Professional Documents
Culture Documents
EDUCATIONREVITALISATIONPROJECTPHASEII
NATIONALDIPLOMAIN
BUILDINGTECHNOLOGY
SITEMANAGEMENTII
COURSECODE:BLD210
YEAR2SEMESTERII
THEORY
Version1:December2008
i
SITEMANAGEMENTII
TABLEOFCONTENTS
WEEK1 SITEMANAGEMENT
(1.1) Organisation
WEEK2 PRINCIPALCHARACTERISTICSOFLARGEMEDIUMANDSMALLCONSTRUCTION
COMPANIES
(1.1) SmallConstructionCompanies
WEEK3 MAKINGTHERIGHTDECISIONS
(2.1) DecisionMaking
WEEK4 MAKINGTHERIGHTDECISION(CONTD)
(2.1) Decisionsunderconditionsofuncertainty
WEEK5 MAKINGTHERIGHTDECISIONS(CONTD)
(2.1) TheNeedforDecisionsonProjects
WEEK6 COMMUNICATION
(3.1) DefinitionsandProcessesofCommunication
WEEK7 COMMUNICATION(CONTD)
(3.1) WrittenFormsofCommunication
WEEK8 COMMUNICATION(CONTD)
(3.1) CommunicationSkills
WEEK9 THEPROCESSOFMANAGEMENT
(1.1;4.1)BackgroundtoPlanningControl
WEEK10 THEPLANNINGPROCESS
(4.2) PlanningProceduresintheConstructionIndustry
WEEK11 THEPLANNINGPROCESS(CONTD)
(4.2) PlanningTechniques
WEEK12 THEPLANNINGPROCESS(CONTD)
(4.2) TypesofProgrammes
WEEK13 THEPLANNINGPROCESS(CONTD)
(4.2) TypesofProgrammes(contd)
ii
WEEK14 WORKSTUDY
(5.1) MeaningofWorkStudyandAssociatedTerms
WEEK15 WORKSTUDY(CONTD)
(5.2) BenefitsofWorkStudy
iii
WEEK 1: SITE MANAGEMENT
(1.1) Organisation
To meet the growing demand for accurate and competitive tendering which is the main
method of obtaining work in the building industry, and to the satisfactory completion
of projects, organisation must be the key word. This is done in many and varied ways,
but all have one thing in common: the breaking down of the whole organisation into
groups, sections or departments each of which would have certain given tasks or
objectives, as laid down in the objectives and policy of the firm. This is called an
organisational structure. Each section will have a leader who must ensure that the work
This organisational structure is on formal lines and must be if the objectives are to be
carried out. Each sections objectives must be clearly defined in writing so that actions
and decisions can be laid at the correct door quickly, enabling answers to be given in a
short space of time, when they will be most effective. This can only lead to a better
performance of all round and reduce the feeling of frustration that can arise through
will develop between the members of the organisation at all levels. This must be
allowed to thrive so that a happy team spirit is built up with all the worthwhile benefits
to the individual and the company as a whole that this will bring as long as the formal
iv
generally will take a shallow or deep form and resemble pyramids when laid down in
v
Typical Types of Organisational Structure or Patterns
There are several different types of organisation structures, the commonest are:-
1) Shallow Structure
Maximum of 25 operatives
Its advantage is that it makes communication easier from top to operatives as there are no
officers between. While its disadvantage is that it makes the organisation very vulnerable, as
vi
2) Deep or Military Structure:
Used when bigger set up working to much finer limits is desirable, requiring more departments
.
manager
Supervisors
GeneralForemen
O P E R A T I V E S
This is a combination of shallow and deep military structure. It combines most of the advantages
vii
Planningdepartment Safetyandtrainingoffice
Plantmanager
Surveyor
Buyer
Engineer
Transport
Agent
joiner Bonussurveyor
Span of Control
Within the limit of an organisation, the groups, section or department will be ruled and guided by
a leader who will have the responsibility of ensuring that his section carries out it objectives to a
final satisfactory conclusion with a greater number of person and under once control efficiency
viii
c. Unofficial sub-groups forming within the main group;
In normal circumstances, between five and seven is the maximum number of persons to
b. The speed in which decision most be made and there are importance
d. The leader himself considering the load he has to carry in relation to his character and the
stability.
In any organisation structure or span of control certain relationships exist . These are expressed
as;
a. Lateral relationship; persons being on equal footing, e.g. two general foremen.
b. Direct relationships: one person able to give an instruction or order that must be
ix
Self Assessment Questions.
Q5. State five factors that can affect control efficiency within an organisation
x
WEEK 2: PRINCIPAL CHARACTERISTICS OF LARGE, MEDIUM AND
SMALL CONSTRUCTION COMPANIES
xi
Medium Sized Firm
Medium size contractor usually employs between 26 and 300 staff, and operatives and often
have an organisational structure which does not incorporate a planning department (see fig 2.2).
The planning function is usually undertaken by the contract directors or contract manager. Here
again, the bar chart form of presentation is widely adopted as it is already understood at site
management level and acceptable to the client.
Typical work undertaken by a medium sized firm includes housing modernisation work,
industrial development work etc. One-off office type development can readily be planned, again
using bar-chart. The company has a small work division and sometimes is active in speculative
housing section.
xii
Chairman
Managing director
Financial director Small works Estimating buying Surveying director Sales directors
directors director
Responsibilitiesfor:
Preparationofmasterprogramme;in
Linisonwithcontractscontractmanager;
financialcontroldirectorofproject;linison
witharchitectsoverallprojectcontrol
Contract manager
Responsibilities for:
Assisting contracts directors with preparation of master
programme; in Licison resources between sites, attendance at
monthly site meetings; monthly reports.
Responsibilities for:
Short term planning on site, coordination of S It
S i t e e
MM a naa n
g ear ger
labour, and resources subcontractors; linison
with buying department, material control
weekly site planning meeting and progress
reports /site diary.
xiii
Large Construction Firms
They usually employ above 500 staff and operatives, undertaking complex multi-million
naira projects with a large array of plants and equipment(see fig 2.3).
The planning techniques adopted by the company depends upon the techniques which
best suits its planning needs. A contractor undertaking work involving speculative and
local authority housing projects may adopt the line of balance techniques may be adopted
for complex one off type projects while less complex may be planned using bar charts.
They often have adequate provision for in services training courses to keep site
management aware of planning and construction development. The introduction of
computers make networks techniques a more viable planning proposition both as a head
office and site planning took. Most forms of planning tools are now used in computer
software form.
xiv
Fig 2.3 Large Sized Firm
Chairman
Managingdirector
Contracts Director
Contract Director
Contract Director
Planning engineers/ production contract directors are allocated to major projects to provide site
based planning services to site Construction managers.
xv
Self Assessment Questions
Q1. State three types of construction companies.
xvi
WEEK 3: MAKING THE RIGHT DECISIONS
Whatever policy is laid down, it must be the result of deliberation and discussion. Hence the
making of right decisions is fundamental to good management practice.
The decision maker. Although policy emanate from the board of directors they may originate
from any level of management in the form of recommendations upward to the board. Such
policy decisions are usually actions , that are the responsibility of management at the point of
impact. Thus the managing director, or other top executive, lays down guide lines for others
to follow, in harmony with the objectives and board policy generally.
At top management level the decisions to be taken are not usually numerous, but they may be
far-reaching in effect and costly if based on an error of judgment. Problems arising at lower
levels can be dealt with as and when they occur, provided that they are within the
discretionary limits of responsibility and authority of those concerned.
Problems of a wider nature are passed upwards for decisions within the more extensive
mandates of line management above. Thus there may be a series of filters with the mesh
progressively narrowing as problems pass though for higher decisions. Those which survive
to the top are clearly of special importance or difficulty. At that level the critical factor is to
determine the points of principles involved. If they are within the framework of the
objectives and board policy, a firm decisions can be made and communicated. Should new
policy be invoked, however, then the matters concerned may need a special report, with
appropriate recommendation, and a place on an early board agenda.
The decisions maker may be a single individual, but often enough there is added value in
consultation, perhaps trying it on the dog first; and even using the collective wisdom of a
formal or informal committee. In this context it is important to have regard to the personality
and temperament of the decision-maker. Is he, for instances, an incurable optimist or a
cautious pessimist? Does he still prefer hunch to scientific method? Do his decisions suffer
from inconsistency? It is here that, despite the usual arguments against committee decisions,
there is a chance of levelling out any undue bias.
xvii
In every company there are a number of important issues that requires the attention of top
management, in this context the board of directors. There are the fundamental policies that
emerge from the basic objectives, which can be conveniently divided up into:
a. Marketing and policies
b. Production policies
c. Financial policies
d. Personnel polices.
Policies decision as laid down in statement form set out the standing answers to each of the
main questions likely to be raised, so that all staff concerned are able to know exactly what is
expected of them in any normal set of circumstances. Situations that arise regularly can be
dealt with automatically by references tot he standard rules made in advance. This ensures
that all action taken will be in accordance with the wishes of the board and a step nearer
attaining the desired objectives.
The laying down of basic policy clearly helps to achieve uniformity of action throughout the
company and consistency from one event to another. Furthermore, it helps with delegations,
as subordinates reasonably expected to know the rules, which helps co-ordination.
These rules can be put in writing as manuals of procedure, office instructions and
memoranda, provided that adequate provision is made for them to be kept up to data and to
be flexible enough to cope with special or local circumstances. There may even be unwritten
rules well appreciated and observed by all concerned. The important factor is that all policy
decisions should be understood throughout the organisation as a vital part of its existence and
as a means of achieving consistency in action.
Some policy decisions, of course have to be made to deal with exceptional circumstances or
emergencies, and these require special treatment as described later.
xviii
WEEK 4: DECISION MAKING (CONTD)
In the previous section consideration was given to making the right decisions but more
often than not decision have to be based on imperfect knowledge. Although analytical
skill can be developed, and the chances of success strengthened, it is seldom possible to
obtain all the information one would like to have. There are many types of decision, but
at least those having a long time span and therefore looking well into the future have to
be made under conditions of uncertainty.
Quite apart from the dynamic environment and the problems of forecasting, it is difficulty
to know, for example, what competitors are planning to do in the same basic situation.
Despite industrial espionage and the poaching of informed executives, it can still be
possible for several boards of directors to be meeting at virtually the same time, each
arriving at similar policy decisions likely to make a significant impact on the others. This
kind of situation can, to some extent, be offset by top management representative or,
more formally, through a relevant trade association. Even so, there are still likely to be
key policy decisions which remain closely guarded for as long as possible, if only in the
interest of cooperate survival.
Probability techniques
xix
Operational research
Statistical analysis
Queuing theory
Linear programming
Simulation
Stock control systems
Decision tree theory
Sensitivity analysis etc
.
Self Assessment Questions
Q1. What makes taking decision difficult?
Q2. Briefly discuss how decisions are made in an atmosphere of uncertainty.
Q3. State any five tools used for decision making in an uncertain condition.
xx
WEEK 5: DECISION MAKING (CONTD)
Before tendering for projects there is a need for the firm to take a critical look at a
number of things before bidding:
It will be necessary to see if the company resources can match the works load required
bearing in mind the amount of work load already committed to.
One must also consider the project in relation to the location of the project and other
restrictions such as access to site, nature of the site, setting out, temporary offices for
employers, time require for project, order of works, sectional completion, liquidates and
ascertained damages, retention fee, form of payment and site security.
The amount of work that can be handled by the firm and the amount that will have to be
sublet to sub contractors must be determined.
The current work load in the estimating department and how well they can cope with
new one to meet the time of submission must also be considered.
It will be useful to have knowledge of the competition also.
It is important to evaluate the values of currently accepted tenders within the year.
To evaluate the values of currently accepted tenders within the year.
Can the items descriptions be priced i.e. do they adequately describe the work involved.
Is any of the various contract documents contradictory?
It is also important to asses the amount of prime cost and provisional sums indicating the
number of nominated sub-contractors and how well the documents have been pre-
planned. Usually the prime cost (PC) sums are sums allowed for nominated sub-
contractors or suppliers.
It will be necessary to see if there are alterations or divisions or standard clauses or
supplementary clauses in the tender documents.
Also to asses the strength of plants and labour requirements
xxi
Finally one needs to consider if the company wishes to carryout work for the client or the
representatives.
xxii
WEEK 6: COMMUNICATION
Communication is the process of passing ideas and meanings (information) to members of the
It is as old as time itself-a relationship between sender and receiver-that elicits response from the
receiver. It is of vital importance in the controlling, co-ordinating and motivating of people. Just
understand, for errors can be costly. Communication in the building industry normally takes one
i. Oral instruction
Which ever method is adopted, certain considerations relate to all, they should be:
c. Definite: so that no doubt is left as what the message means; should not be changed
d. Situational communication should suit both the situation and the person receiving it.
Oral Instruction
These should be given (oral) in a manner that reflects efficiency and enthusiasm. The posture
should be upright but relaxed; the speech clear, calm, yet communicating. The verbal instructions
xxiii
should be given directly to the person concerned; otherwise the message could become distorted
with passing on. The face to face talk will generally have far more success than the written
word; it will also enable questions to be asked and queries rose without delay. It should always
be remembered that most people are prepared to be asked to do something rather than be ordered
to do something.
Written instruction
Written words come in many forms of communication found in the building industries such as:
a. Letters
b. Reports
c. Minutes of meetings
d. General documentation
xxiv
A.NANOTHERLIMITED
MEMO
From............................................. To................................
Date..............................
Subject.......................................
Message..................................................................message................................
Message......................................................message..........................................
Signatureofsender
A.NANOTHERLIMITED
BUILDINGCONTRACTOR
1762BLOCKROAD,
KAWOKADUNA
Telephone:062078596
Ourref:oj/56/08 date:080808
Yourref:kb/52/08
Address:jkblockltd,
Buildermerchantaliu
Akiluroad,
Kaduna.
Dearsir,
Order1672/08
Withreferencetotheaboveorder,wehavetoadviceyouthatfourof
theplasticlightfittingwerefoundtobebrokenuponreceiptofthe
orderat31July2008.
Weshallbepleasedifyouwillreplacetheseassoonaspossible.
Yoursfaithfully
Isahkan
xxvi
General Considerations When Writing Letters.
Letters should be on firms headed paper giving full name, address and telephone
number.
a. Dear Sir (so) or Madam (strictly business) always end up with yours faithfully.
b. Dear Mr. Aboki - (less formal) always ends up with yours sincerely.
i. Body of letter: if of a business nature should be short and to the point care been taken
ii. Complimentary clause: toward the lower right hand side f sheet should be
xxvii
a. Yours faithfully coder as per salutation
b. Yours truly
iii. Signature and designation: person sending letters signs names, typed, with position
Q3. Using a memo write an instruction to a site agent of a building project on any subject of your
choice.
xxviii
WEEK 7: COMMUNICATION (CONTD)
Notice Boards
A usefully means of conveying information if placed in a prominent position where every one
can see.
Copies of such items are as the constructions regulation, building regulations, the working rule
agreement should be kept in a site in a position where they can be reached easily for point
reference.
Site Records
There are many site records which have to be made out each week regarding labour plant and
materials. It is important to remember that this document have a specific use and must therefore
always be filled in actually and when required, whether daily, weekly or monthly.
These are often proved to be the most useful document if well kept, with right type of
information recorded on it, its values in matters of disputes in the project can not be over
emphasised. The main one objective of the site diary should be record of event and information
that do not warrant special record been kept. As a general rule, items which might be well
xxix
Telephone promises from sub contractors and suppliers, etc.
Delays in program due to late delivery of materials, late start of sub contractors, etc.
For effective construction management and to enable supervisors and operatives carry out their
Information that will help in operations- only information which would help
Construction methods, situations, site layout alterations where such changes are
Clearly defined roles, duties and obligations; do not leave workers guessing as to
what their roles, duties and obligations are. They should clearly know their roles and
xxx
Keeping staff abreast of trends in the construction industry. This can be done through
job training.
REPORTS
These are used to relate information to some one back to some, such as investigation, something
witnessed or subjected ideas, the main object of a report should be to disclose facts for
be avoided, but care must be taken to ensure readers fully understand what the report is meant to
convey.
i. Heading
iii. The body of report used of sub-hierarchy and dividing information into section should
xxxi
Self Assessment Questions
xxxii
WEEK 8: COMMUNICATION (CONTD)
How to communicate
Timing it is essential that communication be done at the most auspicious time. It should do
the firm no good to pass on information long after such information may have been necessary for
the successful undertaking of a task. Such delay could lead to serious mistakes in construction
process or construction delays on site.
It would equally be bad if an information is set so early that when the time for its application
arrives every one would have long forgotten such communication ever took place. Good timing
is therefore crucial in communication.
Clarity Experts list seven essentials for clear communication which are candid, clear,
complete, concise, correct, courteous and concrete.
Listening-you may not appreciate the value of listening until you try taking to someone who
would just not listed. To be able to listen well, you need to; stop talking, remove distractions, be
patient, ask questions and show sympathy.
Barriers to Communication
There are three basic types of stumbling blocks that usually mar our best efforts in
communication.
Semantic barriers- languages often constitutes a problems in communication especially
where people differs in tongue. Even where both parties speak the same language, the levels of
perception and proficiency may vary widely and thus, create barriers. Some words have more
than one meaning and for good communication each word must have clearly understood
meaning to all parties involved.
Psychological barriers- some people listening without hearing and look without seeing.
Indeed many a manager ends up hearing what he expects to hear. Where there is lack of trust it
becomes difficult for managers to do open in communication with the suspect staff. When
employed believers or perceive their manager as being understanding, they tend to be more frank
and open with him.
xxxiii
Technical barriers relates to problems of timing information overload, short circulating
and cultural differences
SITE RELATIONS
All instructions should be in writing. Where they are oral seek confirmation in writing.
Be sure to explain your position clearly to all parties. This happens best if you are
Mark out clearly whom among your staff show issue or receive instructions.
Investigate the cause of poor work early. Dont wait until a wall has been completed
xxxiv
WEEK 9: THE PROCESS OF MANAGEMENT
Management is achieving stated objectives usually to produce goods and services by using
Planning;
Organising;
Staffing;
Leading;
Controlling.
These functions are carried out sequentially in a given set up for management to be said to be
performing its functions. The process of production which is why management is undertaken is
to produce goods or provide services. These are achieved using resources by management. These
resources are made up of men, materials, machines, and money. They are sometimes referred to
xxxv
Fig 9.1 Production Process
xxxvi
Planning This is a predetermined course of action. It is a detailed method, formulated
beforehand, for doing or making something. Planning is deciding in advance what to do,
when to do it, and how do it (production). Planning aim is to lay down the direction in
which a move is made proving, taking into account the resources that are available.
Nothing can result without a plan in any form of production, as activities will not be
related and persons will go their own ways the result, chooses and disorder. Any plan
produced can only be a guess as to what is likely to happen, but by the use and collection
of all relevant information and its critical examination, this guess becomes much more
calculated one, with a high degree of accuracy and foresight of problems and possible
delays. Above all it will enable set standard to be allied down which will produce a
control system.
Policies
Strategies
Rules
Programmes
Budgets
Objectives
Missions
Purposes (aims)
Policy planning: Any organisation must look ahead to the future to assess trends, markets
and finances, this is generally the task of top management, the principal, board of directors, or in
xxxvii
some cases, a committee. This activity is termed policy planning and in most cases the success of
The policy of a company should be laid down in writing and should cover the following topics:
b. Financial structure
c. Time scale
e. Purchases
f. Organisation.
Planning for a construction work by the contractor is carried out in the three phases of the project
Pre-tender planning;
Pre-contract planning;
Construction planning.
Fig 9.2 shows the types of planning undertaken by the contractor in the execution of a building
project.
xxxviii
Fig 9.2 Types of Planning by the Contractor in a Given Project.
Q6. Using neat diagram explain the different types planning undertaken by a the
xxxix
WEEK 10: THE PLANNING PROCESS (CONTD)
Pre-tender planning: much of the builders work is obtained through the process of tender
and if a builder is to stay in business his estimates have to be competitive and a good percentage
of them successful. All facts that are collected should be processed and critically examined for
this objective to be achieved. Therefore the procedure of pre tender planning needs to be
planned so that a systematic approach can be made to ensure that all information and facts are
gathered on time.
The various activities carried during pre tender planning are as follows:-
Method statement
Plant schedule
Outline programmes.
Pre-tender Report:
xl
I] SITE:
Trespass precautions
Police regulations
Concealed services
Photographs
Types of soil
Stability
Sources of water
Pumping
Disposal of water
xli
Pumping
Disposal of water
Telephone
TV
IV] LABOUR
Availability
V] TIPPING FACILITIES
xlii
Method statement
Basically this indicates how the project is to be built, what plant is to be used and so on. Each
stage of the operation is studied to find the best method of completing, carefully weighing
Plant schedule
This is carried out on the completion of method statement and is a detailed summary of all the
plant and equipment required to build a project, giving as much relevant detail as possible, such
as number and type of plant required and in number of weeks required (also availability whether
It is of great importance in this pre tender stages that a full list of required sub- contractors and
suppliers is drawn up it would then become necessary to send out an inquiry form not only to
obtain quotations but to ascertain whether or not the sub-contractors can be available on dates
required and can complete in whatever time has been roughly allocated on the pre-tender
programme. Enquires must be sent out to suppliers in much the same manner as sub
contractors out with consideration as to delivery date. Prices at this stage must also be taken into
account to ensure that supplies can be maintained regarding quantity and quality.
Outline programme
This should be produced as soon as possible from estimated information. This is not a detailed
plan but outlines the main operation and sub contractors work. The plan will enable all parties
xliii
concerned in the pre-tender preparations to co-ordinate their activities and to assess time required
for plants use, use of site huts and supervisors durations on site.
Estimate
With all the information now available in the estimator can begin to allocate prices to items in
the bill of quantity (BOQ), estimating not only the direct cost but also the indirect cost. Upon the
completion of estimate, the estimator will present the persons concerned, with finalizing the
tender with a summary of the estimate with cost, enabling them to give approval or otherwise.
After the final completion and vetting of the estimate a figure is agreed and submitted. The
Q1. List the various activities that are carried out during the pre tender planning.
Q2. Write out the items that the general description of site will carry in a site investigation
report.
Q3. What are the services to be reported on when writing a pre tender report?
a) Method Statement;
b) Plant Schedule.
xliv
WEEK 11: THE PLANNING PROCESS (contd)
It is suggested that reference to Programme in construction contract will require at least the
basic information of a list of verbal descriptions of activities or operations together with a list of
dates for commencement and completion of each activity. The extent of the list of activities will
depend upon the contract description of the programme.
Standard Forms of contract do not adopt a common approach to the description of programmes,
the role of the programme in the administration of the contract and the obligations and rights as
to programme. It is suggested that in the absence of a detailed description of the form and
content of the programme, it is necessary to identify the intended role of the programme in the
contract, in order to decide the type of programme required by the contract. This aspect is dealt
with in the Article The Role of the Programme. The obligations of the parties as to programme
is dealt with in the Article Obligations as to Programme.
A variety of programme techniques are available for use in the execution of building projects.
Among them are the following:-
Bar Chart(Gantt Chart);
Critical Path Method(CPM);
Precedence Network Diagram;
PERT;
Line of Balance, etc.
It should be remembered that the precise form in which construction programme is drawn either
manually or by computer will depend to some extent on the experience of the Builder, the
requirements contained in the conditions of contract and the National Building Code (in the case
of Nigeria).It is now desirable to prepare building programmes using computers in the execution
of building projects. The most common type of technique employed is the bar chart.
xlv
Bar Chart or Gantt Chart
Kempners (1980) recognise that Henry Gantt first introduce bar charts in the early 1900s by
popularising the graphical presentations of work versus, time. Each operation is represented by a
block or bar drawn to a time scale. Bar charts are well suited to depicting construction sequence,
and are readily understood at all levels of management and are the most commonly used method
by small and sized construction firms. Development in project management computers software
has led to electronic bar charts relation s used on bar charts being used.
Fig 11.1 below shows an example of a bar chart programme.
The bar chart is a two dimensional chart. The x-axis of the chart shows the project timeline. The
y-axis of the chart is a list of specific activities that must be accomplished to complete the
project. These activities are typically listed in order of earliest start on the project. The content of
the bar chart are bars that show the planned (and/or actual) start and end times for each task.
Since the tasks are usually arranged from earliest to latest, most bar charts show a pattern of bars
that begin in the upper left of the chart and proceed to bars that complete the project displayed in
the bottom right of the chart.
For the activities, duration, and sequence shown in the table below, the related bar chart is
shown.
xlvi
Table11.1ACTIVITESTABLE
Duration
Activity Prior Activity
(work-weeks)
1 3 None
2 5 1
3 2 2
4 3 1
5 2 4
xlvii
5) Print the activity name above each bar, if possible.
xlviii
WEEK 12: THE PLANNING PROCESS (CONTD)
Below are the different types of programmes that a contractor has to produce in the execution of
a building contract:-
A) Pre-tender Programme (Preliminary)-this is one of the activities that are performed
by the building contractor during the pre tender planning stage of the project as is shown on
Figure 12.1 below
Figure 12.1 Pre Tender Programme
B) The Master Programme- is the programme prepared by the main contractor for the
actual execution of the building work.Figures 12.2 and 12.3 below shows typical examples of
master programmes of building projects.
xlix
Figure 12.2 Typical Master Programme
Q1. Using a typical simple building project , prepare its preliminary and master programme.
Q2.Obbtain a preliminary and master programme of a typical project and try to read and
interpret them.
Q3. Prepare the resources schedules for Q2.
li
WEEK 13: THE PLANNING PROCESS ( CONTD )
down further into Six weekly (see Figure 13.1); Weekly (see Figure 13.2); and Daily(see
Figure 13.3) programmes to allow for finer planning and facilitate effective control on the
lii
Figure 13.1 Six Weekly Programme
liii
liv
Using a typical master programme draw a six weekly programme from the it and extract the
weekly programme and subsequently the daily programme.
lv
WEEK 14: WORK STUDY
The terms work study is defined in British standard 31.38:1969 glossary of term used in work
study as;
A management service based on those techniques, particularly method study and work
measurement, which are used in the examination of human work in all its context, and which
lead to the systematic investigation of all the resources and factors which affects the
efficiency and economy of the situation being reviewed, in order to effect improvement.
As thus defined the phrase work study is used to associate two distinct yet completely
interdependent groups of techniques. These groups have been subtitled method study and
work measurement respectively, the techniques to which they refer are concerned on the one
hand with the way in which work is done, and on the other with the value or work content
of the task itself. The distinction, although convenient for instructional purpose, should be
carried no further, for while in practice individual specialist may be spend the majority of
their time in one or other field, from the point of view of an organisation as a whole major
portion of the benefits of works study will be lost if attempts are made to use either groups of
Method study is defined in British standard 31.38: 1969 as the systematic recording and
critical examination of the factors and resources involved in existing and proposed ways of
doing work, as a means of developing and applying easier and more effective methods and
reducing costs.
Work Measurement is the techniques used in the the investigation of human work with a
view of establishing the time it takes a qualified worker to perform a given task.
lvi
WORK STUDY
HIGHER PRODUCTIVITY
lvii
Q4. What do you understand by the term Work Measurement?
lviii
WEEK 15: WORK STUDY (CONTD)
The benefit result of work study in an organisation like the construction industry is shared
Better control
lix
Better working conditions
Less fatigue
a) the organisation;
b) the supervisor;
c) the operative.
lx