilar masuk site
Clearing ROW
Tronton Masuk Site
Loading pipa
Clearing ROW
Galian manual
Loading pipa
Hauling pipa
Clearing ROW
Membuat bundwall
Clearing ROW
Galian manual
Loading pipa
Hauling pipa
Clearing ROW
Membuat bundwall
Clearing ROW
Galian manual
Loading pipa
Hauling pipa
Clearing ROW
Membuat bundwall
Clearing ROW
Galian manual
Loading pipa
Hauling pipa
Clearing ROW
Membuat bundwall
Clearing ROW
Galian manual
Loading pipa
Hauling pipa
Membuat bundwall
Galian manual
Loading pipa
Hauling pipa
Membuat bundwall

5
Galian manual
Loading pipa
Hauling pipa
Membuat bundwall
Galian manual
Loading pipa
Hauling pipa
Stringing pipa
Loading pipa
Hauling pipa
Stringing pipa
Loading pipa
Hauling pipa
Stringing pipa
Loading pipa
Hauling pipa
Stringing pipa
Tambahan Tronton
Loading pipa
Hauling pipa
Stringing pipa
Tambahan Excavator Kobelco
Loading pipa
Hauling pipa
Fit Up
Safety Induction welder
Prepare material & equipment welding test
Loading pipa
Hauling pipa
Fit Up
Mesin las 4 buah
Prepare material & equipment welding test
Loading pipa
Hauling pipa
Stringing pipa digeser ke KM. 81+980
Welding test Production
2 Joint production + NDT
Brushing & Grinding
Loading pipa
Hauling pipa
Stringing pipa digeser ke KM. 81+500
Menunggu hasil tes production
Loading pipa
Hauling pipa
Stringing pipa digeser ke KM. 81+500
Membuat bundwall

6
Welding preparation
7
8
9
M1 M2 M3 M4 M5 M6 M7 M8
No. Deskripsi Quantity Rekap Progress
2-Feb-17 3-Feb-17 4-Feb-17 5-Feb-17 6-Feb-17 7-Feb-17 8-Feb-17 9-Feb-17 10-Feb-17 11-Feb-17 12-Feb-17 13-Feb-17 14-Feb-17 15-Feb-17 16-Feb-17 17-Feb-17 18-Feb-17 19-Feb-17 20-Feb-17 21-Feb-17 22-Feb-17 23-Feb-17 24-Feb-17 25-Feb-17 26-Feb-17 27-Feb-17 28-Feb-17 1-Mar-17 2-Mar-17 3-Mar-17 4-Mar-17 5-Mar-17 6-Mar-17 7-Mar-17 8-Mar-17 9-Mar-17 10-Mar-17 11-Mar-17 12-Mar-17 13-Mar-17 14-Mar-17 15-Mar-17 16-Mar-17 17-Mar-17 18-Mar-17 19-Mar-17 20-Mar-17 21-Mar-17 22-Mar-17 23-Mar-17 24-Mar-17 25-Mar-17 26-Mar-17 27-Mar-17 28-Mar-17 29-Mar-17 30-Mar-17 31-Mar-17
Contract Signed 1 100% 1 1
Work Preparation
Mobilisasi Equipment & Manpower
1.1 Equipment 21 105% 22 1 2 2 4 1 2 4 1 5
1.2 Manpower 90 61% 55 17 2 16 2 4 14
Temporary Facilities 2 100% 2 1 1
Project Management 7 100% 7 4 1 1 1
QA/QC Programs
4.1 Welder Test / Production Test 18 100% 18 4 14
4.2 Coating Test 6 0% 0
4.3 NDT Personel & Qualification (NA) 6 0% 0

Procurement & Material Supply 1 0%

Site Instalation
Construction Survey 14300 32% 4600 1100 1300 400 400 400 600 400
ROW Clearing, Cut & Fill, Grading 14300 23% 3300 50 650 650 650 800 400 100
14300 20% 2800
Acces Road 50 650 650 650 800
Stringing Include Pipe Transportation from Stock Yard to
Stringing Area 14300 17% 2376 Hauling
108 108 96 108 108 84 36 108 36 84 72 84 84 108 96 96 72 72 72 48 48 48 48 24 72 108 120 168 12 48
Tranching 14300 0% 0
Welding C/w tie-in 1192 8% 99 2 2 3 3 4 6 4 5 2 5 5 4 7 7 11 10 10 9
Holiday - test 1192 0% 0
SDV Installation 1192 0% 0
Joint Coating 1192 0% 0
Lowering 14300 0% 0
Backfilling 14300 0% 0
1788
HSE
HSE Program
1.1 Equipment Inspection 1 75% 0.75 0.75
1.2 Safety Induction 1 80% 0.8 0.8
1.3 Measurement of Safety Performance (HSE Report) 1 0% 0
1.4 APD & Tools 1 25% 0.25 0.25

Closing
Demobilisasi Equipment & Manpower
1.1 Equipment 21 0 0
1.2 Manpower 60 0 0
Re-instatement 14300 0 0